Published on Planning Planet (http://www.planningplanet.com)
Home > Rates, Norms & Durations
By PP WikiCreated 5 Feb 2009 - 05:54
Rates, Norms & DurationsWhat is needed to come up with a production rate?
A duration of time, the manhours involved, and an amount of work produced?
This section is here to document this. What information do you have that you can share?
AutomotiveAutomotive Production Rates & Build Times:
BridgesBridges Production Rates & Buld Times:
Bridge Decking
Traffic DeckingInstallation of temporary traffic decking, consisting of steel beam decking and concrete panels.
A typical rate of = 1.6 m2/hr.
Cable Stringing
Covered Steel FootbridgeSimple universal beam steel bridge in modular sections, welded on site. 16 truss sections each 15 m in length, supported on H-frame vertical columns / supports.
Support Steelwork Fabrication (4 bays) = 25 days Support Steelwork Erection (4 bays) = 30 days Truss erections (4 bays) = 18 days Paintwork To Steel (16 bays) = 35 days Bridge Deck Concrete Works (16 bays) = 60 days (staggered) Bridge Lighting, Roof etc (16 bays) = 40 days Bridge Finishing, Handrails and Grano = 14 days
Structural Steelwork...
Task / Description Slow Ave Fast Units
Simple Universal Beam Steel Bridge, erect support steel H frames - 1.2 - days/no
Simple Universal Beam Steel Bridge, erect 15m truss - 3.3 - m/day
Design
Final Finishes
Page 1 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Formwork & Bases
Paintwork
Structural SteelworkSteel Frames
Task / Description Slow Ave Fast Units
Steel Frame and Roof Members 3.4 - 4.6 Tons/day
Wall Frame, Bow String Truss and Frame - 1.6 - Tons/day
Roof Frame, Curved Truss and Frame - 5.2 - Tons/day
Wall Frame, Glazed Frame and Atrium - 0.3 - Tons/day
Building & ConstructionBuilding & Construction Production Rates & Build Times:
BlockworkBlockwork
Task / Description Slow Ave Fast Units
Thermalite Blockwork, under 100mm thick 1.8 2.5 3.2 m2/hr
Thermalite Blockwork, under 100-150mm thick 1.4 1.9 2.5 m2/hr
Thermalite Blockwork, over 150mm thick 1.2 1.6 2.1 m2/hr
Lightweight Concrete Blockwork, under 100mm thick 1.5 2.2 2.9 m2/hr
Lightweight Concrete Blockwork, under 100-150mm thick 1.4 1.9 2.1 m2/hr
Lightweight Concrete Blockwork, over 150mm thick 1.2 1.6 2.0 m2/hr
Heavyweight Concrete Blockwork, under 100mm thick 1.4 2.1 2.9 m2/hr
Heavyweight Concrete Blockwork, under 100-150mm thick 1.2 1.6 2.1 m2/hr
Heavyweight Concrete Blockwork, over 150mm thick 1.1 1.4 1.8 m2/hr
Face Finish, Raked Out - 71.4 - m2/hr
Face Finish, Bag Rubbed - 29.4 - m2/hr
Face Finish, Flush Pointing - 17.6 - m2/hr
Building Frameworks
Curtain WallingCurtain Walling rate
Assume 30m2 per week for general curtain walling
Task / Description Slow Ave Fast Units
Vertical Glazed Lights, 6m x 2.5m - 14.5 - m2/day
Vertical Glazed Walls, large scale - 70.0 - m2/day
Clerestory Frame/Glazing, 3m x 4m - 28.0 - m2/day
Oriel Window Frame/Glazing, 4m x 2m - 35.0 - m2/day
Glazed Curtain Wall, First Fix - 1.2 - m2/hr
Page 2 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Glazed Curtain Wall, Second Fix - 1.1 - m2/hr
High Quality Glazed Curtain Walling - 25.0 - m2/day
Holding Down Bolts Stanchion Basesstanchion.
Bolt Numbers -->
4 No 6 No 8 No
Item
Make Softwood Framework
0.50 0.70 0.93
Fix Bolts / Framework
1.32 1.54 1.73
Strike Framework
0.38 0.44 0.49
Metal Frameworks
Roof StructureStructural Steel Structures
For medium sized applications with a single crane and fixing gang.
A typical rate 3.4 - 4.6 tonnes/day.
Structural steel for glazed wall, made of 18 no "bow string" strusses 25 m tall, cross braced and wired together, consisting of 69 tonnes of steelwork. Erection in 6 weeks.
Erection Rate 1.65 tonnes/day
Strucural steelwork for curved building roof, 18 number curved complex trussess and cross pearlins etc. Consisting of 500 tonnes of steel. Initially programmed for 14 weeks site installation period.
All Rates in Weeks...
GA drawings 0 - 6
Shop Drawings 4 - 13
Buildings Dept Approval 14 - 17
Shop Fabrication 18 - 30
Page 3 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Corrosion Protection 22 - 32
Site Pre-Assembly 32 - 34
Erection Time 35 - 38 (24 hr working)
Erection Rate 8.95 tonnes/day
Structural steelwork for glazed wall and atria over, 4 number bow string trussess in wall and in roof. Consisting of 7.5 tonnes of steelwork. Erection in 6.5 weeks.
Erection Rate 0.23 tones/day
Timber Frameworks
Roof StructureUsually carried out with a minimum of a 2 man gang, sometimes with an additional labourer.
For a typical semi-detached house structure or similar...
Roof Trusses 1.28 no/hr
Wall Plates 2.76 m/hr
Rafters 1.17 m/hr
Ceiling Joists 32.10 m/hr
Timber frame superstructureTimber framing rates for hospital of 3173m2 GIFA
Assuming that the labour is a 4 man squad working an 8 hour day as this would be normal practice
Wall panels up to 3m in hieght including both external and internal panels ; 30 panels per day (average panel 3.5m long)
Wall panels over 3m in height including both internal and external panels ; 20 panels per day (average panel 2.5m long)
Loose floor joists position and fix 175m sq per day Loose floor joists position, fix & position and fix floor decking 125m sq per day Floor/roof cassette assumed simple 12 X 2.4m 300m sq per day Floor/roof cassette complex shape 150 200 m sq per day Trussed roof erect, brace,sark and felt 100m sq per day (up to 8m span measured at horizantial) Trussed roof erect, brace,sark and felt 80m sq per day (up to 12m span measured at horizantial)
Page 4 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Hip or valley up to 12m long 1 man a day Medium dormer window (2.4m wide) 1 man a day
I hope this helps , but please bare in mind that the more complex projects will take longer.
Timber Frames...
Task / Description Slow Ave Fast Units
Roof Trusses - 1.3 - no/hr
Wall Plates - 2.7 - m/hr
Roof Rafters - 1.2 - m/hr
Ceiling Joists - 32.1 - m/hr
Roof Carcass, Common Rafters, under 3m 18.2 20.0 21.7 no/hr
Roof Carcass, Common Rafters, 3-6mm 13.3 16.6 18.2 no/hr
Roof Carcass, Common Rafters, over 6m 14.1 15.6 16.1 no/hr
Roof Carcass, Jack Rafters, under 3m 18.8 20.1 21.7 no/hr
Roof Carcass, Jack Rafters, 3-6mm 10.4 16.1 16.6 no/hr
Roof Carcass, Purlins, under 3m 5.1 5.4 5.8 no/hr
Roof Carcass, Purlins, 3-6mm 4.3 4.8 5.1 no/hr
Roof Carcass, Purlins, over 6m 3.5 4.3 4.6 no/hr
Roof Carcass, Binders, under 3m 5.7 6.6 7.6 no/hr
Roof Carcass, Binders, 3-6mm 2.1 2.3 2.5 no/hr
Roof Carcass, Binders, over 6m 1.3 1.5 1.6 no/hr
Roof Carcass, Hangers, under 3m 8.2 9.0 9.6 no/hr
Roof Carcass, Collars under 3m 7.6 8.0 9.1 no/hr
Roof Carcass, Collars 3-m 6.5 7.4 8.3 no/hr
Roof Carcass, Ridge Boards under 3m 12.0 13.1 15.3 no/hr
Roof Carcass, Cut Rafter Feet to line 142.0 166.0 175.0 no/hr
Roof Soffits, Softwood, nailed - 9.2 - m/hr
Roof Soffits, Softwood, screwed - 3.9 - m/hr
Roof Soffits Asbestos, under 300mm nailed - 9.1 - m/hr
Roof Soffits Asbestos, under 300mm screwed - 3.8 - m/hr
Roof Soffits, Asbestos, over 300mm nailed - 3.5 - m/hr
Roof Soffits, Asbestos, over 300mm screwed - 1.3 - m/hr
Roof Facia Panels, Softwood 5.1 7.2 9.3 m/hr
Roof Facia Panels, Asbestos 1.3 2.5 3.9 m/hr
Roof Facia Panel Studding, nailed 7.3 8.1 9.0 m/hr
Roof Facia Panel Studding, screwed 4.6 5.2 5.8 m/hr
Roof Facia Panel Studding, bolted to beams 5.4 5.9 6.6 m/hr
Roof Works, Fix Herringbone Strutting - 5.1 - m/hr
Roof Works, Fix Firing Strips - 25.0 - m/hr
Roof Works, Fix Drip/Tilt Filleting - 20.5 - m/hr
ChasesChases
Cutting Chases In BrickworkIn Brickwork (m/hr)
Page 5 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
By Hand
Chase depth -->
0-25mm 25-37mm 37-50mm
Ne 25 mm wide
4.17 2.78 2.08
25-50 mm wide
3.45 2.27 1.69
50-75 mm wide
2.86 1.92 1.45
75-100 mm wide
2.50 1.67 1.23
Machine
Ne 25 mm wide
11.1 5.56 4.17
25-50 mm wide
6.67 4.55 3.33
50-75 mm wide
6.67 4.55 3.33
75-100 mm wide
5.00 3.33 2.50
Cutting Chases In ConcreteIn Concrete (m/hr)
By Hand
Chase depth -->
0-25mm 25-37mm 37-50mm
Ne 25 mm wide
3.03 2.04 1.54
25-50 mm wide
2.50 1.67 1.25
50-75 mm wide
2.13 1.41 1.05
75-100 mm wide
1.82 1.22 0.92
Machine
Chase depth -->
0-25mm 25-37mm 37-50mm
Ne 25 mm wide
5.88 4.00 3.03
25-50 mm wide
5.00 3.33 2.50
50-75 mm wide
4.17 2.86 2.13
75-100 mm wide
3.70 2.44 1.81
Page 6 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Cutting Chases In Heavyweight BlockworkIn Heavyweight Blockwork (m/hr)
By Hand
Chase depth -->
0-25mm 25-37mm 37-50mm
Ne 25 mm wide
3.85 2.63 1.96
25-50 mm wide
3.23 2.17 1.64
50-75 mm wide
2.70 1.82 1.36
75-100 mm wide
2.33 1.56 1.18
Machine
Ne 25 mm wide
7.69 5.00 3.85
25-50 mm wide
6.25 4.17 3.13
50-75 mm wide
5.26 3.57 2.70
75-100 mm wide
4.55 3.13 2.33
Cutting Chases In Lightweight BlockworkIn Lightweight Blockwork (m/hr)
By Hand
Chase depth -->
0-25mm 25-37mm 37-50mm
Ne 25 mm wide
7.69 5.00 3.85
25-50 mm wide
6.25 4.17 3.13
50-75 mm wide
5.26 3.45 2.63
75-100 mm wide
4.55 3.03 2.27
Machine
Chase depth -->
0-25mm 25-37mm 37-50mm
Ne 25 mm wide
14.2 10.0 7.69
25-50 mm wide
11.1 7.69 5.88
50-75 mm wide
10.0 7.14 5.26
Page 7 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
75-100 mm wide
9.09 6.25 4.76
Cutting Switch BoxesCutting Switch Boxes etc (No/hr)
Box Type -->
Small Large
Concrete Hand 7.14 3.57
Machine 12.5 5.56
Brickwork Hand 6.67 4.17
Machine 12.5 6.25
Lightweight Blockwork Hand
Hand Machine
20.0 25.0 10.0 14.3
Heavyweight Blockwork Hand
Hand Machine
7.69 12.5 3.85 5.88
Computer Room / Raised FloorsTypically installed by a 2 man gang
Medium sized room incl cutting 2.67 m2/hr
Concrete Related Works
Formwork
Beam Falsework FormworkRates include for making, fixing, cleaning and minor repair works etc, rates in m2/hr.
Soffits - On runners and props, including erection of props etc.
Hight of Beam Soffit--->
0 - 3.5 m 3.5 - 5.0 m
Width Fix Strike Fix Strike
100 - 200 mm
0.70 1.23 0.58 1.02
200 - 300 mm
0.81 1.39 0.68 1.15
300 - 500 mm
0.93 1.54 0.78 1.28
500 - 750 mm
1.16 1.85 0.96 1.54
1.23 2.17 1.03 1.82
Page 8 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
exc 750 mm
Soffits - On runners and props, on previously erected props etc.
Hight of Beam Soffit--->
0 - 3.5 m 3.5 - 5.0 m
Width Fix Strike Fix Strike
100 - 200 mm
0.96 1.69 0.91 1.67
200 - 300 mm
1.11 1.92 1.05 1.82
300 - 500 mm
1.27 2.08 1.20 2.00
500 - 750 mm
1.56 2.50 1.49 2.44
exc 750 mm
1.64 2.86 1.39 2.70
Sides - Strutted from soffit bearers etc.
