RAILROAD COMMISSION OF TEXAS
How to Submit Oil Online Completions – (Form W-2)
Jacque Teseny, Well Compliance
2
Class Synopsis
This presentation is a general overview of how to file Oil/W-2 Completion Reports utilizing the RRC Online
Completion Filing System. By the end of this PowerPoint you will learn how to properly file online completions for oil wells in Texas. During the class we
will also review common problems that delay the processing & approving of these filings.
3
Logging Inwww.rrc.state.tx.us
4
Logging In Cont’d
5
Online Applications
Important messages and upcoming events
6
Completion Application
7
Select Filing Operator
If you are filing as an Consultant/ Agent - you will enter the
appropriate Operator information here. If you are filing as an
Operator, then the online system will recognize you and you will
skip this step.
8
Filing Options
9
Create a New Packet
You can use either option but use the drilling permit # if you have one.
10
Select a Well
Select the field you completed in, if the well is downhole commingled you would need to select the primary reporting field – refer to SWR 10 Approval Letter
11
Packet Data - Create Packet
12
Packet Data - Create Packet Cont’d
Type Of Completion The options available are:• New Well • Deepening • Plug Back • Sidetrack • Reentry • Other/Recompletion
Well TypeThe options available are:• Producing • Shut-in Producer • UIC • Shut-in UIC
Type of Completion Packet The options available are:• G-1 - Select G-1 for gas
wells or oil wells being reclassed to gas.
• W-2 - Select W-2 for oil wells or gas wells being reclassed to oil.
13
Packet Data / Oil W-2
Tracking # Current Packet Status
14
Packet Data/ Oil W-2 Cont’d
Make sure to click Save after completed !
Date the well is capable of production by the flipping of a switch or
turning of a valve
Required Items
15
W-2 Oil Well Potential Test
*
*
• Enter Pump Size & Type if ‘Pumping’. • Enter Choke Size, if Production Method is
'Flowing'.• Test Date should be newer than the
completion date but prior to the submittal date.
*
* Optional Items
16
W-2 Page 2
If Initial Filing this is the SPUD date
If Initial Filing this may be the Rig Release Date
Lease Line should match the permit exactly – if they don’t you may need an amended
permit
17
W-2 Page 3
This is the Date Found on your
GAU Letter
Be Sure to bubble Yes if there are any additional
surveys attached
Only complete if Multiple Completion – not for workovers or
downhole commingled wells
Rotation Time Within Surface
Casing is a REQUIRED item
18
W-2 Page 4
Depth found on GAU Letter
*
Per SWR 13(b)(5)(a) All Flowing Oil wells must have Tubing Set unless an EXTENSION is granted by field
rules. If the question is answered no you must provide an explanation and your allowable may be withheld.
Optional
19
W-2 Page 5Mark this question yes if there are no
perforations and/or all perforations are isolated and incapable of production
List all perforations that are currently open. If Open Hole check open hole, if horizontal or
directional then select the appropriate lateral label.
List any acidizing/ shot/ fracturing/
cement squeezes/ CIBP’s here with
the affected depths. It is very important to list old perforations
and how they were isolated here if
recompleting a well to prevent a
violation of SWR-10.
List any important information here,
SWR 10 remarks are required.
20
W-2 Page 6 (Certification Page)
If this is marked No and there are no remarks then the well may be processed incorrectly and permit will
be closed out. A Recompletion permit will be required to correct the
well status and completion data.
21
Complete Additional Forms
22
L-1 Electric Log Status Report
Reminder: The Log should be mailed to the Well Compliance
Department (Austin).
23
P-4 Certificate of Compliance & Transportation Authority
It is ideal to use the search boxes on this page – the search feature will
validate that the selected gatherer/purchaser has the proper
codes and requirements for the activity you are listing them for
24
P-4 Certification Page
You can only mark authorized agent if you are listed on the P-5A
or on the operator’s P-5
25
Online W-12 Inclination Report
The items and questions on this form should match the attached
W-12 Exactly
26
Online P-15
27
Load Attachments
W-12’s, W-15’s, and the GAU letter are the most common REQUIRED forms. Refer to field rules for requirements on
proration plats, P-15’s/acreage lists/lease plats etc. Attach a SWR 10 letter if downhole commingling and an L-1 log header
if requesting confidentiality
28
Submittal Page
You can validate your completion for any errors or missing forms prior to submittal.
