Presentation to the Chamber of Commerce

Friday, April 23, 2010

Overview

Project Timeline 2010 Construction Season What’s Next Questions?

Project Timeline

Project initiated 1997SafetyPavementVillage Infrastructure

Design approved 2006.

Project Timeline Bid in January 2009. Construction began Spring 2009.

Water and sewer lines from Pleasant Street to Prince Street.

Drainage improvements starting at Pelton Street through neighborhood south of Broadway.

Reconstructed pavement west of Pleasant Street.

Spring Street drainage improvements.

What’s Going On: 2010 Season Continue water, sanitary sewer, and

storm sewer improvements to West Broadway.Including additional Village Project to install

sanitary sewer connections to Pelton Street.

Continue full depth pavement reconstruction.

Pavement Reconstruction NYSDOT will:

Keep driveways open.Provide notification.

Please contact Engineer-in-Charge with any problems or issues.

Pavement Reconstruction

Example of Signage at Construction Zone

Example of Signage at Business Entrance

What’s Going On: 2010 Season Install stamped concrete median. Install foundations for decorative

sidewalk lighting.Partnership between Village, Congressman

Hinchey, Sullivan Renaissance, and NYSDOT.

What’s Next: 2011 Season Originally anticipated to be two-season

project, but delayed due to changes during construction.

Spring-Summer 2011:Finish pavement.Install curbs.Install new sidewalksPlant trees and other landscaping elements.

What’s Next: 2011 Season NYSDOT intends to replace

all trees removed during construction.

What’s Next: 2011 Season Planned Landscaping includes:

Replacing trees removed during construction.

Installing low-growing juniper shrubs to prevent weed growth in the planting beds.

One year of maintenance provided by landscape contractor.

Traffic control plan.

A plan the community can build on.

What’s Next: 2011 and Beyond

What’s Next: 2011 and Beyond

What’s Next: 2011 and Beyond

Route 26/17C ReconstructionVillage of Endicott (2006/07)

Route 26/17C ReconstructionVillage of Endicott (2006/07)

Route 26/17C ReconstructionVillage of Endicott (2006/07)

Route 26/17C ReconstructionVillage of Endicott (2006/07)

Route 26/17C ReconstructionVillage of Endicott (2006/07)

Thank You! Any questions? Contact Information:

Katy Mangan

Project Manager

607.721.8254

kmangan@dot.state.ny.us

Glenn Sanders

Engineer-in-Charge

845.791.7057

gsanders@dot.state.ny.us