Hight of Beam Soffit--->
0 - 3.5 m 3.5 - 5.0 m
Depth Fix Strike Fix Strike
100 - 200 mm
0.78 1.23 0.74 1.18
200 - 300 mm
0.93 1.39 0.88 1.32
300 - 500 mm
1.06 1.54 1.02 1.47
500 - 750 mm
1.47 2.08 1.39 2.00
exc 750 mm
1.54 2.33 1.47 2.33
Sides - Using clamps and struts etc.
Hight of Beam Soffit--->
0 - 3.5 m 3.5 - 5.0 m
Depth Fix Strike Fix Strike
100 - 200 mm
0.91 1.47 0.87 1.39
200 - 300 mm
1.09 1.64 1.04 1.56
300 - 500 mm
1.27 1.82 1.20 1.72
Page 9 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Columns FormworkRates include for fixing, cleaning and minor repair works etc, rates in m2/hr unless otherwise stated.
Cross Sectional Area-->
Ne 0.2 m2 Exc 0.2 m2
Item Fix Strike Fix Strike
Kickers-Direct to slab (no/hr)
4.00 12.50 2.63 8.33
Kickers-Suspended (no/hr)
2.08 12.50 1.39 8.33
Square Sides-Timber Clamped and Propped Column Height--->
2 - 3 m 3 - 4 m
Item Fix Strike Fix Strike
Cross Section
0.00 - 0.05 m2
1.35 2.70 1.67 3.57
0.05 - 0.10 m2
1.69 3.45 1.82 3.85
0.10 - 0.20 m2
1.82 4.00 2.33 4.55
0.20 - 0.40 m2
2.04 4.55 2.44 5.00
exc 0.40 m2
2.33 5.26 2.50 5.88
Footing formwork
Activity TASKSTask - UOM
Labor (L) - Carpenter (Mandays)
Labor (L) - Helper (Mandays)
Material (M) Material (M) Material (M)
Footing formwork
Footing - Shuttering & Providing Support
Sqm 0.8 Mandays/10Sqm1.5 Mandays/10Sqm
MS Wall Form Panel - 1250 x 500 : 16Nos/10Sqm
Props - 2m to 3m Long : 2 Nos/Rm
Shuttering Oil : 4Ltr/10Sqm
Footing - Deshuttering & insitu Stacking
Sqm 0.48 Mandays/10Sqm0.9 Mandays/10Sqm
Formwork & Falsework - Ground Foundation FormworkFORMWORK & FALSEWORK
Ground Foundation Formwork All formwork rates in m2/hr.
Page 10 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Item Shutter size Fix Strike
To Pilecaps 0.75 m2 1.64 3.85
0.75 - 1.50 m2 1.82 4.55
1.50 - 2.25 m2 2.00 5.00
2.25 - 3.00 m2 2.22 5.56
exc 3.00 m2 2.50 7.14
To Foundations
0.75 m2 1.72 4.55
0.75 - 1.50 m2 1.82 4.55
1.50 - 3.00 m2 2.50 6.25
3.00 - 5.00 m2 2.63 6.67
To Ground Beams
1.50 m2 1.82 4.55
1.50 - 3.00 m2 2.63 6.67
3.00 - 5.00 m2 2.70 7.14
FormworkFormwork
Task / Description Slow Ave Fast Units
Pilecaps, < 0.7m2 0.9 1.6 2.0 m2/hr
Pilecaps, 0.7-2.5m2 1.6 2.0 2.3 m2/hr
Pilecaps, 2.5-3.0m2 2.0 2.3 2.5 m2/hr
Pilecaps, > 3.0m2 2.3 2.5 3.1 m2/hr
Ground Beams, < 0.7m2 1.1 1.7 1.8 m2/hr
Ground Beams, 0.7-1.5m2 1.7 1.8 2.5 m2/hr
Ground Beams, 1.5-3.0m2 1.8 2.5 2.6 m2/hr
Ground Beams, 3.0-5.0m2 2.5 2.6 3.5 m2/hr
Elevated Plain Slab Soffit 0.6 0.8 1.2 m2/hr
Beams, on erected falsework, width 100-200mm 0.9 1.0 1.1 m2/hr
Beams, on erected falsework, width 200-300mm 1.0 1.1 1.3 m2/hr
Beams, on erected falsework, width 300-500mm 1.2 1.3 1.5 m2/hr
Beams, on erected falsework, width 500-750mm 1.5 1.6 1.8 m2/hr
Beams, on erected falsework, width over 750mm 1.4 1.5 1.7 m2/hr
Walls, Construct Kickers 5.3 7.1 10.0 m2/hr
Walls, Fully Framed Formwork/Struts, 1.0-2.0m2 0.9 1.8 1.9 m2/hr
Walls, Fully Framed Formwork/Struts, 2.0-5.0m2 1.0 2.2 2.5 m2/hr
Walls, Fully Framed Formwork/Struts, over 5.0m2 1.2 2.5 2.9 m2/hr
Walls, StoriForm Shutters, 1.0-3.0m2 1.0 1.4 2.0 m2/hr
Walls, StoriForm Shutters, 3.0-5.0m2 1.9 2.3 3.3 m2/hr
Walls, StoriForm Shutters, 5.0-10.0m2 2.3 2.8 3.5 m2/hr
Walls, StoriForm Shutters, 10.0-15.0m2 3.2 4.5 4.0 m2/hr
Walls, StoriForm Shutters, over 15.0m2 3.8 4.8 5.4 m2/hr
Ground Slabs 1.0 1.5 1.8 m2/hr
Columns, Construct Kickers, direct to slab 3.2 4.1 5.4 no/hr
Page 11 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Columns, Construct Kickers, suspended from soffit slab 1.2 2.8 3.2 no/hr
Columns, Square Sides, Timber Clamp/Prop, csa < 0.1m2 1.3 1.6 1.8 m2/hr
Columns, Square Sides, Timber Clamp/Prop, csa 0.1-0.4m2 1.8 2.1 2.4 m2/hr
Columns, Square Sides, Timber Clamp/Prop, csa over 0.4m2 2.0 2.3 2.5 m2/hr
Columns, Square Sides, Steel Forms, 1.5 x 1.5 x 9.0m high 7.9 9.5 10.3 m2/hr
Columns, Square Sides, Steel Forms, 2.0 x 2.0 x 9.0m high 6.9 7.5 8.3 m2/hr
Columns, Square Sides, Steel Forms, 2.0 x 4.0 x 9.0m high 8.5 10.2 12.0 m2/hr
Columns, Round Sides, Sacrificial Plastic Mould, 3.0-4.0m dia 3.5 4.5 6.0 m2/hr
Columns, Round Sides, Steel Mould, 3.0-4.0m dia 5.2 6.5 7.5 m2/hr
Columns, Sloping Column Heads, extra over rate - 2.5 3.5 hrs/no
Staircases, Stair Soffit, Sloping 0.7 0.8 1.0 m2/hr
Staircases, Stair Soffit, Flat Landing 0.8 0.9 1.2 m2/hr
Staircases, Wall Strings 0.4 0.6 - m2/hr
Staircases, Open Strings 0.7 0.8 - m2/hr
Staircases, Riser Boards fixed to strings - 2.5 2.8 m2/hr
Staircases, Risers fixed to Strings - 2.3 2.6 m2/hr
Waffle Flooring, 2.4m grid 1.1 1.4 1.8 m2/hr
Shaft Slip Forming - 300.0 500.0 mm/hr
Table Form, Aluminum System, 400m2 bays 2.1 3.2 3.8 m2/hr
Table Form, H-Frame Steel Falsework, 400m2 bays 1.9 3.0 3.5 m2/hr
Tunnel Forms, Wall and Slab poured as one - 15.6 17.5 m2/hr
Hollorib Decking, lay deck - 43.5 47.5 m2/hr
Hollorib Decking, shear connecting studs - 29.3 31.2 m2/hr
Stop Ends, no perforations 2.8 3.5 4.2 m2/hr
Stop Ends, minor perforations 1.2 1.5 1.9 m2/hr
Stop Ends, dense perforations 0.9 1.1 1.4 m2/hr
Box Outs, 0.01-0.05m2 7.6 8.2 9.1 no/hr
Box Outs, over 0.05m2 3.1 3.9 4.5 no/hr
Dummy Frames, under 3.0m2 4.5 6.2 7.1 no/hr
Dummy Frames, over 3.0m2 3.1 3.7 4.5 no/hr
Formwork Re-UseTypical rate for number of formwork uses before shutter remake. NOTE: This varies significantly depending on care taken with shutters and programme time available etc.
Walls = 20 uses Slab Soffits = 10 - 15 uses Beam & Column Boxes = 30 uses
Hollorib DeckingHollorib Decking
Lay decking = 350 m2/day
Shear Connecting Studs 235 m2 studded per day per gun (4,000 studs/week)
Concrete topping = 4,000 m2/week or 2,000 m2/week incl power floating
Raft formwork
Page 12 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Activity TASKSTask - UOM
Labor (L) - Carpenter (Mandays)
Labor (L) - Helper (Mandays)
Material (M) Material (M) Material (M)
Raft formwork
Raft - Shuttering & Providing Support
Sqm 0.71 Mandays/10Sqm1.41 Mandays/10Sqm
MS Wall Form Panel - 1250 x 500 : 16Nos/10Sqm
Props - 2m to 3m Long : 2 Nos/Rm
Shuttering Oil : 4Ltr/10Sqm
Raft - Deshuttering & insitu Stacking
Sqm 0.42 Mandays/10Sqm0.84 Mandays/10Sqm
Ramp formwork
Activity TASKS Task - UOMLabor (L) - Carpenter (Mandays)
Labor (L) - Helper (Mandays)
Material (M) Material (M) Material (M)
Ramp formwork
Ramp - Shuttering & Providing Support
Sqm 0.22 Mandays/Sqm0.44 Mandays/Sqm
MS Floor Form Panel - 750 x 600 - 13.3Nos/10Sqm
MS Floor Form Panel - 1250 x 500 : 6.4Nos/10Sqm
Adjustable Props - 2.02m to 3.75 m : 2Nos/Sqm and Shuttering Oil : 5Ltr/10Sqm
Ramp - Deshuttering & Stacking Appropriately at Same Location
Sqm 0.13 Mandays/Sqm0.26 Mandays/Sqm
Shades Formwork
Activity TASKS Task - UOMLabor (L) - Carpenter (Mandays)
Labor (L) - Helper (Mandays)
Material (M) Material (M)Material (M)
Shades Formwork
Weather Shade, Chajjas, Corbels Shuttering (Including Propping)
Sqm 0.12 Mandays/Sqm0.14 Mandays/Sqm
MS Floor Form Panel - 750 x 600 - 2.2Nos/Sqm
Adjustable Props - 2.02m to 3.75 m : 2Nos/Sqm
Shuttering Oil : 0.3Ltr/Sqm
Page 13 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Weather Shade, Chajjas, Corbels - Deshuttering & Stacking Appropriately at Same Location
Sqm 0.07 Mandays/Sqm
0.08 Mandays/Sqm
Staircase formwork
Activity TASKSTask - UOM
Labor (L) - Carpenter (Mandays)
Labor (L) - Helper (Mandays)
Material (M) Material (M) Material (M)
Staircase formwork
Staircase (Excluding Spiral Staircase) - Shuttering & Providing Support
Sqm 0.23 Mandays/Sqm0.46 Mandays/Sqm
MS Floor Form Panel - 750 x 600 - 2.2Nos/Sqm
Adjustable Props - 2.02m to 3.75 m : 2Nos/Sqm
Shuttering Oil : 5Ltr/10Sqm
Staircase (Excluding Spiral Staircase) - Deshuttering & Stacking Appropriately at Same Location
Sqm 0.14 Mandays/Sqm0.28 Mandays/Sqm
Tunnel FormsConcrete - Tunnel Forms A system of forms which enables walls and slabs to be cast in the same pour. suited to buildings with large number of identically sized rooms, such as hotels or flats. Used in conjunction with high speed concrete pumps, pre-formed reinforced cages.
RatesSetup 14 days
Slab & Walls 125 m2/day (equals 3.5 rooms)
Dismantle 7 days
Waffle FlooringRate includes for erection of decking and infill beams, cut position & nail plywood ribs, transport position and fix 800 mm x 800 mm waffle forms, clean and oil plywood and adjust to levels (m2/hr). Conservative Erection Rate...
2.4 m grid, ne 3.5 m high soffit = 1.42 m2/hr 3.5 - 5.5 m high soffit = 1.13 m2.hr
Typical composite rate of 18.5 m2/day per 4 man gang. Rate includes decking, waffles and reinforcement fixing.
Walls formwork
Page 14 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Activity TASKS Task - UOM
Labor (L) - Carpenter (Mandays)
Labor (L) - Helper (Mandays)
Material (M) Material (M)
Material (M)
Walls formwork
Walls (Any Thickness), Including Buttresses - Shuttering & Providing Support - Up to 3.5m Height
Sqm
2.22 Mandays/10Sqm(Including Both Sides)
2.64 Mandays/10Sqm(Including Both Sides)
MS Wall Form Panel - 1250 x 500 - 32 Nos/10Sqm(Including Both Sides)
Props - 2m to 3m Long : 4Nos/Rm(Including Both Sides)
Shuttering Oil : 5Ltr/10Sqm(On One Side)
Walls - Deshuttering & insitu Stacking
Sqm
1.32 Mandays/10Sqm(Including Both Sides)
1.76 Mandays/10Sqm(Including Both Sides)
Making Good ConcreteRates including blowing out, preparations, clean and shutter joints and making a fair faced finish.
