View
8
Download
2
Category
Preview:
Citation preview
Project Construction Schedule Review October 14, 2020
Project Construction Schedule ReviewBuilding the Texas Transportation System
October 14, 2020
Project Construction Schedule Review October 14, 2020
Why do we even need a schedule?
▪ It causes more effort to be expended on planning the execution of the project
▪ It allows the project status to be known from project start to end
▪ It leads to better outcomes
▪ How do we get the best possible schedule?
2
Project Construction Schedule Review October 14, 2020
TxDOT Requirements for Schedules
▪ Defined in 2014 Standard Specs in Item 8
– Defaults to a barchart schedule
– CPM if shown on plans (usually under Item 8 in the General Notes)
– Best Practice require compatibility with Primavera P6 in the General Notes
▪ Required Submittals
– Baselines
– Monthly Updates
3
Project Construction Schedule Review October 14, 2020
Baselines
▪ Submittal timeline
– Preliminary Schedule required 7 calendar days before the Precon
– Detailed Baseline submitted within the first 45 calendar days
– Acceptable Baseline before the 90th calendar day
▪ How to meet these deadlines
– Make it clear from the beginning quality and timely schedule submittals are important
– Encourage Contractor to get started, identify scheduler
– Make schedule a line item on partnering meeting agendas
– Send formal correspondence on non-conformance
– Partner with the Contractor, focus on important issues
4
Project Construction Schedule Review October 14, 2020
Baselines - Barcharts
▪ Reviewing Barchart Baseline Schedules
– Meets contract time
– All work is included
– Conforms to the Traffic Control Plan
– Traffic shifts are clearly identified
▪ Common Issues
– Exceed contract time
– Lack of detail
– Traffic shifts not clear
5
Project Construction Schedule Review October 14, 2020
Baselines - CPM
▪ For CPM projects we always use a checklist
– Meets contract time
– Conforms to the Traffic Control Plan
– Traffic shifts are clearly identified
– Concise activity descriptions
– Correct calendars
– “Level of Effort” activities for overall contract time and milestones
– Uses “hard” logic
– Provides quantities and production rates
• Best Practice provide in “User Defined Fields”
– Clearly defined critical path
6
Project Construction Schedule Review October 14, 2020
Baselines - CPM
▪ Common Issues
– Concise activity descriptions
– Correct calendars
– “Level of Effort” activities for overall contract time and milestones
– Relies on “hard” logic not “soft” logic
– Provides quantities and production rates
– Contrived critical path
– Verify post-letting ROW and utility clear dates in PS&E are accounted for
▪ Review Techniques
– Add a “user defined field” and use it to filter and display particulars
– For very large projects, after getting familiar with the overall project take a deep dive into a particular construction sequence
– Perform a “backward pass” review
– Partner with the Contractor’s scheduler
– If there are major issues, identify and return as quickly as possible
7
Project Construction Schedule Review October 14, 2020
Updates
▪ Update reviews for Barchart Schedules
– Look for added activities
– Compare Finish Date
– Compare traffic shift dates
– Compare critical path and access critical path progress
▪ Review workflow
– Populate Project Schedule Summary Report (PSSR)
8
Project Construction Schedule Review October 14, 2020
Updates
▪ PSSR
– One line for each
schedule submittal
– How we are doing
versus the contract
– What happened and
why
9
Project Construction Schedule Review October 14, 2020
Updates
▪ Populate PSSR from CPM schedules
–
– Contract time calendar must be updated each period to reflect actual days
charged
10
Project Construction Schedule Review October 14, 2020
Updates
▪ For CPM – Key Items
– Monthly submittal no later than the 20th calendar day of the following month
• Best Practice is to reduce to 10th calendar day in general notes
– PDF’s of critical path and of all activities
– Not a revision or a time impact analysis
▪ Review workflow
– Upload Schedule and recalculate
– Review the schedule log
– Populate PSSR
– Run schedule comparison program like Claim Digger
• Another option is Change Inspector which compares XER files
11
Project Construction Schedule Review October 14, 2020
Updates
▪ Schedule Comparison to previous period
▪ Most important changes to review
– Added/Deleted Activities
– Added/Deleted Relationships
– Duration/Description Changes
– Actual Date Change
– Progress Change
▪ Did changes affect critical path?
12
Project Construction Schedule Review October 14, 2020
Updates
▪ Evaluate critical path
– Graphically analyze any change from pervious period’s critical path
– Flag previous critical path in “user defined field”
13
Project Construction Schedule Review October 14, 2020
Updates
▪ Common Issues
– Contract time calendar has been updated for
correct days charged
– Progress is accurate
– Original Duration changes
– The update is actually a revision or impacted
schedule
14
Project Construction Schedule Review October 14, 2020
Updates
▪ Note explaining gain or loss of time
– Use previous update as baseline
– Show previous month graphically for comparison
15
Project Construction Schedule Review October 14, 2020
Updates
▪ Retain prior critical path graphics in checklist reports.
16
Project Construction Schedule Review October 14, 2020
Updates
▪ Controversy…
– Schedule Revisions
• Based on most recent update, Not last update submitted
• Must have unrevised update with the same data date to make proper
comparison
– Impacted update schedules
– Failure to make corrections
– Out-sequence-progress
– Recovery Schedules
17
Project Construction Schedule Review October 14, 2020
Updates
▪ Report will provide:
– Summary in transmittal email with recommended action
– Draft letter
– Checklist with notes
– Barchart of critical path
– Barchart of all activities
– Barchart showing progress in period
– Earned Value progress curve
18
Project Construction Schedule Review October 14, 2020
Updates
▪ Earned Value progress curve
19
Project Construction Schedule Review October 14, 2020
TIA’s
▪ Time Impact Analyses (TIA)
– Identify issue and responsibility
– Create documents and correspondence for future use
– Determine when impact began (Step 1)
– Determine when impact ended (Step 4)
– Don’t rely on a predicted impact (Step 2)
– Pictures are very helpful, if we think something might become an issue, take
pictures and save them where they can be found
20
Project Construction Schedule Review October 14, 2020
P6 Setup
▪ Stand alone versus Server Setup
– Stand alone preferred for schedule reviews
– Portable databases
– Ability to create separate databases for each project
– Avoid contamination of Global codes and calendars
▪ Other options
– Use third party programs that create barcharts from XER files directly
▪ XER file issues
– POBS now remedied
– Risktype – Go into XER and delete that section
21
Project Construction Schedule Review October 14, 2020
In Conclusion
▪ Project Scheduling is valuable tool because it benefits:
– Contractor – better planning, likely to increase profit
– TxDOT – more information, less likely to pay for unwarranted claims
– Traveling Public – reduced construction cost and construction time
22
Recommended