Rehabilitating a 105-inch Interceptor – Innovations and ... · Oakland system • Clearly define...

Preview:

Citation preview

Rehabilitating a 105-inch Interceptor – Innovations and

Lessons Learned

Pipe User Group | Northern California

March 13, 2018

Tim Karlstrand and Gary Warren

2

Agenda

• System Overview

• Project Need

• Video

• Lessons Learned

• Technology Evaluation

• Hydraulic Analysis

• Cost Savings

• Odor Management

• Reducing Community Impacts

• Phase 1 Lessons Learned

East Bay Municipal Utility District Overview

• EBMUD provides wastewater treatment for 680,000 of its 1.3 million water customers (“west of hills”)

• Wastewater is collected in large diameter interceptors from seven satellite communities – Alameda

– Albany

– Berkeley

– Emeryville

– Oakland

– Piedmont

– Stege Sanitary District

Wastewater Flow Range

•Wastewater flow from satellites (MGD = million gallons per day)

– Average annual flow = 50 MGD

– Peak wet weather = 415 MGD (at MWWTP)

– Peak wet weather = 700 MGD (system-wide)

– Primary treatment = 320 MGD (max)

– Secondary treatment = 168 MGD (max)

• Significant peaking factor is a key challenge

Wastewater Interceptor System

• EBMUD

– 29 miles of gravity interceptors

– 8 miles of force mains

– 15 pump stations

– MWWTP, plus 3 WWFs

• Satellites

– ~1,600 miles of regional collection system

– ~1,600 miles of private sewer laterals

6

Background Project Need • Corrosion of the South Interceptor is active and

rehabilitation is necessary

– Due to high levels of hydrogen sulfide

7

Background Capital Improvement Program

CIP Update Four Phases of 3rd Street

• Four phases of work over 8+ years

8

Project Segment Total Project

Cost 3rd St Rehab Phase 1* $9.0M

3rd St Rehab Phase 2 $24.9M

Special Structures Rehab $8.3M

Embarcadero Rehab $12.8M

Total $55.0M *3rd St Rehab Phase 1 construction estimate is $6.8M

9

Video

• California Association of Sanitation Agencies (CASA)

2017 award for Outstanding Capital Project https://casaweb.org/about-us/awards-program/

Phase 1 – 4 Project Scope

10

Phase 1

Phase 2

Phase 4 (Embarcadero)

*Phase 3 not shown (Special Structures)

11

Constraint Analysis

• Flow – Dry weather construction

– No pumped bypass (of interceptor flow)

– Tributary flow management

– Daily sediment deposition

• Capacity – Reliability during construction

• Method cannot significantly restrict capacity during non-work hours

– Rehabilitated pipe • New profile cannot significantly reduce capacity

12

Lessons Learned Damage Repair Project

• 1993 Danby

• Rigid sheets

• Grouted in place

• No repairs needed

13

Lessons Learned Wood St Projects

• 2001 Linabond

• Flexible sheets glued with “structural polymer”

• Many repairs needed due to hydrostatic failures

• 2012-15 Linabond

• Rigid sheets glued with “structural polymer”

Technology Evaluation Overview

14

• 10 methods evaluated, 5 screened as feasible

Alternative Project Installation

Post Construction

Manned Inspection

Repairs To-date

Danby Crown

SD-205A 1993 1997 None

Linabond SD-238 2000 2007

2012*, 2017**

SD-342 2012-15 n/a n/a

Ameron SD-297 1993 2015 None

Hobas Numerous Large

Diameter Numerous Some

Sekisui & Danby Spiral

Waterside Large

Diameter ? ?

* ’12 329 individual repairs, 1567 square feet of repairs. ** ’17 9 repair of repairs

15

96-97” diameter

Rehabilitation Systems Slipliner Detail (complete liner)

16

97-100” diameter

Rehabilitation Systems Spiral Liner (complete liner)

17

Rehabilitation Systems Crown Liner Manufacturer

• Danby specified

• No known equal

• Linabond not be specified

• Higher cost

• Longer schedule

• Quality concerns by Linabond

• Lower life cycle

• Unresolved safety concern

• Ameron Arrow-Lock specified for repairs

18

Rehabilitation System Evaluating Alternatives (Operations)

Alternative Operations Impacts*

Remote Plant

1. Crown Lining Medium Medium

2. Slip Lining Low Low

3. Spiral-wound Liner Medium Medium

19

Rehabilitation System Evaluating Alternatives (Cost)

Item Alternative

Crown Liner Slip Lining Spiral Liner

Number of Potential Bidders

2 5-10 1

Historic Bid Spread*

40-50% 10-25% n/a

Marketplace Volatility

High Low Medium

*Actual bid range $4.9-7.5M, Engr Est $5.9M

20

Platform

Rehabilitation Systems Crown Liner Detail (Ph1 Selected – Danby)

101” diameter

Lower Termination Level

21

Flow Management Strategy

Extended Work Hours to Lower Cost and Community Impacts

Weir Wall

• Schematic of In-System Storage

22

Flow Management and Working Hours Control Gate Location

23

Flow Management and Working Hours Control Gate Layout

• District purchased standard wastewater control gate • District designing the bulkhead wall • Contractor got O&M training • District tested before rehab starts