By Hand
With Mechanical Sander
Walls 5.56 m2/hr
8.62 m2/hr
Columns 2.80 m2/hr
6.99 m2/hr
Sides and Soffits of Beams
2.80 m2/hr
6.99 m2/hr
Soffits of Slabs
4.21 m2/hr
7.58 m2/hr
Vertical Bolt Holes
16.67 no/hr
Horizontal Bolt Holes
14.49 no/hr
Vertical Shutter Joints
28.57 m/hr
Horizontal Shutter Joints
25.00 m/hr
Rub Down Precast Concrete
16.95 m2/hr
Scabble
Single head brush hammer
0 - 4 mm 30.74 hrs/m2
0 - 8 mm 59.14 hrs/m2
Three head brush hammer
0 - 4 mm 37.14 hrs/m2
0 - 8 mm
Page 15 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
71.12 hrs/m2
Mixing ConcreteMixing By Hand
A typical rate of 0.32 m3/hr of concrete. Compulsory Paddle Mixer Generally with one or two 3.5m3 drums, giving a cycle time of 60 to 80 seconds (m3/Hr). Mix Time --> 60 secs 80 secs
Single drum plant
210 158
Double drum plant
420 315
Task / Description Slow Ave Fast Units
Concrete Weight, 1m3 - 2.4 - Tonnes
Readymix Lorry, Length - 8.3 - m
Readymix Lorry, Width - 2.5 - m
Readymix Lorry, Height - 3.7 - m
Readymix Lorry, Length - 24.4 - Tonnes
Readymix Lorry, Turning Circle - 16.4 - m
Readymix Lorry, Allowable Access Ramp Gradient - 17.0 20.0 degrees
Mixing Concrete, By Hand - 0.3 - m3/hr
Mixing Concrete, Single Drum Paddle Mixer 158.0 180.0 210.0 m3/hr
Mixing Concrete, Double Drum Paddle Mixer 315.0 370.0 420.0 m3/hr
Mixing Concrete, Single Drum Plant Pan Mixer - 120.0 - m3/hr
Mixing Concrete, Dry Mix Plant - 90.0 - m3/hr
CONCRETINGProperties
1 m3 of concrete weights 2.4 tonnes Skip Capacities Dual Flow Skips Skip Size
Qty Per Lift
Laiden Weight
0.50 m3 0.44 m3 1,261 kg
0.75 m3 0.68 m3 1,850 kg
1.00 m3 0.94 m3 2,585 kg
Rollover Skips, Front discharge Skip Size
Qty Per Lift
Laiden Weight
0.50 m3 0.44 m3 1,361 kg
0.75 m3 0.68 m3 2,057 kg
Readymix Lorries
- Length 8.23 m
- Width 2.43 m
- Height 3.66 m
Page 16 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
- Weight 24.38 tonnes
- Turning Circle
16.36 m
Dry Lean ConcreteFrom readymix truck and spade finish (m3/hr).
Roads and Runway Areas
1.39
Paths 0.57
Drains, tipped direct
0.85
Drains, thrown in
0.68
Placement & Finishing
Concrete Cycle TimesBlinding Concrete
Placing blinding direct from ready mix truck, rate of 4-5 m2/hr or 0.2-0.3 m3/hr.
Base / Floor Slabs
Concourse slab concrete pour, 36 m x 18 m, concrete volume of 1,500 m3 and 290 tonnes of reinforcement. Blind 1 day, formwork 2 days, reinforcement 5 days and concrete on day 8. Adit base slabs, concrete volume of 140 m3. Steelfixing for 4 days and concrete on the 5th day.
Tunnel Sections
Simple cooling watermain tunnels, a typical cycle time of 5 days per 8 m sections, or a rate of 0.16 m/hr.
Track Slab
Track slab concrete pour, 36 m x 28 m, concrete volume of 1,050 m3 and 360 tonnes of reinforcement. Excavate 6 m from one edge 7 days, strut 9 days, final excavation 3 days, pile chipping 5 days, blind 4 days, reinforcement 5 days and concrete on day 32. On simple pours, with little formwork, 24 m x 28 m, concrete volume of 1,200 m3 and 220 tonnes of reinforcement. Blind 3 days, reinforcement 3 days and concrete on day 8.
Wall Slabs
Adit wall construction, concrete volume of 80 m3. Steelfixing for 3 days and concrete on 4th day.
Roof Slabs
Adit roof slab construction, concrete volume of 80 m3. Steelfixing for 4 - 5 days and concrete on the 6th day.
Staircases
Standard staircase, concrete volume of 60 - 80 m3. Steelfixing for 4 days, formwork for 3 days and concrete on the 7 th day. Simple staircase from track slab up to platform edge, a rise of 1.2 m, a typical cycle time of 3 days per flight.
Slip FormingConcrete - Slip Forming
A typical period of 10 - 14 days is required to setup the shutter on the ground and cast the platform.
Rate of climb of formwork = 200 - 300 mm/hr.
Page 17 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Table FormsConcrete - Table Forms
Fast method of forming walls/slabs with movable shutter. This rate is inclusive of walls and columns etc.
Rate of 100 - 150 m2/day
Concrete FinishingConcrete Finishing
Task / Description Slow Ave Fast Units
Surface Finishing, Steel Float By Hand 9.2 13.9 25.0 m2/hr
Surface Finishing, Wood Float By Hand 11.7 17.2 29.4 m2/hr
Surface Finishing, Power Float 13.9 20.8 37.0 m2/hr
Surface Finishing, Light Brush on Trowel 55.8 90.1 170.0 m2/hr
Surface Finishing, Brush on Trowel Margin 28.8 48.5 85.0 m2/hr
Surface Finishing, Sprayed By Pump, expose aggregate 65.0 95.0 145.0 m2/hr
Surface Finishing, Wire Brush, expose aggregate 15.0 25.0 30.0 m2/hr
Making Good Walls, prepare, shutter, pour - 5.5 8.6 m2/hr
Making Good Columns, prepare, shutter, pour - 2.8 6.9 m2/hr
Making Good Sides of Beams, prepare, shutter, pour - 2.8 7.0 m2/hr
Making Good Slab Soffits, prepare, shutter, pour - 4.2 5.5 m2/hr
Making Good Bolt Holes, prepare, shutter, pour 14.8 16.8 25.8 no/hr
Making Good Rubdown Precast Concrete, prepare, shutter, pour - 18.0 - m2/hr
Making Good Scabble 3 head brush hammer, prepare, shutter, pour 30.7 59.5 73.8 hrs/m2
Concrete Finishes (m2/hr).
Area Finished -->
0-40 m2 40-200 m2 exc 200 m2
Steel Float by Hand
9.26 13.89 25.00
Wood Float by Hand
11.76 17.24 29.41
Power Float
13.89 20.83 37.04
Light Brush on Trowel
55.56 90.91 166.67
Brush on Trowel Margin
27.78 45.45 83.33
Sprayed using hand pump
55.56 90.91 142.86
Wire Brush, expose agg
6.99 11.76 20.83
Page 18 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Concrete PumpingLarge Concrete Pours, lorry pump.
Simple Rule Of Thumb, concretors 0.5 - 1.0 hrs/m3 of concrete, depending on access, pour size and concrete availability.
Base Slabs etc, 1,200m3 equalling 25 - 35m3/hr per pump, with 3 No pumps and 12 men for 2 shifts of 12 hrs.
OFC LayingOFC Laying
By Using Concrete/Road Cutter Equipment
Resources
Survey Team of 4 (1 Suveyor , 3 Assistants) Equipment with Operator and Helper Cutting Line Marking team ( 2-3 Persons) OFC cable laying team ( 4 Persons) Splicing team (2 technicians )
Productivity
if everything is planned properly with adequate overlap of 3-4 days. 400-500m/day can be achieved.
By using trenching machine
Equipment with Operator and helper Mini Dozer with operator OFC Laying laying team (6-8 persons) Rest resources as per above
Productivity
If everything has planned properly with adequate overlap of 2-3 days. 250-300m/day can be achieved.
Place Concrete Barrowing Concrete (m3/hr).
Receive concrete from mixer/lorry direct to barrow, wheel to placing position, tip and return.
Distance 0 - 10 m 2.32
10 - 20 m 1.81
20 - 50 m 1.08As above but including load concrete from deck/tray. Distance 0 - 10 m 0.99
10 - 20 m 0.87
20 - 50 m 0.66
Extra over to place direct, for dump and shovel in from side, a typical rate of 0.26 hrs/m3.Direct From Ready Mix Lorry (m3/hr). Type Ready
MixVia Dumper
Via Dumper
Tip Direct
Tip Direct Thrown In
Mass Fill 3.12 2.56 1.49
50mm Blinding
1.27 1.06 0.82
Ground Beams ne 0.1 m2 SA
1.52 1.30 1.00
Page 19 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Ground Beams ex 0.1 m2 SA
1.69 1.49 1.16
Pile Caps ne 0.1 m2 SA
1.16 1.06 0.79
Pile Caps ex 0.1 m2 SA
2.56 2.13 7.69
Duct Walls 0.78 0.71 0.52
Stub Columns
0.43 0.39 0.29
Ground Slab ne 155 mm
2.13 1.82 1.22
Ground Slab 150-300 mm
2.33 1.96 1.27
Ground Slab 300-500 mm
2.56 2.13 1.35
Drains, Bed & Cover
0.91 0.85 0.73
By Lorry Mounted Concrete Pump (m3/hr). Thickness -->
13.5 m3/hr 18 m3/hr
Solid Slabs ne 100 mm
2.17 2.63
100 - 150 mm
2.44 2.94
150 - 200 mm
2.63 3.23
200 - 300 mm
2.86 3.45
300 - 500 mm
3.23 3.85
Coffered Slabs 1.64 1.82
Columns 0.5 - 0.10 m2
1.59 1.59
exc 0.10 m2
1.82 1.82
Wall ne 150 mm
1.61 1.89
150 - 225 mm
1.89 2.33
exc 225 mm
2.56 3.23
Independent Beams
1.54 1.54
Stairs and Landings
1.27 1.89
By Dumper, From Ready Mix Lorry To Position (m3/hr). Dumper Capacity -->
0.6 m3 0.8 m3 1.2 m3 1.5 m3 2.3 m3
0 - 20 m 10.41 14.08 18.82 25.00 33.33
Page 20 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
20 - 50 m
9.09 12.36 16.39 22.22 29.41
50 - 100 m
7.29 10.41 13.88 18.86 25.00
100 - 250 m
5.78 7.87 10.00 13.51 18.18
250 - 500 m
3.65 4.95 8.33 8.95 12.35
500 - 750 m
2.16 2.92 4.27 5.43 7.87
750 - 1,000 m
- - - 3.97 5.78
By Tower/Mobile Crane (m3/hr). 0.4 m Skip
0.6 m Skip
0.8 m Skip
Pile Caps SA ne 2 m2
1.19 1.39 1.61
Mass Fill Pours
SA 2-5 m3
1.75 2.04 2.33
ne 10 m3
3.70 4.17 4.76
10-25 m3
4.00 4.55 0.84
exc 25 m3
4.35 5.00 5.86
Slabs ne 100 mm
0.90 1.09 1.21
100-150 mm
1.09 1.31 1.47
150-200 mm
1.26 1.53 1.69
200-300 mm
1.26 1.53 1.69
Exc 300 mm
1.38 1.66 1.85
Trough & Coffered Slabs
0.95 1.09 1.21
Structural Topping ne 100 mm
0.90 1.09 1.25
Stairs & Landings
0.64 0.64 0.64
Blinding ne 150 mm
0.88 1.00 1.10
Beams SA 0-0.05 m
0.52 0.58 0.69
SA 0.05-0.1 m
0.58 0.65 0.78
SA ex 0.1 m
0.76 0.85 1.02
Walls ne 100 mm
0.64 0.76 0.88
Page 21 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
100-150 mm
0.76 0.92 1.05
150-300 mm
0.95 1.11 1.28
exc 300 mm
1.10 1.28 1.47
Columns SA ne 0.05 m2
0.43 0.45 0.48
SA 0.05-0.1 m2
0.48 0.50 0.54
SA ex 0.1 m2
0.51 0.53 0.57
Concrete Placement
Task / Description Slow Ave Fast Units
Placing concrete, lorry based pump 30.0 40.0 50.0 m3/hr
Hollorib Decking, concrete topping 85.0 100.0 120.0 m2/hr
Hollorib Decking, concrete topping, incl PowerFloat 40.0 50.0 70.0 m2/hr
Placing Concrete, By Wheelbarrow over 1-10m 2.1 2.3 2.5 m3/hr
Placing Concrete, By Wheelbarrow over 10-20m 1.5 1.8 2.1 m3/hr
Placing Concrete, By Wheelbarrow over 20-50m 0.8 1.1 1.5 m3/hr
Placing Direct From Readymix Lorry, Mass Fill 2.8 3.1 3.3 m3/hr
Placing Direct From Readymix Lorry, 50mm Blinding - 1.3 1.6 m3/hr
Placing Direct From Readymix Lorry, Ground Beams 1.5 - 1.7 m3/hr
Placing Direct From Readymix Lorry, Pile Caps 1.0 1.5 2.3 m3/hr
Placing Direct From Readymix Lorry, Duct Walls - 0.8 1.1 m3/hr
Placing Direct From Readymix Lorry, Stub Columns - 0.4 0.6 m3/hr
Placing Direct From Readymix Lorry, Ground Slab 2.1 2.3 2.6 m3/hr
Placing Direct From Readymix Lorry,Drains Bed and Cover - 0.9 1.0 m3/hr
Placing From Tower Crane, Pile Caps 1.2 1.4 1.6 m3/hr
Placing From Tower Crane, Mass Fill 4.0 4.5 5.5 m3/hr
Placing From Tower Crane, Slabs under 150mm thick 0.9 1.3 1.7 m3/hr
Placing From Tower Crane, Slabs over 150mm thick 1.2 1.5 1.8 m3/hr
Placing From Tower Crane, Trough/Coffered Slabs 0.9 1.1 1.2 m3/hr
Placing From Tower Crane, Stairs and Landings 0.6 0.7 0.9 m3/hr
Placing From Tower Crane, Blinding 0.8 1.0 1.1 m3/hr
Placing From Tower Crane, Beams under 150mm thick 0.5 0.6 0.8 m3/hr
Placing From Tower Crane, Beams over 150mm thick 0.6 0.8 1.0 m3/hr
Placing From Tower Crane, Walls 0.6 1.1 1.5 m3/hr
Placing From Tower Crane, Columns 0.4 0.5 0.6 m3/hr
Post Tensioning Works
Post TensioningConcrete - Post Tensioning Sequence:
Concrete poured 1st Bay. After 48 hrs concrete is stressed to initial strength (15 kN takes 1 day). 5 days after initial stressing, concrete is stressed to final strength (30 kN takes 1 day).
