Progress of Shintake Monitor Work

KEK site meetingAugust 26, 2009

T. Yamanaka

IP Target

• Design was fixed.• Fabrication is going on now.

Design of IP TargetDesign of IP Target

Collimator Scan

• Preparation of hardware is almost finished.– Only just lead collimator block is not prepared.

• Remaining task is to write scanning program

Background Monitor

• Drive system of background monitor is prepared.

• It need just only lead converter sheet

Cherenkov Detector

• Fabrication was finished.• Calibration of photon nu

mber using cosmic ray was almost finished.

• Put Cherenkov detector at the actual position as a trial

Cosmic Ray Data

Laser Transport

• Ordered a mount table for laser transport line as same as the EXT LW group

• It will be connected by PVC pipe to the mount table of EXT LW group.

Put this optical table on a mount

Replacement of Actuators

• Mirror actuators are changed from old ones.• New actuators (Thorlabs) need Windows’s base

d control– Windows machine is prepared– They are connected to PC by USB

• By using “AnywhereUSB” USB devices are converted to LAN

– To control by program and communicate with EPICS, LabVIEW is installed

• Need to write LabVIEW program Now here