29
Submittal Page Cont’d
Once submitted you must contact the Railroad Commission Well Compliance Department to add any attachments,
complete any additional forms or make any corrections to the existing packet.
30
Finished !
31
MY MESSAGES/OPERATOR MESSAGES
My Message
s
• All Messages Issued to Currently Logged in User Only
Operator
Messages
• All Messages Issued to the Associated P-5 Operator Number• Ideal to use if someone has left your company or you have multiple filers!
Recent
Notifications
• All Messages issued within the selected time frame -- i.e. the last 7 days
***Once your packet has been submitted it is of the utmost importance to check your messages and respond to messages once the items have been
corrected. The packet is brought to the RRC staff’s attention much more quickly in an internal “messages response” queue that is checked every morning.***
Use this option to update existing packets you have created or you will have access to update existing completions that were submitted hardcopy.
32
Top 30 Problems That Can Delay A Completion Packet’s Final Approval
1. Failing to respond to messages online from the RRC Analyst, even if you have corrected the problem.
2. Not filing all required forms with the packet.3. Over-assigning acreage.4. Log headers do not have all the required
information.5. Amending Drilling Permit ASAP and follow-up for
approval.
33
Top 30 Problems That Can Delay A Completion Packet’s Final Approval
6. Make sure all questions are answered correctly and completely.
7. Adding a second/another P4 when an initial P4 has already been filed.
8. Make sure that P4 gatherers and purchasers have an active P5.
9. Make sure all electronic forms are completed, certified, and submitted.
34
Top 30 Problems That Can Delay A Completion Packet’s Final Approval
10. Filing information that is not needed.11. Properly labeling attachments.12. Make sure that all of the following are correct:– Type of Completion– Purpose of Filing– Well Type
13. File drilling permit prior to drilling the well.
35
Top 30 Problems That Can Delay A Completion Packet’s Final Approval
14. If the information on the G5 does not meet the requirements, be sure to file a PVT Analysis or Compositional Analysis.
15. Lease lines measurements should be the same as drilling permit lease line measurements, if not explain
16. Use the remarks section of the completion forms (G1/W2) to explain any changes or amendments. Also use this section for any information that you want the analyst or the RRC to know.
36
Top 30 Problems That Can Delay A Completion Packet’s Final Approval
17. Make sure that any attached files display properly (P12’s, plats).
18. W-12 not filled out correctly or is incomplete. 19. No change in completed, commenced, and
completion dates when the well is worked over or re-completed
20. Not addressing remarks related to SWR10 information (i.e. remarks, perfs, formations).
37
Top 30 Problems That Can Delay A Completion Packet’s Final Approval
21. If a well is worked over or recompleted, showing how the perforations were isolated.
22. Hard copy filings that are filed with incomplete or missing information.
23. Operators adding zeros in the extra spaces linked to the well numbers.
24. If acreage assignment changes as wells are drilled, filing revised P15’s, proration plats, and or acreage list for all wells on the lease that have revised acreage.
38
Top 30 Problems That Can Delay A Completion Packet’s Final Approval
25. Shut-In/Time of Run for G1’s (1 Point Test) should be 1440 minutes (24 hours).26. The well is completed in formations that are outside the designated correlative interval for the completed field and a SWR 10 has not been filed.27. The formation record section on the G-1/W-2 should show the formation names that define each completed field.
39
Top 30 Problems That Can Delay A Completion Packet’s Final Approval
28. Not Filing proration acreage plats when field rules require that acreage be assigned to each well
29. Not checking the field rules before filing30. Not utilizing the RRC website to retrieve well
information
40
CONTACT US
E-MAIL: PRORATIONUNIT@RRC.STATE.TX.US
For immediate assistance call the Well Compliance (Proration)
main phone number: 512-463-6975