Page 22 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Formwork may now be struck and adjacent bay poured.
Post Tensioning
Task / Description Slow Ave Fast Units
Lag for Initial Stress Tensioning after 1st bay cast - 48.0 - hrs
Lag for Final Stress Tensioning after Initial Stress - 120.0 - hrs
Pre-Cast Works
PRECAST CONCRETE FLOOR SYSTEMSPlank Elements (crane handled)
Rates given in hours/plank.
Plank Lengths
ne 3m 3-6m ex 6m
Activity
Unload/stack at ground level
0.016 0.019 0.022
Unload/stack upper levels
0.021 0.024 0.028
Sling from ground to levels
0.019 0.021 0.025
Place in position from stack
0.120 0.150 0.180
Block Elements Rates given in hours/thousand blocks.
Block Thickness
75-125mm
125-200mm
ex 200mm
Activity
Unload pallets/stack on ground
By forklift
0.90 1.02 1.20
By Crane
1.20 1.26 1.38
Unload pallets/stack at upper levels
By forklift
1.50 1.62 1.80
By Crane
2.34 2.40 2.70
Sling from ground to levels
By forklift
1.44 1.56 1.74
By Crane
1.56 1.62 1.80
Place in position from stacks
12.00 13.80 15.00
Reinforcement
Footing Reinforcement
Page 23 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Activity TASKSTask - UOM
L - Barbender/Fitter (Mandays)
L - Helper (Mandays) M M M
Footing Reinforcement
Foot Rein - Placing in Position & Binding - Using TMT Bars, Mild Steel, Tor Steel
Mt 0.28 Mandays/0.1Mt0.38 Mandays/0.1Mt
Bars - Include 5% Wastage
Binding Wire : 5 kg/0.1Mt
Cover Blocks - 10No/0.1Mt
Foot Rein - Straightening, Cutting (With Machine Cutting), bending - Using TMT Bars, Mild Steel, Tor Steel
Mt 0.2 Mandays/0.1Mt0.28 Mandays/0.1Mt
Bars - Include 5% Wastage
Foot Rein - Straightening, Cutting (With Manual Cutting), bending - Using TMT Bars, Mild Steel, Tor Steel
Mt 0.29 Mandays/0.1Mt0.32 Mandays/0.1Mt
Bars - Include 5% Wastage
ReinforcementMesh reinforcement - to slabs = 10.5 m2/hr
Mesh reinformcement - to beams/columns = 2.5 m2/hr
Reinforcement
Task / Description Slow Ave Fast Units
Slabs/Foundations, steelfixing, 6mm 40.3 38.4 36.5 hrs/tonne
Slabs/Foundations, steelfixing, 8mm 28.2 26.9 25.8 hrs/tonne
Slabs/Foundations, steelfixing, 10mm 22.5 20.6 20.1 hrs/tonne
Slabs/Foundations, steelfixing, 12mm 16.9 16.3 15.4 hrs/tonne
Slabs/Foundations, steelfixing, 16mm 12.0 11.5 10.9 hrs/tonne
Slabs/Foundations, steelfixing, 20mm 9.2 8.6 8.2 hrs/tonne
Slabs/Foundations, steelfixing, 25mm 6.9 6.7 6.5 hrs/tonne
Slabs/Foundations, steelfixing, 32mm 5.7 5.5 5.2 hrs/tonne
Slabs/Foundations, steelfixing, 40mm 5.3 5.1 4.9 hrs/tonne
Slabs/Foundations, steelfixing, 50mm 5.2 4.9 4.6 hrs/tonne
Beams/Columns, steelfixing, 6mm 55.4 52.8 50.6 hrs/tonne
Beams/Columns, steelfixing, 8mm 38.8 37.0 35.1 hrs/tonne
Beams/Columns, steelfixing, 10mm 29.5 28.4 26.9 hrs/tonne
Beams/Columns, steelfixing, 12mm 23.4 22.4 21.9 hrs/tonne
Beams/Columns, steelfixing, 16mm 16.6 15.8 15.1 hrs/tonne
Beams/Columns, steelfixing, 20mm 12.4 11.9 11.3 hrs/tonne
Beams/Columns, steelfixing, 25mm 9.9 9.2 8.7 hrs/tonne
Beams/Columns, steelfixing, 32mm 6.8 6.6 6.2 hrs/tonne
Page 24 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Beams/Columns, steelfixing, 40mm 6.1 5.9 5.6 hrs/tonne
Beams/Columns, steelfixing, 50mm 6.1 5.9 5.6 hrs/tonne
Walls, steelfixing, 6mm 41.2 40.8 39.1 hrs/tonne
Walls, steelfixing, 8mm 29.2 28.6 27.4 hrs/tonne
Walls, steelfixing, 10mm 22.7 22.0 21.2 hrs/tonne
Walls, steelfixing, 12mm 17.6 17.3 16.9 hrs/tonne
Walls, steelfixing, 16mm 12.4 12.2 11.8 hrs/tonne
Walls, steelfixing, 20mm 9.4 9.2 8.7 hrs/tonne
Walls, steelfixing, 25mm 7.4 7.2 7.0 hrs/tonne
Walls, steelfixing, 32mm 7.0 6.8 6.4 hrs/tonne
Walls, steelfixing, 40mm 6.4 6.1 5.9 hrs/tonne
Walls, steelfixing, 50mm 5.3 5.1 4.8 hrs/tonne
Staircases, steelfixing, 6mm 48.9 48.0 45.5 hrs/tonne
Staircases, steelfixing, 8mm 34.4 33.6 31.9 hrs/tonne
Staircases, steelfixing, 10mm 26.6 25.8 24.3 hrs/tonne
Staircases, steelfixing, 12mm 20.9 20.4 19.5 hrs/tonne
Staircases, steelfixing, 16mm 14.6 14.4 13.8 hrs/tonne
Staircases, steelfixing, 20mm 11.3 10.8 10.5 hrs/tonne
Staircases, steelfixing, 25mm 8.6 8.4 8.2 hrs/tonne
Reinforcement RatiosReinforcement Ratios
Task / Description Slow Ave Fast Units
Pile Cap, Concrete m3 x Ratio = Rebar Tonnes - 14.8 - % ratio
Base Slab, Concrete m3 x Ratio = Rebar Tonnes - 13.2 14.1 % ratio
Suspended Slab, Concrete m3 x Ratio = Rebar Tonnes - 20.6 25.6 % ratio
Platform Slab, Concrete m3 x Ratio = Rebar Tonnes - 15.6 - % ratio
Columns, Concrete m3 x Ratio = Rebar Tonnes 15.8 18.7 28.7 % ratio
Walls, Concrete m3 x Ratio = Rebar Tonnes 14.7 15.0 - % ratio
Staircase Reinforcement
Activity TASKSTask - UOM
L - Barbender/Fitter (Mandays)
L - Helper (Mandays) M M M
Staircase Reinforcement
Staircase Rein - Placing in Position & Binding - Using TMT Bars, Mild Steel, Tor Steel
Mt 0.32 Mandays/0.1Mt0.34 Mandays/0.1Mt
Bars - Include 5% Wastage
Binding Wire : 5 kg/0.1Mt
Cover Blocks - 10No/0.1Mt
Page 25 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Staircase Rein - Straightening, Cutting (With Machine Cutting), bending - Using TMT Bars, Mild Steel, Tor Steel.
Mt 0.2 Mandays/0.1Mt
0.28 Mandays/0.1Mt
Bars - Include 5% Wastage
Staircase Rein- Straightening, Cutting (With Manual Cutting), bending - Using TMT Bars, Mild Steel, Tor Steel.
Mt 0.29 Mandays/0.1Mt0.32 Mandays/0.1Mt
Bars - Include 5% Wastage
Walls Reinforcement
Activity TASKSTask - UOM
L - Barbender/Fitter (Mandays)
L - Helper (Mandays) M M M
Walls Reinforcement
Walls Rein - Placing in Position & Binding - Using TMT Bars, Mild Steel, Tor Steel
Mt 0.41 Mandays/0.1Mt0.45 Mandays/0.1Mt
Bars - Include 5% Wastage
Binding Wire : 5 kg/0.1Mt
Cover Blocks - 10No/0.1Mt
Walls Rein - Straightening, Cutting (With Machine Cutting), bending - Using TMT Bars, Mild Steel, Tor Steel.
Mt 0.2 Mandays/0.1Mt0.28 Mandays/0.1Mt
Bars - Include 5% Wastage
Walls Rein - Straightening, Cutting (With Manual Cutting), bending - Using TMT Bars, Mild Steel, Tor Steel.
Mt 0.39 Mandays/0.1Mt0.43 Mandays/0.1Mt
Bars - Include 5% Wastage
Walls Rein - Stirrups Cutting and Bending
Mt 0.47 Mandays/0.1Mt0.5 Mandays/0.1Mt
Bars - Include 5% Wastage
Walls Rein - Stirrups Teing Mt
0.55 Mandays/0.1Mt
0.57 Mandays/0.1Mt
Bars - Include 5% Wastage
Decking
Page 26 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Decking
Task / Description Slow Ave Fast Units
Simple Universal Beam Steel Bridge, concrete bridge deck, grano cover - 7.1 - m/day
Demolition & Break Out
Breaking Out & Openings
Breaking OutConcrete And Remove (hrs/m3)
Depth Hand Machine
Slabs - unreinforced Ne 50 mm 2.35 1.96
50 - 100 mm 3.15 2.46
100 - 200 mm 3.75 3.94
200 - 300 mm 4.12 5.55
Slabs - reinforced Ne 50 mm 4.71 3.92
50 - 100 mm 5.52 4.32
100 - 200 mm 5.88 4.71
200 - 300 mm 6.12 9.09
Walls - unreinforced all walls 4.71 3.04
Walls - reinforced all walls 5.52 3.92
Beams - reinforced all sizes 7.50 5.89
Columns - reinforced all sizes 9.20 7.30
Foundations - unreinforced all sizes 3.60 3.00
Foundations - reinforced all sizes 5.40 4.80
Breaking Out Tarmac
Rates include for breaking out and removal of rubble (hrs/m3).
Depth Hand Machine
Pavings Ne 50 mm 1.96 1.56
50-100 mm 2.08 1.64
100-150 mm 2.17 1.75
Roadways upto 150 mm 3.57
Breaking Out Brickwork
Rates include for breaking out and removal of rubble (hrs/m3).
