View
212
Download
0
Category
Preview:
Citation preview
Terence O’Rourke
Terence O’Rourke
Project Manager
Finish Under Budget
Keep Client Happy
Keep Team Happy
Meet Requirements
Project Management Requirements:
Terence O’Rourke
• Timely & Appropriate Planning
• Collection
• Creation• Distribution
• Storage• Retrieval
• Management
• Control
• Monitoring
• Disposition of Project Information
Terence O’Rourke
Project Manager
Problems Occurred:
• Human Interactive• Develop scripts within the
model checker• Update the model with
IFC files• Refresh to keep
program from stalling
Terence O’Rourke
Project Manager
• Team Meetings schedule• Meeting Minutes• Design Information• Additional Project Issues
Terence O’RourkeTerence O’Rourke
• On Project Set-up
Name Mobile Number Email Discipline Access
John Smith 087-2169348 johnsmith@gmail.com Mechanical
Jane Ross 087-6849389 janeross69@gmail.com Electrical
Peter White 087-2868799 Peter.white@gmail.com Architect
• Delivery Conformation to Project Manager
• Avoid “out of office” reply's
• Enable users to access design files quicker
• Programme timeline
• Resolve issues in advance
Terence O’Rourke
• On Project Start-up
Specify:
• Discipline Tasks
• Discipline Stages
Task Stage Duration Start End
1 - Heat Loss Design 2 days Nov-21-2016
2 - Duct Sizing Design 3 days Nov-24-2016
15 – Fit-out Construction 6-weeks Jan-05-2017
• Task Duration
• Site Start Date
• Expected Finish Date
Nov-23-2016
Nov-27-2016
Jan-16-2017
Terence O’Rourke
• On Project Start-up
Allows:
Project Manager to show case
the overall design to the client
before work on site
commences.
Terence O’Rourke
Summary
1.0Introduction
2.0Objectives
2.1ProjectObjectives
2.2ListofObjectives
3.0SystemDesign
3.1PrimaryRequirements
3.2SecondaryRequirements
3.3GeneralUserInterface(GUI)
3.3GeneralUserInterface(GUI)
3.4Security
3.5DocumentManagement
3.6Database
4.0KnowledgeManagement
Conclusion
Bibliography
Appendix
Terence O’Rourke
Recommended