PROJECT MANAGEMENT

IN

Submitted byBanaja pattanayak

MBA IInd year

A Project Report on

Welcome to Construction World

Top 10 Construction Companies

AFCONS began its operation as a civil construction firm way back in 1959. The Company was then a partnership between RODIO FOUNDATION ENGINEERING LIMITED, SWITZERLAND AND HAZARAT AND COMPANY, INDIA

, AFCONS has emerged as the leader in its business field by continuously delivering its world class services in the areas of Marine Works, Highways, Bridges, Metro Works, Power Houses, Tunnels, Oil & Gas, LNG Tanks and other general Civil Engineering Projects

Line Of Business

Power Project Transportation Marine Drive

Buildings & Industrial Structure Oil & Gas Special Foundation

Financial Highlights

Mission•To be a prominent transnational infrastructure company recognized for business innovation, focused on total satisfaction and enhanced value creation for all its stakeholders.

Goal •It aims to be a billion dollar company by 2011-12.

PROJECT MANAGEMENT

Project Management is a well-established approach to managing and controlling the introduction of new initiatives or organizational changes.

Tools of Project Management

Estimating Time Risk Impact Scheduling Simple Projects Critical Path Analysis Planning Large Project Stake Holders Analysis Stake Holders Planning &management

Project-1

Owner : New Delhi Municipal Council

Client : Engineers India Limited on behalf of NDMC

Contractor : M/s AFCONS –Sterling & Wilson Consortium

PROJECT TEAM

1. Projects consists of Construction of service Corridor at Middle Circle and laying of the Service of Connaught Place,

2. Total Contract Value : 236.70 Crores

3. AFCONS Scope : 180.42 Crores

4. Revised AFCONS Scope : 198.39 Crores *

5. S & W Scope : 56.30 Crores.

6. Duration of Project : 18 Months.

7. Date of Issue of letter of acceptance : 04th Nov 2009

8. Date of completion of Project. : 03 May 2011

9. Defect Liability Period of Project. : 12 Months from the

date of issue of completion certificate.

PROJECT DETAIL

Design and Construction of Cut & Cover Tunnel Including

Switchover Ramps and One Underground Station in Airport

AreaAMEL – C3 Project

Project-2

Client : Delhi Metro Rail Corporation

Limited

Consultant : Airport Line Consultants

Contractor : Afcons Infrastructure Limited

Total Length - 3630 RM

Excavation - 791250 Cum

Piling - 2900 RM

Reinforcement - 12500 MT

Concrete - 95000 Cum

Structural Steel- 5000 MT (Temp.

works)

Major items of Work

CONCLUSION