Depth Hand Machine
Walls/columns Ne 100 mm 2.40 1.38
exc 100 mm 2.75 1.57
Foundation all sizes 2.75 1.57
Breaking Diaphragm Wall
Page 27 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Breaking Openings using coring machine 0.2m3/hour
Breaking out to expose couplers using hand held braker 1.75m2/day ot 2.5m run/day (0.7m slab)
Task / Description Slow Ave Fast Units
Concrete Slabs, unreinforced 50-150mm 3.2 - 1.9 hrs/m3
Concrete Slabs, unreinforced 150-300mm 5.5 4.1 3.7 hrs/m3
Concrete Slabs, reinforced 50-150mm 5.2 - 3.9 hrs/m3
Concrete Slabs, reinforced 150-300mm 9.1 6.2 4.7 hrs/m3
Concrete Walls, unreinforced 4.7 3.9 3.1 hrs/m3
Concrete Walls, reinforced 5.6 4.7 3.9 hrs/m3
Concrete Foundations, unreinforced 3.6 3.3 3.0 hrs/m3
Concrete Foundations, reinforced 5.4 5.1 4.8 hrs/m3
Concrete Beams 7.5 6.5 5.6 hrs/m3
Concrete Columns 9.2 8.2 7.3 hrs/m3
Tarmac paving 20-50mm thick 1.9 1.7 1.5 hrs/m3
Tarmac paving 50-100mm thick 2.1 - 1.6 hrs/m3
Tarmac paving 100-150mm thick 2.1 - 1.7 hrs/m3
Tarmac roadway 150mm thick - 3.6 - hrs/m3
Brickwork, walls and columns 2.4 1.8 1.3 hrs/m3
Brickwork, foundations 2.7 2.1 1.5 hrs/m3
Cutting HolesCutting Holes in concrete by Hand (no/hr
Hole depth (mm) --> 0-75 75-125 125-250 250-375 375-500
Ne 50 cm2 2.94 1.85 1.75 - -
50-100 cm2 2.22 1.39 1.32 - -
100-150 cm2 1.67 1.11 1.05 - -
250-500 cm2 1.28 0.88 0.83 - -
Cutting Holes in concrete by Machine (no/hr)
Hole depth (mm) --> 0-75 75-125 125-250 250-375 375-500
Ne 50 cm2 - - 5.88 5.00 4.55
50-100 cm2 - - 4.00 3.45 3.03
100-150 cm2 - - 2.50 2.17 1.92
Page 28 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
150-250 cm2 - - 1.67 1.45 1.28
250-500 cm2
Common BrickworkCommon Brickwork, by Machine (no/hr)
Hole depth (mm) --> 0-75 75-125 125-250 250-375 375-500
Ne 100 cm2 - 16.6 7.69 5.26 4.00
100-250 cm2 - 12.5 5.88 4.00 2.94
250-500 cm2 - 10.0 5.00 3.33 2.50
500-100 cm2 - 8.33 4.17 2.78 2.08
Common Brickwork, by Hand (no/hr)
Hole depth (mm) --> 0-75 75-125 125-250 250-375 375-500
Ne 100 cm2 11.1 8.33 5.56 3.85 -
100-250 cm2 9.09 7.14 4.55 3.23 -
250-500 cm2 7.69 5.88 3.85 2.70 -
500-100 cm2 6.67 4.76 3.23 2.27 -
Cutting BackCutting Back Concrete
Cutting Piles For Pile Caps, Using Breaker & Air Tools
Providing A Rough Finish (hrs/pile)
Pile Diameter--> 0.35m 0.5m 0.6m 0.79m 0.94m 1.1m 2.2m
0 - 100mm high 0.32 0.44 0.63 0.93 1.38 1.74 8.10
100-200mm high 0.39 0.56 0.81 1.22 1.83 2.16 8.58
200-300mm high 0.44 0.64 0.94 1.45 1.92 2.34 9.00
300-500mm high 0.49 0.72 1.07 1.65 2.10 2.50 9.50
500-750mm high 0.68 1.02 1.54 2.16 2.55 2.55 10.01
750-1000mm high 0.83 1.32 1.78 2.36 3.37 4.20 10.52
Providing A Neat Finish (hrs/pile)
Pile Diameter--> 0.35m 0.5m 0.6m 0.79m 0.94m 1.1m 2.2m
Page 29 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
0 - 100 mm high - 0.63 0.90 1.32 1.93 2.25 9.72
100-200 mm high - 0.76 1.11 1.65 2.39 2.81 10.29
200-300 mm high - 0.85 1.25 1.93 2.49 3.04 10.85
300-500 mm high - 1.05 1.59 2.38 2.73 3.25 11.40
500-750 mm high - 1.41 2.13 2.97 3.45 4.30 12.01
750-1000mm high - 2.07 2.79 3.72 4.38 5.43 12.62
Cut Concrete Slabs
Using Trolley Type Clipper Saw (m/hr)
Ne 25 mm deep 15.2
25-50 mm deep 11.5
50-75 mm deep 6.67
Cutting Back
Task / Description Slow Ave Fast Units
Concrete Pile Caps, 50-300mm deep and 0.6m dia 0.6 - 0.3 hrs/no
Concrete Pile Caps, 300-750mm deep and 0.6m dia 1.5 - 0.4 hrs/no
Concrete Pile Caps, > 750mm deep and 0.6m dia 1.8 - 0.8 hrs/no
Concrete Pile Caps, 50-300mm deep and 1.1m dia 1.9 - 0.8 hrs/no
Concrete Pile Caps, 300-750mm deep and 1.1m dia 2.5 - 1.1 hrs/no
Concrete Pile Caps, > 750mm deep and 1.1m dia 4.2 - 2.3 hrs/no
Concrete Pile Caps, 50-300mm deep and 2.5m dia 9.2 - 8.2 hrs/no
Concrete Pile Caps, 300-750mm deep and 2.5m dia 10.1 - 9.5 hrs/no
Concrete Pile Caps, > 750mm deep and 2.5m dia 11.5 - 10.2 hrs/no
Concrete, Cutting Slabs, 5-25m deep - 15.2 - m/hr
Concrete, Cutting Slabs, 25-50m deep - 11.5 - m/hr
Concrete, Cutting Slabs, 50-75m deep - 6.7 - m/hr
Concrete, Cutting Holes, coring machine - 0.2 - m3/hr
Concrete, Cutting Back to expose couplers 0.7m slab - 2.5 - m/day
Cutting ChasesCutting Chases
Task / Description Slow Ave Fast Units
Concrete, cutting by hand, < 25mm wide 1.5 2.1 3.1 m/hr
Concrete, cutting by hand, 25-50mm wide 1.2 1.6 2.5 m/hr
Page 30 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Concrete, cutting by hand, 50-75mm wide 1.0 1.4 2.1 m/hr
Concrete, cutting by hand, 75-100mm wide 0.9 1.2 1.8 m/hr
Concrete, cutting by machine, < 25mm wide 3.1 4.0 5.8 m/hr
Concrete, cutting by machine, 25-50mm wide 2.5 3.3 5.0 m/hr
Concrete, cutting by machine, 50-75mm wide 2.1 2.9 4.2 m/hr
Concrete, cutting by machine, 75-100mm wide 1.8 2.4 3.7 m/hr
Brickwork, cutting by hand, < 25mm wide 2.1 2.7 4.1 m/hr
Brickwork, cutting by hand, 25-50mm wide 1.6 2.3 3.5 m/hr
Brickwork, cutting by hand, 50-75mm wide 1.4 1.9 2.8 m/hr
Brickwork, cutting by hand, 75-100mm wide 1.2 1.6 2.5 m/hr
Brickwork, cutting by machine, < 25mm wide 4.2 5.5 11.1 m/hr
Brickwork, cutting by machine, 25-50mm wide 3.3 4.5 6.7 m/hr
Brickwork, cutting by machine, 50-75mm wide 3.3 4.5 6.7 m/hr
Brickwork, cutting by machine, 75-100mm wide 2.5 3.3 5.0 m/hr
Light Blockwork, cutting by hand, < 25mm wide 3.8 5.0 7.7 m/hr
Light Blockwork, cutting by hand, 25-50mm wide 3.2 4.2 6.3 m/hr
Light Blockwork, cutting by hand, 50-75mm wide 2.6 3.4 5.3 m/hr
Light Blockwork, cutting by hand, 75-100mm wide 2.3 3.1 4.5 m/hr
Light Blockwork, cutting by machine, < 25mm wide 7.7 10.0 14.2 m/hr
Light Blockwork, cutting by machine, 25-50mm wide 5.9 7.7 11.1 m/hr
Light Blockwork, cutting by machine, 50-75mm wide 5.2 7.2 10.0 m/hr
Light Blockwork, cutting by machine, 75-100mm wide 4.7 6.3 9.1 m/hr
Heavy Blockwork, cutting by hand, < 25mm wide 1.9 2.6 3.8 m/hr
Heavy Blockwork, cutting by hand, 25-50mm wide 1.6 2.1 3.2 m/hr
Heavy Blockwork, cutting by hand, 50-75mm wide 1.3 1.8 2.7 m/hr
Heavy Blockwork, cutting by hand, 75-100mm wide 1.2 1.5 2.3 m/hr
Heavy Blockwork, cutting by machine, < 25mm wide 3.8 5.0 7.7 m/hr
Heavy Blockwork, cutting by machine, 25-50mm wide 3.2 4.2 6.2 m/hr
Heavy Blockwork, cutting by machine, 50-75mm wide 2.7 3.6 5.2 m/hr
Heavy Blockwork, cutting by machine, 75-100mm wide 2.3 3.1 4.5 m/hr
Cutting SwitchboxesCutting Switchboxes
Task / Description Slow Ave Fast Units
Cutting in Concrete, small box 7.1 9.5 12.5 no/hr
Cutting in Concrete, large box 3.6 4.5 5.6 no/hr
Cutting in Brickwork, small box 6.6 9.5 12.5 no/hr
Cutting in Brickwork, large box 4.2 5.3 6.3 no/hr
Cutting in Lightweight Blockwork, small box 20.0 23.0 25.0 no/hr
Cutting in Lightweight Blockwork, large box 10.0 12.5 14.3 no/hr
Cutting in Heavyweight Blockwork, small box 7.7 10.0 12.5 no/hr
Cutting in Heavyweight Blockwork, large box 3.8 4.8 5.9 no/hr
Housing DemolitionsDemolition
Page 31 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Task / Description Slow Ave Fast Units
Weight, Structural Steel - 2.5 - Tonnes/m3
Remove & Cart away, Ceramic Wall Tiles 2.0 2.5 3.4 m2/hr
Remove & Cart away, Wallpaper, 1 layer - 8.7 - m2/hr
Remove & Cart away, Wallpaper, 2 layers - 7.1 - m2/hr
Remove & Cart away, Wallpaper, 3 layers - 5.7 - m2/hr
Remove & Cart away, Lathe and Plaster Ceilings 3.2 4.6 5.0 m2/hr
Remove & Cart away, Plaster to Walls 2.1 3.1 5.9 m2/hr
Remove & Cart away, External Render - 3.9 - m2/hr
Remove & Cart away, Floor Screed - 3.2 - m2/hr
Remove & Cart away, Concrete Paving - 4.0 - m2/hr
Remove & Cart away, Brickwork Walls, 1.0 brick thick - 1.3 - m2/hr
Remove & Cart away, Brickwork Walls, 0.5 brick thick - 2.6 - m2/hr
Remove & Cart away, Brickwork Walls, Sand/Lime Mortar - 1.8 - hrs/100
Remove & Cart away, Fireplace and Hearth - 1.9 - hrs/no
Remove & Cart away, Floor Boards - 6.2 - m2/hr
Remove & Cart away, Skirting, Architrave, Dado rail etc - 16.5 - m/hr
Remove & Cart away, Staircase - 7.3 - hrs/no
Remove & Cart away, Windows, 0-1m2 - 0.6 - hrs/no
Remove & Cart away, Windows 1-2m2 - 0.8 - hrs/no
Remove & Cart away, Windows 2-3m2 - 0.9 - hrs/no
Remove & Cart away, Doors - 0.3 - hrs/on
Remove & Cart away, Door Frame - 0.1 - hrs/no
Remove & Cart away, Floor and Ceiling Joists - 1.1 - hrs/m
Remove & Cart away, Wall Plates - 3.9 - hrs/m
Remove & Cart away, Iron Bath - 1.4 - /hrs/no
Remove & Cart away, Wash Basin/Sink - 0.8 - /hrs/no
Remove & Cart away, Pipework including brackets etc - 6.1 - m/hr
Removal of Housing FinishesHACKING OFF/ REMOVE MATERIALS
Removal of Housing Finishes . All rates in m2/hr, unless otherwise indicated. Remove and cart away.