24

South Interceptor Diurnal Water Level

Platform Level Possible Work Hours

• Flow modeling in work area

PS-H Off PS-H On

Flow Management and Working Hours Remote Operations Impacts

25

South Interceptor Projected Flow at IPS

Flow Management and Working Hours Plant Operations Impacts

Total Projected Flow at IPS

Projected Storage at Plant ~7 MG

Assumed Plant Base Flow Rate

26

Scenario Available

Work Hours Productivity Work Hours

Wood St 4 2

3rd St 10 8

Productivity Improvement -- 300%

Potential Cost Savings -- $0.5-1 million

Potential Schedule Savings -- 1-2 months

• Extended work hours due to control gate

• Cost of control gate assembly ~$100K

Flow Management and Working Hours Comparison to Wood St Work Hours

Safety and Odor Odor Treatment System – Study Overview

• Feed hypo from SAC Dechlor at 1 to 4 gpm

• Goal is to reduce sulfide loading and release during construction

• Collect liquid and gas sulfide data

27

•Grab samples taken at S54 and S60

• Conclusions

– Clear reduction in liquid sulfides with 3 GPM hypo feed

28

Avg. Sulfide (mg/L)

Baseline Week 1

Baseline Week 2

1GPM Hypo

3 GPM Hypo

S54 2.3 1.8 1.3 0.2

S60 2.5 2.2 1.9 0.4

Safety and Odor Odor Treatment System – Initial Liquid Results

29

Safety and Odor Odor Treatment System – Baseline Gas Results

Average Value During Work Times

Reduction from Baseline

4AM-4PM ppm Baseline 16.9 0% 1 GPM 13.5 20% 3 GPM 7.1 58%

30

• Average during 3 GPM hypo feed -> 58% reduction in H2S

Safety and Odor Odor Treatment System – Initial Gas Results

• Contractor operates hypo feed system

• Cost Savings: Dosing 3 gpm is $108K versus $325K for odor scrubber

• Contractor provides redundant odor control system in work area

31

Safety and Odor Odor Treatment System – Contractor Scope

Challenges/Risks Community/Business

Risk Initial Risk Level

Mitigations Residual Risk Level

Residential neighborhood construction impacts

(working hours and traffic on narrow streets)

High

• Shift work hours to daytime with control gate

• Add temporary manhole outside residential area (inside Post Office)

• Limit work hours for staging and access in residential area

• Design traffic controls to minimize traffic impacts

Low

Public upset about construction impacts (noise, light, and odor) Medium

• Clearly define contractor requirements for controlling construction impacts to threshold values

• Measure and enforce requirements

Low

Public upset about displaced street parking and towing

Medium

• Provide resident notice about no parking via mailers and changeable message signs

• Secure an alternative parking area for residents, if needed

Low

Impact to Post Office operations caused by traffic disruption High

• Add new manhole outside roadway

• Limit work hours for manholes in the path of travel for freight trucks

• Work closely with Post Office

Low

32

Challenges/Risks Safety/Regulatory/Permitting

Risk Initial Risk Level

Mitigations Residual Risk Level

Manned entry into active sewer under confined space conditions with hazardous sewer gases High

• Design an odor treatment system that reduces hazardous sewer gas levels below OSHA limit

• Clearly define safety requirements

• Monitor compliance with safe work practices

Low

Sanitary sewer overflow in tributary system (Oakland) caused by contractor’s operations Medium

• Clearly define requirements to maintain free flowing condition in Oakland system

• Clearly define penalties in special provisions for sanitary sewer overflow in Oakland system

Low

Not receiving obstruction and excavation from City of Oakland on schedule

Medium • Obtain pre-approval of traffic control

plans

• Work closely with City of Oakland Medium

Criminal activity jeopardizes safety of District staff High

• Clearly define site security requirements in special provisions Medium

Worker exposure to toxic rehabilitation materials in a confined space condition High

• Only specify materials that are proven safe in a confined space condition

• Specify requirements for ventilation system

Low

33

Challenges/Risks Technical/Quality

34

Risk Initial Risk Level

Mitigations Residual Risk Level

Design does not provide flow management strategy that provides enough working hours for proper application

High

• Utilize flow equalization available at Plant and South Interceptor to extend working hours

• Utilize temporary bulkhead wall and control gate to extend working hours

Low

Design does not incorporate lessons learned from previous Wood St. Rehab projects High

• Utilize project team from Wood St. Rehab projects for design submittal review

• Incorporate details from Wood St. Rehab project RFIs and COs into bidding documents

Low

Design does not anticipate challenges associated with managing tributary flows Medium

• Collect best available data on tributary flows (size, peak flow rate, etc)

• Clearly define contractor’s responsibility to convey tributary flows in special provisions

Low

Rehabilitation materials are applied under unsuitable conditions High

• Only specify rehabilitation materials that are proven under active flow condition

• Require manufacturer representative assistance during application

• Apply rigorous quality assurance test procedures

Medium

35

Questions

Recommended