PROJECT SPECIFICATION Micro-simulation Model of Idrottsparken Roundabout
ANALYSIS OF COMMUNICATION AND TRANSPORT SYSTEM (TNK103)
Lecturer:
Clas Rydergren
Ellen Grumert
8/7/2019 Project Specification Idrottsparken
http://slidepdf.com/reader/full/project-specification-idrottsparken 2/12
Table of contents
Introduction ....................................................................................................................................1
Background ....................................................................................................................................1
Project aim and purpose ..................................................................................................................1
Goals and requirements ...................................................................................................................1
Usage..........................................................................................................................................3
Overview of the system...................................................................................................................3
Description of the system ............................................................................................................3
Components ................................................................................................................................5
Delimitation or What is not included ...........................................................................................5
Delivery..........................................................................................................................................6
Documentation................................................................................................................................6
Time plan........................................................................................................................................7
8/7/2019 Project Specification Idrottsparken
http://slidepdf.com/reader/full/project-specification-idrottsparken 3/12
Introduction
Nowadays, the traffic population increases rapidly so that the road is over capacity. This
condition become a problem for the transportation. To identify, analyze, design and solve the
traffic problem, traffic engineer could use simulation model. The traffic simulation model is a
technique that can be used to figure the real traffic conditions because the calibrated and
validated simulation could represent the real traffic condition. There are 3 methods of
simulation. They are micro-simulation, meso-simulation and macro-simulation. In this
project, a micro-simulation is applied to develop a model in the roundabout at the
Idrottsparken.
Background
The roundabout at Idrottsparken consists of four legs. It connects 3 roads. They are
Kungsgatan, Södra Promenaden and Albrektsvägen. Congested traffic occurs during peak
hours in the morning and afternoon. In the location, the congestion can be seen from the
queue length at each roundabout’s leg. From the preliminary survey, the long queuing
affecting the congestion is contributed by traffic flows from Kungsgatan and Sodra
Pramenaden. This project focuses on the roundabout at Idrottsparken which is influenced by
nearest intersection in Kungsgatan.
Project aim and purpose
The aim of this project is to develop, calibrate, validate and experiment the micro-simulation
model of the traffic in the roundabout at Idrottsparken so that the performance of the
8/7/2019 Project Specification Idrottsparken
http://slidepdf.com/reader/full/project-specification-idrottsparken 4/12
- create form(s) to conduct the main
survey (week 13, deadline: April, 3,
2011)
3 Data Collection Obtained data of:
- road geometry design and network
(week 14)
- Demand data, consisting of traffic
volume: traffic flow approaching
the roundabout, and turning flow(week 14)
- Calibration data using the queue
length, and validation data using
travel time (week 14 and 15)
- traffic signaling (week 14)
- Input data that related with user
behavior like reaction time are
difficult to be observed, so we use
the default data from AIMSUN.
1st
4 Developing Model
Simulation
- Develop model using Aimsun
software (road geometry and
network) (week 14-15) E h ki f th d l ( k
1st
8/7/2019 Project Specification Idrottsparken
http://slidepdf.com/reader/full/project-specification-idrottsparken 5/12
- Finalizing and submit project report
(week 22, deadline: June, 1, 2011)
Usage
The developed model can be used to figure the current traffic situation in the roundabout at
Idrottsparken and identify the congestion problem. It also can be proposed to improve the
roundabout performance, so that this project could be an alternative suggestion for the local
authority.
Overview of the system
The roundabout at Idrottsparken is congested during rush hours, especially in Kungsgatan and
Sodra Promenaden direction. The nearby city center brings a large number of passenger cars.
The roundabout at Idrottsparken is figured below.
8/7/2019 Project Specification Idrottsparken
http://slidepdf.com/reader/full/project-specification-idrottsparken 6/12
Figure 2. Influence Area
The analysis focus on the roundabout only, whereas the intersection is considered in the
model because that intersection involves the roundabout congestion.
The base data needed is the roundabout, intersection and road geometry. To draw the network
geometry, we combine between the field measurement and the map digitization. The software
used is AutoCAD. The data needed include the traffic control and speed limit.
8/7/2019 Project Specification Idrottsparken
http://slidepdf.com/reader/full/project-specification-idrottsparken 7/12
Thursday
April 7th,
2011
07.15 - 08.30 √ √ √ - conducted in 15 minutes.
The total time needed for a
survey is 75 minutes.The period of survey has
been chosen on that time by
considering that the survey
should be started before
the onset of congestion
and end after the
dissipation of all
congestion.
15.45 – 17.00 √ √ √ -
Tuesday
April 12nd
,
2011
07.15 - 08.30 - - - √
15.45 – 17.00 - - - √
WednesdayApril 13
rd,
2011
07.15 - 08.30 - - - √
15.45 – 17.00 - - - √
Thursday
April 14
th
,2011
07.15 - 08.30 - - - √
15.45 – 17.00 - - - √
All of the data gathered from the field survey will be the input for the AIMSUN program to
be simulated in a traffic model. The built model will be calibrated and validated with the
separated data to ensure the model represent the real condition of the study area. When the
simulation model is well validated, meaning that it already represents the real traffic
conditions, the experienced problems is ready to be analyzed. Based on the problem that isfound in simulation model, we can propose a suggestion to solve the problem.