Ceramic wall tiles
2.50
Wallpaper -1 layer 8.70
-2 layers 7.05
-3 layers 5.75
Lathe & Plaster ceilings
4.55
Plaster to walls
3.05
External render
3.90
Floor screed 3.05
Page 32 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Concrete paving
4.00
Brickwalls - London Stocks
x 1 brick 1.35
- Londond Stocks x 0.5 bricks
2.65
- Sand/Lime mortar
1.80 hrs/100
Fireplace and metal hearth
1.90 hrs/no
Floor Boards 6.20
Architrave, dado, skirting etc
16.50 m/hr
Staircase 7.35 hrs/no
Windows 0 - 1 m2 0.65 hrs/no
1 - 2 m2 0.80 hrs/no
2 - 3 m2 0.91 hrs/no
Doors 0.25 hrs/no
Door frame 0.10 hrs/no
Floor & Ceiling Joists
1.09 hrs/m
Wall plate 3.90 hrs/m
Bath 1.45 hrs/no
Basin 0.85 hrs/no
Pipework, incl brackets etc
6.15 m/hr
Drainage, Manholes and GulleysManholes and Gulleys
Task / Description Slow Ave Fast Units
Concrete Pre-Cast Manhole Units, 610 x 455 x 51 mm - 1.2 - hrs/no
Concrete Pre-Cast Manhole Units, 990 x 610 x 64 mm - 1.6 - hrs/no
Brickwork Manhole, 1.0 brick engineering - 0.3 - m2/hr
Brickwork Manhole, 1.5 brick engineering - 0.2 - m2/hr
Brickwork Manhole, 2.0 brick engineering - 0.2 - m2/hr
Benching to Manhole, under 0.5m2 - 0.9 - hrs/no
Benching to Manhole, 0.5-0.75m2 - 1.2 - hrs/no
Benching to Manhole, 0.75-1.0m2 - 1.8 - hrs/no
Brickwork Manhole, build in pipes, under 150mm dia - 0.1 - hrs/no
Brickwork Manhole, build in pipes, 150-225mm dia - 0.2 - hrs/no
Brickwork Manhole, build in pipes, over 225mm dia - 0.3 - hrs/no
Brickwork Manhole, build in cast iron covers 0.3 0.6 1.2 hrs/no
Yard Gulleys, 75-150mm dia pipes, bed and level - 2.2 - no/hr
Yard Gulleys, 150-225mm dia pipes, bed and level - 1.8 - no/hr
Yard Gulleys, 225-300mm dia pipes, bed and level - 1.5 - no/hr
Page 33 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Road Gulleys, 600mm deep, bed and level - 1.2 - no/hr
Road Gulleys, 750mm deep, bed and level - 0.8 - no/hr
Road Gulleys, 900mm deep, bed and level - 0.4 - no/hr
Road Gulleys, 1,200mm deep, bed and level - 0.3 - no/hr
Road Gulleys, install gratings - 5.0 - no/hr
PVC Manhole - 15.0 - mins/no
Land Drains
Task / Description Slow Ave Fast Units
Land Drains, Concrete, butt jointed, under 150mm dia, 0-5m run - 11.6 - m/hr
Land Drains, Concrete, butt jointed, under 150mm dia, 5-30m run - 14.1 - m/hr
Land Drains, Concrete, butt jointed, under 150mm dia, over 30m run - 18.8 - m/hr
Land Drains, Concrete, butt jointed, 150-225mm dia, 0-5m run - 8.4 - m/hr
Land Drains, Concrete, butt jointed, 150-225mm dia, 5-30m run - 10.2 - m/hr
Land Drains, Concrete, butt jointed, 150-225mm dia, over 30m run - 11.9 - m/hr
Land Drains, Concrete, butt jointed, 225-300mm dia, 0-5m run - 5.4 - m/hr
Land Drains, Concrete, butt jointed, 225-300mm dia, 5-30m run - 6.5 - m/hr
Land Drains, Concrete, butt jointed, 225-300mm dia, over 30m run - 7.9 - m/hr
Drainage
Task / Description Slow Ave Fast Units
PVC Drainage, 1m pipes, 100-150mm dia, 0-5m run - 5.7 - m/hr
PVC Drainage, 1m pipes, 100-150mm dia, 5-30m run - 8.1 - m/hr
PVC Drainage, 1m pipes, 100-150mm dia, over 30m run - 9.5 - m/hr
PVC Drainage, 3m pipes, 100-150mm dia, 0-5m run - 12.2 - m/hr
PVC Drainage, 3m pipes, 100-150mm dia, 5-30m run - 15.2 - m/hr
PVC Drainage, 3m pipes, 100-150mm dia, over 30m run - 18.2 - m/hr
PVC Drainage, 6m pipes, 100-150mm dia, 0-5m run - 22.2 - m/hr
PVC Drainage, 6m pipes, 100-150mm dia, 5-30m run - 27.7 - m/hr
PVC Drainage, 6m pipes, 100-150mm dia, over 30m run - 33.3 - m/hr
PVC Drainage, 3m pipes, 150-200mm dia, 5-30m run - 10.6 - m/hr
PVC Drainage, 3m pipes, 150-200mm dia, over 30m run - 12.8 - m/hr
PVC Drainage, 6m pipes, 150-200mm dia, 5-30m run - 21.2 - m/hr
PVC Drainage, 6m pipes, 150-200mm dia, over 30m run - 25.6 - m/hr
Stoneware Drainage, Cement/Sand Joints, 75mm dia, 0-5m run - 4.7 - m/hr
Stoneware Drainage, Cement/Sand Joints, 75mm dia, 5-30m run - 5.5 - m/hr
Stoneware Drainage, Cement/Sand Joints, 75mm dia, over 30m run - 6.6 - m/hr
Stoneware Drainage, Cement/Sand Joints, 100mm dia, 0-5m run - 4.4 - m/hr
Stoneware Drainage, Cement/Sand Joints, 100mm dia, 5-30m run - 5.0 - m/hr
Stoneware Drainage, Cement/Sand Joints, 100mm dia, over 30m run - 6.2 - m/hr
Stoneware Drainage, Cement/Sand Joints, 150mm dia, 0-5m run - 3.2 - m/hr
Stoneware Drainage, Cement/Sand Joints, 150mm dia, 5-30m run - 3.8 - m/hr
Stoneware Drainage, Cement/Sand Joints, 150mm dia, over 30m run - 4.5 - m/hr
Stoneware Drainage, Cement/Sand Joints, 225mm dia, 0-5m run - 2.1 - m/hr
Stoneware Drainage, Cement/Sand Joints, 225mm dia, 5-30m run - 2.6 - m/hr
Page 34 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Stoneware Drainage, Cement/Sand Joints, 225mm dia, over 30m run
- 3.1 - m/hr
Stoneware Drainage, Cement/Sand Joints, 300mm dia, 0-5m run - 1.4 - m/hr
Stoneware Drainage, Cement/Sand Joints, 300mm dia, 5-30m run - 1.7 - m/hr
Stoneware Drainage, Cement/Sand Joints, 300mm dia, over 30m run - 2.4 - m/hr
Stoneware Drainage, Cement/Sand Joints, over 375mm dia, 0-5m run - 1.1 - m/hr
Stoneware Drainage, Cement/Sand Joints, over 375mm dia, 5-30m run - 1.3 - m/hr
Stoneware Drainage, Cement/Sand Joints, over 375mm dia, over 30m run - 1.6 - m/hr
Stoneware Drainage, Flexible Joints, 75mm dia, 0-5m run - 8.3 - m/hr
Stoneware Drainage, Flexible Joints, 75mm dia, 5-30m run - 10.0 - m/hr
Stoneware Drainage, Flexible Joints, 75mm dia, over 30m run - 12.5 - m/hr
Stoneware Drainage, Flexible Joints, 100mm dia, 0-5m run - 7.7 - m/hr
Stoneware Drainage, Flexible Joints, 100mm dia, 5-30m run - 9.1 - m/hr
Stoneware Drainage, Flexible Joints, 100mm dia, over 30m run - 10.0 - m/hr
Stoneware Drainage, Flexible Joints, 150mm dia, 0-5m run - 5.2 - m/hr
Stoneware Drainage, Flexible Joints, 150mm dia, 5-30m run - 6.2 - m/hr
Stoneware Drainage, Flexible Joints, 150mm dia, over 30m run - 7.7 - m/hr
Stoneware Drainage, Flexible Joints, 225mm dia, 0-5m run - 2.7 - m/hr
Stoneware Drainage, Flexible Joints, 225mm dia, 5-30m run - 3.3 - m/hr
Stoneware Drainage, Flexible Joints, 225mm dia, over 30m run - 4.0 - m/hr
Stoneware Drainage, Flexible Joints, 300mm dia, 0-5m run - 1.7 - m/hr
Stoneware Drainage, Flexible Joints, 300mm dia, 5-30m run - 2.1 - m/hr
Stoneware Drainage, Flexible Joints, 300mm dia, over 30m run - 2.5 - m/hr
Stoneware Drainage, Flexible Joints, over 375mm dia, 0-5m run - 1.4 - m/hr
Stoneware Drainage, Flexible Joints, over 375mm dia, 5-30m run - 1.6 - m/hr
Stoneware Drainage, Flexible Joints, over 375mm dia, over 30m run - 2.1 - m/hr
PVC, Stoneware, Pitch Fibre & Concrete Joints - 2.4 - mins/no
Pitch Fibre Pipes, 75mm dia, 0-5m run - 9.1 - m/hr
Pitch Fibre Pipes, 75mm dia, 5-30m run - 16.6 - m/hr
Pitch Fibre Pipes, 75mm dia, over 30m run - 20.0 - m/hr
Pitch Fibre Pipes, 100mm dia, 0-5m run - 9.1 - m/hr
Pitch Fibre Pipes, 100mm dia, 5-30m run - 16.6 - m/hr
Pitch Fibre Pipes, 100mm dia, over 30m run - 20.0 - m/hr
Pitch Fibre Pipes, 150mm dia, 0-5m run - 6.6 - m/hr
Pitch Fibre Pipes, 150mm dia, 5-30m run - 12.5 - m/hr
Pitch Fibre Pipes, 150mm dia, over 30m run - 14.3 - m/hr
Pitch Fibre Pipes, 200mm dia, 0-5m run - 6.2 - m/hr
Pitch Fibre Pipes, 200mm dia, 5-30m run - 11.1 - m/hr
Pitch Fibre Pipes, 200mm dia, over 30m run - 12.5 - m/hr
Pitch Fibre Pipes, 225mm dia, 0-5m run - 5.8 - m/hr
Pitch Fibre Pipes, 225mm dia, 5-30m run - 10.0 - m/hr
Pitch Fibre Pipes, 225mm dia, over 30m run - 12.1 - m/hr
Hepsleve Rubber Joint System, 75mm dia, 0-5m run - 12.5 - m/hr
Page 35 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Hepsleve Rubber Joint System, 75mm dia, 5-30m run - 14.3 - m/hr
Hepsleve Rubber Joint System, 75mm dia, over 30m run 11.2 16.6 30.1 m/hr
Hepsleve Rubber Joint System, 100mm dia, 0-5m run - 10.0 - m/hr
Hepsleve Rubber Joint System, 100mm dia, 5-30m run - 12.5 - m/hr
Hepsleve Rubber Joint System, 100mm dia, over 30m run - 14.3 - m/hr
Hepsleve Rubber Joint System, 150mm dia, 0-5m run - 7.1 - m/hr
Hepsleve Rubber Joint System, 150mm dia, 5-30m run - 9.1 - m/hr
Hepsleve Rubber Joint System, 150mm dia, over 30m run 8.3 10.0 13.8 m/hr
Hepsleve Rubber Joint System, 225mm dia, 0-5m run - 6.8 - m/hr
Hepsleve Rubber Joint System, 225mm dia, 5-30m run - 4.5 - m/hr
Hepsleve Rubber Joint System, 225mm dia, over 30m run - 5.5 - m/hr
Hepsleve Rubber Joint System, 300mm dia, 0-5m run - 2.5 - m/hr
Hepsleve Rubber Joint System, 300mm dia, 5-30m run - 2.9 - m/hr
Hepsleve Rubber Joint System, 300mm dia, over 30m run - 3.7 - m/hr
Hepsleve Rubber Joint System, over 375mm dia, 0-5m run - 1.9 - m/hr
Hepsleve Rubber Joint System, over 375mm dia, 5-30m run - 2.3 - m/hr
Hepsleve Rubber Joint System, over 375mm dia, over 30m run - 2.7 - m/hr
Concrete Pipes, 1.5m pipes, 375mm dia, 0-5m run - 2.8 - m/hr
Concrete Pipes, 1.5m pipes, 375mm dia, 5-30m run - 3.4 - m/hr
Concrete Pipes, 1.5m pipes, 375mm dia, over 30m run - 3.8 - m/hr
Concrete Pipes, 1.5m pipes, 450mm dia, 0-5m run - 2.7 - m/hr
Concrete Pipes, 1.5m pipes, 450mm dia, 5-30m run - 3.2 - m/hr
Concrete Pipes, 1.5m pipes, 450mm dia, over 30m run - 3.6 - m/hr
Concrete Pipes, 1.5m pipes, 525mm dia, 0-5m run - 2.5 - m/hr
Concrete Pipes, 1.5m pipes, 525mm dia, 5-30m run - 2.9 - m/hr
