Powell Construction Project Update Prepared: January 27, 2017 Project Details Architects IStudio Architects General Contractor: MCN Build DGS Project Manager: Jennifer Battle Project Completion: Building D - March 2017 Planned Work through February 10, 2017: Interior Work:

● Install Rubber Flooring (1st Floor)

● Install Kitchen Cooler / Freezer

● Install Remaining Kitchen Equipment

● Install Flooring (2nd Floor)

● Install Lighting Fixtures (2nd Floor)

Exterior Work :

● Exterior Stair pans

● Continue roof installation

● Finish installation of curtain wall and windows

● Installation of roof monitors

● Installation of stair guardrails and brick supports is going

● Installation of brick screen wall is ongoing

Progress Photos are on the next page.

1200 First Street, NE | Washington, DC 20002 | T 202.442.5885 | F 202.442.5026 | dcps.dc.gov

1

Media Center

1200 First Street, NE | Washington, DC 20002 | T 202.442.5885 | F 202.442.5026 | dcps.dc.gov

2

Cafeteria Ceiling Grid

1200 First Street, NE | Washington, DC 20002 | T 202.442.5885 | F 202.442.5026 | dcps.dc.gov

3

Ground Floor Corridor

1200 First Street, NE | Washington, DC 20002 | T 202.442.5885 | F 202.442.5026 | dcps.dc.gov

4

Exterior Brick Screen Wall

1200 First Street, NE | Washington, DC 20002 | T 202.442.5885 | F 202.442.5026 | dcps.dc.gov

5

1200 First Street, NE | Washington, DC 20002 | T 202.442.5885 | F 202.442.5026 | dcps.dc.gov

6

Recommended