Components
The results of the project consist of:
1. Documented data collection.
2. Calibrated and validated simulation model.
3 R d b t bl id tifi ti l t d ith th ti b d th
8/7/2019 Project Specification Idrottsparken
http://slidepdf.com/reader/full/project-specification-idrottsparken 8/12
condition is unlike the other two intersections which are relatively far from the
roundabout and give small effect to the roundabout.
3. Based on the preliminary survey, our group decides the data collection will beconducted during the morning and afternoon peak hours, at 07:30-08:30 AM and
16:00-17:00 PM, with the early 15 minutes warming up time.
4. The traffic signal system used for the existing condition model is fixed time control
plan signal.
5. In the traffic simulation model of AIMSUN, the calibration process will use thequeue data, while the validation process will use the travel time data. The queue and
travel time data that is calculated is queue and travel time of the vehicle in the sectionbefore they enter the roundabout.
6. The input data that are related to human behavior like reaction time and queuing
leaving speed is difficult to be gathered in the field survey, so that we use the data
from the AIMSUN default and literature.
7. In this traffic simulation and analyzes, there are no considerations or analyzes in the
sound pollution, air pollution or other environmental impacts.
General demands of the complete systemThe general demands of the system outputs or final suggestions have to fulfill some aspects asfollows:
1. The traffic simulation model has to be as good as possible represents the real trafficcondition of the study area. To achieve this, error checking, calibration and validation
have to be held.
2. The alternative improvement suggestion will be compared to the existing conditions
weather it will be better or worse.
8/7/2019 Project Specification Idrottsparken
http://slidepdf.com/reader/full/project-specification-idrottsparken 9/12
2 Project Plan This part will explain the time table and man-hours
allocation in conducting the entire works on the project
3 Project Report This is the final result of the project works. In this document
our group will report the entire problems, analysis, and
conclusion of what we obtain from the study area of
Idrottsparken roundabout. This document will be consisting
of Introduction, Overview of Existing condition, Literature
Review, Data Collection, Modeling / Simulation, Analysis,
Conclusion.
4 Opposition Report In the nearly end of the project course, our group will
oppose other group’s project which will be documented in
an opposition report, consisting of suggestions, inputs, or
critics if necessary.
5 A documented datacollection
This part is consisting of data forms, field survey forms, andother data-gathering related documents. The analyses result
in the AIMSUN simulation will also collected in this part of
project.
Time plan
Th ti t bl f thi j t hi h l i i th d t il f k d th ll ti f ti
8/7/2019 Project Specification Idrottsparken
http://slidepdf.com/reader/full/project-specification-idrottsparken 10/12
1
Appendix
Activity and time plan
Project title: Microsimulation of the roundabout at Idrottsparken
Project members: Date: 05/04/2011
1. Mochdiana Hernawan Version: 1.0
2. Petrus Hery TC
3. Tri Sudibyo
Activities Time Who Weeks
No Description Hours Initials 12 13 14 15 16 17 18 19 20 21 22
1 Introductory seminars 12 All mon
2 Construct project group and indicate project priorities 1 All
3 Supervision
First meeting (Supervision 1) 1 All tue
Supervision 2 7 Allmon
Supervision 3 1 All mon
Supervision 4 1 All
Supervision 5 1 All
Supervision 6 1 All
4 Preliminary survey wed
check location of the roundabout 1 All
check of the traffic condition 1 All
check of the traffic signaling 1 All
determine point for the surveyor 1 All
5 Project specification and project plan - All
Developing the time plan (Gant chart) 3 All
Writing project specification 14 All
Project specification and project plan delivery wed
8/7/2019 Project Specification Idrottsparken
http://slidepdf.com/reader/full/project-specification-idrottsparken 11/12
6 Developing and finalizing the traffic survay form 4 All
7 Collecting data
Traffic Flow, turning movement and queue data 10 All
Travel time data 10 All
Road geometry and network design 1 All
Traffic signaling 1 All
8 Develop AIMSUN Modeling
Develop the model 16 All
Error checking the model 8 All
Calibrate the model with appropriate field data 16 All
Validate the model with field data 16 All
Scenario(s) as alternative suggestion 10 All
9 Project Report Writing
Draft report writing
Chapter I (Introduction) 4 AllChapter II (Overview of Existing Condition) 4 All
Chapter III (Literature Review) 6 All
Chapter IV (Data Collection) 6 All
Chapter V (Modeling / Simulation) 4 All
Chapter VI (Analysis) 4 All
Chapter VII (Conclusion) 4 All
Finalizing report writing
Chapter I (Introduction) 2 All
Chapter II (Overview of Existing Condition) 2 All
Chapter III (Literature Review) 4 All
Chapter IV (Data Collection) 4 All
Chapter V (Modeling / Simulation) 4 All
Chapter VI (Analysis) 4 All
8/7/2019 Project Specification Idrottsparken
http://slidepdf.com/reader/full/project-specification-idrottsparken 12/12
Chapter VII (Conclusion) 4 All
Preliminary report submission (for opposition) 1 All thu
Written opposition 1 All tue
Final revision after the opposition 4 All
Final report submission 1 All fri
10 Mid project evaluation 1 All mon
11 Final report presentation 2 All wed
12 Project group self assessment 1 All wed
Total number of hours 205