Concrete Pipes, 1.5m pipes, 525mm dia, over 30m run - 3.4 - m/hr
Concrete Pipes, 1.5m pipes, 600mm dia, 0-5m run - 2.4 - m/hr
Concrete Pipes, 1.5m pipes, 600mm dia, 5-30m run - 2.7 - m/hr
Concrete Pipes, 1.5m pipes, 600mm dia, over 30m run - 3.3 - m/hr
Concrete Pipes, 1.5m pipes, 675mm dia, 0-5m run - 2.2 - m/hr
Concrete Pipes, 1.5m pipes, 675mm dia, 5-30m run - 2.6 - m/hr
Concrete Pipes, 1.5m pipes, 675mm dia, over 30m run - 2.9 - m/hr
Concrete Pipes, 1.5m pipes, 750mm dia, 0-5m run - 1.1 - m/hr
Concrete Pipes, 1.5m pipes, 750mm dia, 5-30m run - 2.4 - m/hr
Concrete Pipes, 1.5m pipes, 750mm dia, over 30m run - 2.5 - m/hr
Concrete Pipes, 1.5m pipes, 1,050mm dia - 2.9 4.2 m/day
Concrete Pipes, 1.5m pipes, 1,500mm dia - 2.5 3.8 m/day
Concrete Pipes, 1.5m pipes, 1,800mm dia - 2.1 2.6 m/day
Concrete Pipes, 2.5m pipes, 375mm dia, 0-5m run - 3.6 - m/hr
Concrete Pipes, 2.5m pipes, 375mm dia, 5-30m run - 4.3 - m/hr
Concrete Pipes, 2.5m pipes, 375mm dia, over 30m run - 5.0 8.0 m/hr
Concrete Pipes, 2.5m pipes, 450mm dia, 0-5m run - 3.4 - m/hr
Concrete Pipes, 2.5m pipes, 450mm dia, 5-30m run - 4.1 - m/hr
Concrete Pipes, 2.5m pipes, 450mm dia, over 30m run - 4.5 9.0 m/hr
Concrete Pipes, 2.5m pipes, 525mm dia, 0-5m run - 3.3 - m/hr
Concrete Pipes, 2.5m pipes, 525mm dia, 5-30m run - 3.8 - m/hr
Page 36 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Concrete Pipes, 2.5m pipes, 525mm dia, over 30m run - 4.1 - m/hr
Concrete Pipes, 2.5m pipes, 600mm dia, 0-5m run - 3.0 - m/hr
Concrete Pipes, 2.5m pipes, 600mm dia, 5-30m run - 3.5 - m/hr
Concrete Pipes, 2.5m pipes, 600mm dia, over 30m run - 4.0 - m/hr
Concrete Pipes, 2.5m pipes, 675mm dia, 0-5m run - 2.8 - m/hr
Concrete Pipes, 2.5m pipes, 675mm dia, 5-30m run - 3.3 - m/hr
Concrete Pipes, 2.5m pipes, 675mm dia, over 30m run - 3.7 - m/hr
Concrete Pipes, 2.5m pipes, 750mm dia, 0-5m run - 2.6 - m/hr
Concrete Pipes, 2.5m pipes, 750mm dia, 5-30m run - 3.1 - m/hr
Concrete Pipes, 2.5m pipes, 750mm dia, over 30m run - 3.6 - m/hr
Lay Shingle Around Pipework, under 150mm dia - 7.0 - m/hr
Lay Shingle Around Pipework, over 150mm dia 4.0 5.5 9.0 m/hr
Earthworks & Excavation
Basement Excavations
Basement ExcavationBasement Excavation
Task / Description Slow Ave Fast Units
Hydraulic Excavator, 0.3m3 bucket, Sand/Soil - Basement Works 6.4 8.0 9.4 m3/hr
Hydraulic Excavator, 0.3m3 bucket, Gravel Beds - Basement Works 5.5 6.9 8.1 m3/hr
Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk - Basement Works 5.2 6.5 7.9 m3/hr
Hydraulic Excavator, 0.3m3 bucket, Hard Ground - Basement Works 4.7 5.9 8.2 m3/hr
Hydraulic Excavator, 0.4m3 bucket, Sand/Soil - Basement Works 12.6 15.4 18.9 m3/hr
Hydraulic Excavator, 0.4m3 bucket, Gravel Beds - Basement Works 11.7 14.3 16.7 m3/hr
Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk - Basement Works 10.9 13.3 15.6 m3/hr
Hydraulic Excavator, 0.4m3 bucket, Hard Ground - Basement Works 9.7 11.8 14.0 m3/hr
Hydraulic Excavator, 0.5m3 bucket, Sand/Soil - Basement Works 18.2 20.0 23.0 m3/hr
Hydraulic Excavator, 0.5m3 bucket, Gravel Beds - Basement Works 16.5 18.1 20.0 m3/hr
Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk - Basement Works 15.4 16.7 19.3 m3/hr
Hydraulic Excavator, 0.5m3 bucket, Hard Ground - Basement Works 13.3 15.4 17.7 m3/hr
Excavate and Remove
Excavate and Remove
Task / Description Slow Ave Fast Units
Excavate Spoil Heaps to Transport, 0.6m3 bucket, Sand/Soil 14.5 20.0 25.6 m3/hr
Excavate Spoil Heaps to Transport, 0.6m3 bucket, Gravel Beds 15.2 20.4 25.6 m3/hr
Excavate Spoil Heaps to Transport, 0.6m3 bucket, Clay/Chalk 12.3 18.5 23.2 m3/hr
Excavate Spoil Heaps to Transport, 0.6m3 bucket, Boulder Clay 11.2 16.9 21.3 m3/hr
Excavate Spoil Heaps to Transport, 1.1m3 bucket, Sand/Soil 25.4 30.3 35.7 m3/hr
Excavate Spoil Heaps to Transport, 1.1m3 bucket, Gravel Beds 25.6 31.3 37.0 m3/hr
Excavate Spoil Heaps to Transport, 1.1m3 bucket, Clay/Chalk 22.5 27.8 33.3 m3/hr
Page 37 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Excavate Spoil Heaps to Transport, 1.1m3 bucket, Boulder Clay 18.9 24.4 30.3 m3/hr
Load Spoil to Barge, capacity 2,000m3 - 8.0 - hrs
Load Spoil to Barge, capacity 1,500m3 - 6.5 - hrs
Load Spoil to Barge, capacity 1,000m3 - 5.5 - hrs
Spoil conveyor, 600mm belt, 150m/min - 260.0 - m3/hr
Bell Ground AnchorsBell Ground Anchors
Task / Description Slow Ave Fast Units
Uncased Anchors, 10m long - 2.0 - no/day
Top Cased Anchors, 15m long - 1.0 - no/day
Anchors stressing - 2.2 - no/day
Bored PilingBored Piling
Task / Description Slow Ave Fast Units
Cycle Time, 5-20m deep 8.0 4.0 4.0 days/no
Cycle Time, 20-40m deep 10.0 8.0 - days/no
Cycle Time, 40-70m deep 25.0 10.0 - days/no
Cycle Time, 70-90m deep 45.0 25.0 - days/no
Cycle Time, 90-135m deep 60.0 45.0 - days/no
Move piling setup to next location - 2.0 - hrs
Excave shaft by grab, general fill/uppr levels - 3.5 - m/hr
Excave shaft by grab, sand/minor rubble - 2.1 - m/hr
Excave shaft by grab, marinve/aluvium - 2.5 - m/hr
Excave shaft by grab/RCD, CDT - 0.5 - m/hr
Excave shaft by grab/RCD, CDG 200/gravel - 0.5 - m/hr
Excave shaft by RCD/Chisel, corestones - 0.5 - m/hr
Excave Rock Socket by RCD, grade IV/V rock - 0.2 0.3 m/hr
Excave Rock Socket by RCD, grade II/III rock - 0.1 0.2 m/hr
Excave Rock Socket by RCD, tendering rate - 0.1 - m/hr
Add/remove RCD plant - 2.0 - hrs
Add/remove RCD drill string/drill bit - 5.0 - hrs
Remove Obstruction, above water hand hammers - 0.8 - m/hr
Remove Obstruction, below water heavy chisel - 0.5 - m/hr
Concrete Plug, RCD off/tremmie/concrete/cure/RCD on 60.0 53.0 50.0 hrs
Install air lift tremmie tube - 5.0 - hrs
Fabricate reinforcement cages - 2.5 - hs/cage
Install reinforcement cages - 2.0 - hrs/no
Shaft cleaning, air lifting after excavation - 8.0 - hrs
Shaft cleaning, air lifting after cage installed - 2.0 - hrs
Page 38 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Shaft concreting/extract casing 5-70m deep - 12.0 - hrs
Shaft concreting/extract casing 70-95m deep - 14.0 - hrs
Shaft concreting/extract casing 95-135m deep - 48.0 - hrs
Concrete curing prior to remove telescopic casing - 72.0 - hrs
Concrete Testing, Coring Test - 3.2 2.2 m/hr
Concrete Testing, Sonic Logging Test - 2.5 - hrs/no
Concrete Testing, Vibration Test - 6.5 - hrs/no
Bulk ExcavationBulk Excavation
Task / Description Slow Ave Fast Units
Excavation Bulking Factor, Sand/Soil - 15.0 20.0 %
Excavation Bulking Factor, Gravel - 33.0 - %
Excavation Bulking Factor, Clay/Chalk - 40.0 - %
Excavation Bulking Factor, Boulder Clay - 45.0 - %
Excavation Bulking Factor, Rock - 60.0 - %
Spoil Weight, Rock - 2.5 - Tonnes/m3
Spoil Weight, Concrete - 2.4 - Tonnes/m3
Spoil Weight, Landfill/CDG - 1.9 - Tonnes/m3
Spoil Weight, Sand - 1.8 - Tonnes/m3
Rail Mounted Grab, 2.0m3 bucket 2.4min lift cycle 30.0 48.0 59.0 m3/hr
Crane Mounted Clamshell Grab, 2.0m3 bucket 2.9min lift cycle 25.0 33.0 41.0 m3/hr
Crane Mounted Clamshell Grab, 2.5m3 bucket 2.9min lift cycle 34.0 42.0 52.0 m3/hr
Hydraulic Excavator, 0.3m3 bucket, Sand/Soil 6.9 8.7 10.2 m3/hr
Hydraulic Excavator, 0.4m3 bucket, Sand/Soil 23.4 28.6 33.4 m3/hr
Hydraulic Excavator, 0.5m3 bucket, Sand/Soil 45.5 50.0 58.0 m3/hr
Hydraulic Excavator, 0.3m3 bucket, Gravel Beds 5.6 7.1 8.2 m3/hr
Hydraulic Excavator, 0.4m3 bucket, Gravel Beds 20.5 25.0 29.0 m3/hr
Hydraulic Excavator, 0.5m3 bucket, Gravel Beds 36.8 40.0 46.0 m3/hr
Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk 5.6 7.1 8.3 m3/hr
Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk 20.5 25.0 28.7 m3/hr
Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk 37.0 40.0 46.0 m3/hr
Hydraulic Excavator, 0.3m3 bucket, Hard Ground 4.5 6.1 7.2 m3/hr
Hydraulic Excavator, 0.4m3 bucket, Hard Ground 17.9 22.2 25.0 m3/hr
Hydraulic Excavator, 0.5m3 bucket, Hard Ground 25.7 28.6 32.9 m3/hr
Dewatering
Cofferdam WorksSoil Mix Wall Three auger machine drilling and mixing cement into three cores. H-piles dropped into two, then machine moves along by two holes.
An average output was 4 - 5 m/day.
Dewatering
Page 39 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
To setup a cofferdam dewatering system, including boring, pump installation and outflow pipework and drainage tanks etc, typical rates are...
Small 2 hole system, for an overrun tunnel, with a single drilling rig takes about 7 - 10 days to get up and running. A larger system, with 10 - 15 holes, for a station type cofferdam will take in the region of 3 weeks with 2 rigs. This
can be speeded up with the use of more rigs to reduce the well boring times.
A typical rate of 2.5 days per pump installation can be used to calculate detailed pumping arrangements. The water level can be dropped in a "closed cofferdam" within a 6 to 8 hour period for a 25,000 m2 cofferdam with a 2 m water level reduction. For smaller closed areas it will take only a few hours at most to reduce the water level by 2.5 - 3 metres.
Recharge System - Average well depth of say 55 m deep, not into rock, 9 wells in 10 days or 1.11 days/no with an additional 4 - 5 days to connect pipework and recharge backup tanks etc.
