Previous Week’s ActionItem # 1

-Further Map and Test the GPS System- Determine Accuracy- Determine Repeatability

South Quad Stationary Test

1750

1800

1850

1900

1950

2000

2050

2100

2150

2440 2450 2460 2470 2480 2490 2500 2510

Longitude

La

titu

de

South Quad 1

South Quad 2

Units in decimalminutes, e.g.14.XXXX minutes

Debartolo Quad

8800

8850

8900

8950

9000

9050

1950 2000 2050 2100 2150

Longitude

Lat

itud

e

0 ft #1

0 ft #2

0 ft #3

50 ft #1

50 ft #2

50 ft #3

100 ft #1

100 ft #2

100 ft #3

100 ft

Units in decimalminutes, e.g.14.XXXX minutes

Previous Week’s ActionItem # 2

-Determine a Drive System- Met with Dr. Skaar- Initially considered a simulated tank drive

with roller chain connecting the front and back wheels on each side

- Chose 2 driven wheels and 2 casters

Current Status of Concept

Current Status of Concept

-Finalizing the Conceptual Model

-Key Features Include

- Two Independently Driven Wheels

- Two Casters

- Mast and Boom with 2 Sensors

- Electronic Compass

-On Schedule with No Showstoppers

Next Week’s Action Items

-Finalize Budget and Begin Purchasing Components

-Preliminary Prototyping

- CAD Modeling

- Physical Prototypes

Questions???

Thank you