PROJECT OVERVIEW
• FM Budget 21 589 225€
• Total contracted 16 214 784.16 €– EU Grant 12 532 983.41€– National Co-financing 3 681 801.05
– Total contracted / FM budget 75.11 %
• Total certified 13 007 325.45 €
• Financial Implementation certified / contract : 80,22 %
9th Cohesion FundMonitoring Committee CR
1164/94
ISPA Measure 2002 BG 17 P PE 017
9th Cohesion FundMonitoring Committee CR
1164/94
ISPA Measure 2002 BG 17 P PE 017
WWTP BALCHIK AND МАRINE OUTFALL
Works ContractWWTP Balchik
• Commencement Date: 28th June 2006
• Completion Date: 10th March 2010
• Physical Execution: 99.6 %
• Financial Execution: 80 %
• WWTP is operational as from 10th March 2010
• 1 year DNP commenced on 10th March 2010
9th Cohesion FundMonitoring Committee CR
1164/94
WWTP Balchik Taking – over of the Works and Sections
9th Cohesion FundMonitoring Committee CR
1164/94
WWTP BALCHIK
Aeration tank
Sludge tank
9th Cohesion FundMonitoring Committee CR
1164/94
WWTP BALCHIK
Main Tanks
9th Cohesion FundMonitoring Committee CR
1164/94
WWTP BALCHIK
Sludge Storage Tank
9th Cohesion FundMonitoring Committee CR
1164/94
Works ContractBalchik Water Supply& Sewerage Network
ConnectionsISPA Measure 2002 BG 17 P PE 017
• Date of works contract signature: 18th of Dec. 2007
• Commencement Date: 21st of April 2008
• Completion Date: 5th of January 2010
• Physical Execution: 99.8%
• Financial Execution: 75%
9th Cohesion FundMonitoring Committee CR
1164/94
Balchik Water Supply& Sewerage Network Connections
Information boards
9th Cohesion FundMonitoring Committee CR
1164/94
Balchik Water Supply & Sewerage Network Connections
Varnenska str.part No1fully competed
Varnenska str.part No2 fully competed
9th Cohesion FundMonitoring Committee CR
1164/94
Balchik Water Supply & Sewerage Network Connections
Edelvays str.part 1 – fully completed
Edelvays str.part 2 – fully completed
9th Cohesion FundMonitoring Committee CR
1164/94
Balchik Water Supply & Sewerage Network Connections
Sr.Gora str. part 1- fully completed
Sr.Gora str. part 2 -– gravelling works
9th Cohesion FundMonitoring Committee CR
1164/94
Balchik Water Supply & Sewerage Network Connections
Volga str. part No1 – fully completed
Volga str. part No2 – fully completed
9th Cohesion FundMonitoring Committee CR
1164/94
Service ContractPreparation of Design and Works
Supervision for ISPA Measure Balchik
• Commencement Date: 15th December 2005
• Completion Date: 30th December 2011
• Time elapsed: 100 %
• Financial Execution: 85 %
9th Cohesion FundMonitoring Committee CR
1164/94
Service Contract Technical Assistance for
Implementation of four ISPA Measures for Integrated Water Management in Smolian, Varna, Balchik and Shoumen
(Lot 3)
• Commencement Date: 14th July 2007
• Completion Date: 17th September 2010
• Time elapsed: 100 %
• Financial Execution: 99 %
9th Cohesion FundMonitoring Committee CR
1164/94
Supply Contract Delivery of diagnostic and modeling
equipment for the water and waste water network
Commencement Date: 28th of January 2008
Completion Date: 28th September 2008
Time elapsed: 100 %
Financial Execution: 100 %
9th Cohesion FundMonitoring Committee CR
1164/94
Compliance with Article 8of the Financing Memorandum
8.4.b )The presentation of a final programme for the treatment, reuse and disposal of the sludge under terms acceptable to the Commission.
The sludge programme was reviewed for its compliance with the requirements of the EC. The revised draft version of it had been re–submitted to the EC’s services for their review and approval.
All other conditions in compliance with article 8 of the FM are to be considered as fulfilled.