Dewatering
Task / Description Slow Ave Fast Units
Setup small 2 hole system 10.0 8.0 6.0 days
Setup large 15 hole system - 21.0 - days
Calculate system times per pump - 2.5 - days/pump
Setup Recharge System - 3.5 - days/pump
Excavate & Reduce LevelsExcavate By Hand
Trenches (m3/hr)
Depth in Metres->
Ne 1.5 1.5-3.0 3.0-4.5
Sand/Soil lose
0.66 0.45 0.33
Sand/Soil firm 0.57 0.38 0.28
Gravel 0.45 0.31 0.23
Clay/Heavy Soil
0.46 0.31 0.24
Boulder Clay 0.38 0.26 0.19
Pits or Bases Ne 2 m2 (m3/hr) Depth in Metres->
Ne 1.5 1.5-3.0 3.0-4.5
Sand/Soil lose
0.5 0.33 -
Sand/Soil firm 0.43 0.29 -
Gravel 0.34 0.23 -
Clay/Heavy Soil
0.35 0.24 -
Boulder Clay 0.28 0.19 -
Hand Transportation of Spoil (m3/hr) Wheel
0 - 10 m 6.25
10 - 20 m 3.23
20 - 50 m 2.13
Trim Excavation (m3/hr) Ave Thickness Sand Gravel Clay Boulders
0 - 25 mm 20.00 16.67 20.00 14.29
Page 40 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
25 - 50 mm 11.11 8.33 9.09 7.69
50 - 75 mm 7.69 5.88 6.25 5.00
75 - 125 mm 5.56 4.35 4.55 3.70
Excavate & Spread and LevelSmall Scale Spread and Level By Hand
Including load and wheel an average of 20 m from tipped heap (m3/hr) Layers -> n.e.25mm 25-
75mm75.200mm Exc.200mm
Sand/Soil
n.e. 200 m2 1.03 1.03 1.12 1.23
exc. 200 m2 1.37 1.37 1.49 1.64
Gravel/Shingle
n.e. 200 m2 - 0.86 0.93 1.03
exc. 200 m2 - 1.14 1.23 1.37
Hardcore
n.e. 200 m2 - 0.85 1.02 1.27
exc. 200 m2 - 1.02 1.27 1.69
Spread and Level By Crawler Shovel Rates in (m3/hr) Machine Bucket-> 0.6m3 0.8m3 1.0m3 1.2m3
Sand/Soil
n.e. 200 m2 18.67 38.46 43.48 52.63
exc. 200 m2 24.39 50.00 55.56 66.67
Gravel/Shingle
n.e. 200 m2 18.87 38.46 43.48 52.63
exc. 200 m2 24.39 50.00 55.56 66.67
Hardcore
n.e. 200 m2 15.87 31.25 37.04 43.48
exc. 200 m2 19.23 40.00 47.62 55.56
Clay
n.e. 200 m2 17.24 35.71 43.48 47.62
exc. 200 m2 22.22 45.45 55.56 62.50
Note:
n.e means "not exceeding"
Excavation Works
Excavate & LoadExcavate Spoil Heaps and Load to Transport (m3/hr):
Material 0.6 m3 0.8 m3 1.0 m3 1.2 m3Sand/Soil 20.0 25.6 30.3 35.7
Gravel 20.4 25.6 31.3 37.0
Page 41 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Clay/Chalk 18.5 23.2 27.8 33.3
Boulder Clay 16.9 21.3 24.4 30.3
Note:
0.6m3, 0.8m3, 1.0m3 and 1.2m3 are excavator bucket capacity. 20.0, 25.6, 30.3 and 35.7 etc are excavation rates in m3 / hr
Excavate By Crawler Shovel.Including excavate and bank/stock pile (m3/hr)
Sand/Soil
Machine Bucket -> 0.6m3
0.8m3 1.0m3 1.2m3
Pushed n.e.20 m
20.00 25.00 30.30 35.71
Pushed 20 - 50 m
13.89 20.41 23.81 27.78
Pushed 50 - 125 m
7.63 12.66 16.67 20.41
Gravel
Pushed n.e. 20 m
20.40 25.64 31.25 37.04
Pushed 20 - 50 m
14.29 20.83 25.00 28.57
Pushed 50 - 100 m
7.69 12.82 17.24 21.28
Clay/Chalk/Heavy Soil Pushed n.e. 20 m
18.52 23.26 27.78 33.33
Pushed 20 - 50 m
12.66 18.52 21.74 25.64
Pushed 50 - 100 m
6.99 11.63 15.15 18.87
Boulder Clay Pushed n.e. 20 m
16.95 21.28 24.39 30.30
Pushed 20 - 50 m
11.63 16.95 19.61 23.26
Pushed 50 - 100 m
6.33 10.42 13.70 17.54
Including excavate and load to transport (m3/hr) Machine Bucket ->
0.6m3 0.8m3 1.0m3 1.2m3
Sand/Soil 17.86 23.26 27.03 30.30
Gravel 16.67 23.26 27.78 31.25
Chalk/Heavy Soil
14.71 21.74 25.00 29.41
Boulder Clay 13.70 19.61 22.22 27.03
Page 42 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Ground ExcavationGround Excavation Rates (m3/hr):
Ground Type Bucket Bulk Works Basements Trenches Small & DeepSand/Soil 0.3m3 8.7 8.0 7.1 8.4>
0.4m3 28.5 15.4 25.0 10.0
0.5m3 50.0 20.0 28.6 13.3
Gravel 0.3m3 7.1 6.9 6.1 4.5
0.4m3 25.9 14.3 22.2 8.7
0.5m3 40.0 18.1 28.6 11.1
Clay/Chalk 0.3m3 7.1 6.5 6.1 4.1
0.4m3 25.0 13.3 22.2 8.3
0.5m3 40.0 16.7 28.6 10.5
V.Difficult 0.3m3 6.1 5.9 5.4 4.1
0.4m3 22.2 11.8 20.0 7.7
0.5m3 28.6 11.8 20.0 6.7
Small or Deep Excavations
Task / Description Slow Ave Fast Units
Hydraulic Excavator, 0.3m3 bucket, Sand/Soil 6.7 8.4 9.9 m3/hr
Hydraulic Excavator, 0.3m3 bucket, Gravel Beds 3.2 4.5 5.0 m3/hr
Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk 3.3 4.1 5.2 m3/hr
Hydraulic Excavator, 0.3m3 bucket, Hard Ground 3.3 4.1 5.2 m3/hr
Hydraulic Excavator, 0.4m3 bucket, Sand/Soil 8.2 10.0 11.7 m3/hr
Hydraulic Excavator, 0.4m3 bucket, Gravel Beds 7.1 8.7 10.2 m3/hr
Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk 6.5 8.3 9.4 m3/hr
Hydraulic Excavator, 0.4m3 bucket, Hard Ground 6.3 7.7 9.1 m3/hr
Hydraulic Excavator, 0.5m3 bucket, Sand/Soil 12.2 13.3 15.4 m3/hr
Hydraulic Excavator, 0.5m3 bucket, Gravel Beds 10.2 11.1 12.9 m3/hr
Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk 9.7 10.5 12.1 m3/hr
Hydraulic Excavator, 0.5m3 bucket, Hard Ground 6.1 6.7 7.7 m3/hr
Material WeightsWagon sizes and tonnage capacities vary and should be taken into consideration.
Rock = 2.5 T/m3 Concrete = 2.4 T/m3 Landfill / CDG = 1.9 T/m3 Sand = 1.8 T/m3
Spoil By BargeRemoval / Transportation Of Spoil By Barge:
The size, getting material to the facility, location and movement restrictions of the barge loading facilities are critical to production. A 2,000 m3 flat bottom barge, could easily be loaded 1.5 times per day, with a planned allowance of 2 no movements per day for example...
1,000 m3 barge, filled in 9.5 hrs = 2 movements/day 1,500 m3 barge, filled in 6.5 hrs = 3.5 movements/day
Page 43 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Spoil By ConveyorRemoval / Transportation Of Spoil By Conveyor: The size and location of the conveyor are critical to production and should be sized according to the most critical peaks in excavation.
There are the following parameters to select...
Max excavation per hour 185 m3/hr
Assume belt size 600 mm
Assume conveyor trough angle 20 degrees
From the above you read off specific parameters from the suppliers table...
Recommended belt speed 150 m/min
Angle of repose for dry sand 35 degrees
Angle of surcharge 20 degrees
You must then read off, from the manufacturers tables the conveyor capacity...
Cross-sectional area of load 0.02979 m2
At a speed of 150 m/min gives 268 m3/hr
Assume a bulking factor for excavated sane = 15%, and assume 50 minutes work per hour to allow for blockages and maintenance etc...
268 x 85% x 50/60 = 190 so therefore capacity of conveyor = 190 m3 per hour = OK.
Hong Kong Airport Express Station conveyor was capable of 11,500 m3/week.
Ground Compaction
Compact & ConsolidateCompact & Consolidate using Vibratory Roller or compactor.
Sand 31.25 m2/hr Soil 58.82 m2/hr Clay 55.56 m2/hr Hardcore 38.46 m2/hr Ash 57.85 m2/hr
Deep CompactionEssentially required in order to reduce expected ground settlement and to protect underground utilities / structures etc.
Deep compaction by 350 mm dia Vibroflot, 3 m centres in sand. Working on 12 hour basis, a vibroflot will achieve an output of 3-4,000 m3/shift (5,000 m3/day has been achieved in
an extended shift).
Ground Compaction
Task / Description Slow Ave Fast Units
Deep Vibroflot, 3m centres 330.0 380.0 465.0 m3/hr
Vibro-Roller, Sand 28.5 31.2 45.2 m2/hr
Vibro-Roller, Soil - 58.8 - m2/hr
Vibro-Roller, Clay - 55.6 - m2/hr
Vibro-Roller, Hardcore - 38.4 - m2/hr
Vibro-Roller, Ash - 57.8 - m2/hr
Page 44 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Hand Fill & CompactLoose from side of excavation, including compaction (m3/hr)...
Material Ne 100m 100-200mm 200-300mm exc 300mLoose Sand/Soil 0.85 1.02 1.28 1.69
Clay/Heavy Chalk 0.77 0.92 1.16 1.56
Hoging 0.81 0.97 1.20 1.61
Hardcode 0.71 0.84 1.06 1.41
Ground Monitoring
Reclamation & Filling
Spread & LevelingSpread and Level
Task / Description Slow Ave Fast Units
Crawler Shovel, 0.8m3 bucket, Sand/Soil, pushed 5-50m to stockpile 13.9 20.4 25.0 m3/hr
Crawler Shovel, 0.8m3 bucket, Sand/Soil, pushed 50-120m to stockpile 7.6 9.5 12.6 m3/hr
Crawler Shovel, 0.8m3 bucket, Gravel, pushed 5-50m to stockpile 14.2 20.4 25.6 m3/hr
Crawler Shovel, 0.8m3 bucket, Gravel, pushed 50-120m to stockpile 7.6 10.2 12.8 m3/hr
Crawler Shovel, 0.8m3 bucket, Clay/Chalk, pushed 5-50m to stockpile 12.7 18.4 23.2 m3/hr
Crawler Shovel, 0.8m3 bucket, Clay/Chalk, pushed 50-120m to stockpile 6.9 8.9 11.6 m3/hr
Crawler Shovel, 0.8m3 bucket, Boulder Clay, pushed 5-50m to stockpile 11.6 16.9 21.3 m3/hr
Crawler Shovel, 0.8m3 bucket, Boulder Clay, pushed 50-120m to stockpile 6.3 8.2 10.4 m3/hr
Crawler Shovel, 1.2m3 bucket, Sand/Soil, pushed 5-50m to stockpile 23.8 28.5 35.7 m3/hr
Crawler Shovel, 1.2m3 bucket, Sand/Soil, pushed 50-120m to stockpile 16.7 18.5 20.4 m3/hr
Crawler Shovel, 1.2m3 bucket, Gravel, pushed 5-50m to stockpile 25.0 32.0 37.0 m3/hr
Crawler Shovel, 1.2m3 bucket, Gravel, pushed 50-120m to stockpile 17.2 19.3 21.2 m3/hr
Crawler Shovel, 1.2m3 bucket, Clay/Chalk, pushed 5-50m to stockpile 21.7 27.5 33.3 m3/hr
Crawler Shovel, 1.2m3 bucket, Clay/Chalk, pushed 50-120m to stockpile 15.1 16.9 18.8 m3/hr
Crawler Shovel, 1.2m3 bucket, Boulder Clay, pushed 5-50m to stockpile 19.6 24.5 30.3 m3/hr
Crawler Shovel, 1.2m3 bucket, Boulder Clay, pushed 50-120m to stockpile 13.7 15.9 17.5 m3/hr
Crawler Shovel, 0.6m3 bucket, 50-200m2, Sand/Soil 18.6 28.5 38.5 m3/hr
Crawler Shovel, 0.6m3 bucket, over 200m2, Sand/Soil 24.4 37.2 50.0 m3/hr
Crawler Shovel, 0.6m3 bucket, 50-200m2, Gravel 18.9 28.6 38.4 m3/hr
Crawler Shovel, 0.6m3 bucket, over 200m2, Gravel 24.2 37.2 50.0 m3/hr
Crawler Shovel, 0.6m3 bucket, 50-200m2, Hardcore 15.8 23.5 31.2 m3/hr
Crawler Shovel, 0.6m3 bucket, over 200m2, Hardcore 19.2 29.6 40.0 m3/hr
Page 45 of 100
11/3/2014http://www.planningplanet.com/print/book/export/html/422384
Crawler Shovel, 0.6m3 bucket, 50-200m2, Boulder Clay 17.2 26.4 35.7 m3/hr
Crawler Shovel, 0.6m3 bucket, over 200m2, Boulder Clay 22.2 33.8 45.4 m3/hr
Crawler Shovel, 1.2m3 bucket, 50-200m2, Sand/Soil 43.5 48.0 52.6 m3/hr
Crawler Shovel, 1.2m3 bucket, over 200m2, Sand/Soil 55.5 61.1 66.7 m3/hr
Crawler Shovel, 1.2m3 bucket, 50-200m2, Gravel 43.8 48.3 52.9 m3/hr
Crawler Shovel, 1.2m3 bucket, over 200m2, Gravel 55.5 61.1 66.7 m3/hr
Crawler Shovel, 1.2m3 bucket, 50-200m2, Hardcore 37.1 40.3 43.5 m3/hr
Crawler Shovel, 1.2m3 bucket, over 200m2, Hardcore 47.6 51.6 55.6 m3/hr
Crawler Shovel, 1.2m3 bucket, 50-200m2, Boulder Clay 43.8 45.7 47.6 m3/hr
Crawler Shovel, 1.2m3 bucket, over 200m2, Boulder Clay 55.6 59.1 62.5 m3/hr
Steel StruttingSteel Strutting...
Task / Description Slow Ave Fast Units
Horizontal heavy duty strutting - 2.0 - days/no
Diagonal heavy duty strutting - 6.0 - days/no
Trench ExcavationsTrench Excavation...
Task / Description Slow Ave Fast Units
Hydraulic Excavator, 0.3m3 bucket, Sand/Soil 5.6 7.1 8.2 m3/hr
Hydraulic Excavator, 0.3m3 bucket, Gravel Beds 4.8 6.1 7.3 m3/hr
Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk 4.8 6.1 7.1 m3/hr
Hydraulic Excavator, 0.3m3 bucket, Hard Ground 9.7 5.4 6.4 m3/hr
Hydraulic Excavator, 0.4m3 bucket, Sand/Soil 20.5 25.0 29.2 m3/hr
Hydraulic Excavator, 0.4m3 bucket, Gravel Beds 18.2 22.2 26.0 m3/hr
Hydraulic Ex