Parking Impact

• End of July: Construction to begin on Charger Park

parking lot extension (207 new spaces)

• Before Nov 15: Charger Park parking lot extension

available

• Nov 15: Shelby Center/Madison Hall lot taken offline for

construction (355 spaces)

• Nov 17: Start of construction of Welcome Center/Student

Services Building

• Spring Semester 2016: Welcome Center/Student Services

Building complete (205 spaces)

• Short Term Net: -148 spaces

• Long Term Net: +57 spaces