Project Spotlight | Lake Almanor Spillway Bridge | Canyon Dam, CAFiberForceTM by ABC Polymer Industries | (205) 620-9889 | abcpolymerindustries.com

Caltrans has included 4 pounds of our macro/micro mix, ProMax to minimize cracking on the bridge deck. Both the readymix supplier and contractor were extremely happy with the way the ProMax Blend mixed and placed. This project is the second time Caltrans has used stainless steel #11 rebar, which is used in place of traditional rebar to avoid corrosion from de-icing salts.

Project Spotlight LAKE ALMANOR SPILLWAY BRIDGE • CANYON DAM, CA

PROJECT DATAAPPLICATION TYPE Bridge deck

OWNER State of California DOT (Caltrans)

ARCHITECT CaltransENGINEER CaltransCONCRETE CONTRACTOR Q&D Construction

READY-MIX CONCRETE SUPPLIER

White Cap Ready Mix

FIBER SUPPLIER FiberForceFIBER TYPE & DOSAGE

ProMaxTM

4 lbs per cubic yard

VOLUME 700 cubic yards DIMENSIONS 2,000 feet longPROJECT DATE September 2018