View
218
Download
0
Category
Preview:
Citation preview
8/10/2019 PM Resource Leveling
1/17
Scheduling With Constrained
Resources
So far have assumedall resources required for
project will be available.
Q: Will they be available? What happens if theyare not?
8/10/2019 PM Resource Leveling
2/17
Resource Loading
Resource Loading: amount of a specifiedresource required throughout a project
Assume have a well-defined project
Have defined the kinds of resourcesand amount or numberof
resources for every work package
8/10/2019 PM Resource Leveling
3/17
Resource Loading Analysis:
apply to constrainedresources
Example: Work Package D resource requirements:
Programmer 160 hrs.
Systems Analyst 40 hrs.
Mainframe Computer 10 hrs.
Suppose Systems Analyst time and Mainframe Computer time, no
problem. Hence, ignore thesein resource loading analysis.
Programmers are very busy and in short supply.
Hence, focus on this in resource loading analysis
8/10/2019 PM Resource Leveling
4/17
Resource Loading Analysis (contd)
Assume
Work Package D must be completed in 2 weeks
Each programmer can devote at most 20 hrs per week.
Thus, the required programmers for Work Package D:
160 hrs
2 wks20
80 hrs. 80 4 programmerswk
wkwk hrs
hrs
programmer
= =
Work Package D will require 4 programmers for two weeks
Similar estimates are made for number of programmers for every
work package in the project
8/10/2019 PM Resource Leveling
5/17
Activity
Immediate
Predecessors
Time
(weeks)
Resource
(Programmers)A --- 2 3
B --- 3 8
C --- 2 6
D --- 2 4
E A 4 9
F C 2 7
G D, F 3 2
H B, G 4 1
B
D
H
F G
E
C
A
Start
End
Project Network
8/10/2019 PM Resource Leveling
6/17
Resource Loading Analysis
Questions:
According to the schedule, how many programmers will
be needed each week for the project?
Given the shortage of programmers, will there be
enough programmers for the project?
8/10/2019 PM Resource Leveling
7/17
Gantt Chart, early times
1 2 3 4 5 6 7 8 9 10 11
CP
A, 3 E, 9
B, 8
C, 6 F, 7 G, 2 H, 1
D, 4
Key:
e.g., Activity D requires 4 programmers
According to the schedule, how many programmers will
be needed each week for the project?
8/10/2019 PM Resource Leveling
8/17
24
1 2 3 4 5 6 7 8 9 10 11
A
E
B
C
F
G
H
D
24
22201816141210
8642
B
F
G
21
16
11
2 1
E
Resource Loading Diagram
Early Times
A, 3 E, 9
B, 8
C, 6 F, 7 G, 2 H, 1D, 4
1 2 3 4 5 6 7 8 9 10 11
Gantt Chart
For example, during weeks 1 and 2
Activities A, B, C, and D are
scheduled
So, number of programmers needed is
3 + 8 + 6 + 4 = 21
In week 3
Activities E, B, and F are scheduled
So, 9 + 8 + 7 = 24
(Most project management software perform this kind of analysis)
8/10/2019 PM Resource Leveling
9/17
Resource Leveling
What happens if required resources exceed the
available amount?
Use resource leveling technique
8/10/2019 PM Resource Leveling
10/17
Resource Leveling (contd)
1 2 3 4 5 6 7 8 9 10 11
A
E
B
C
F
G
H
D
24
22
20
18
1614
12
10
8
6
4
2B
F
G
2124
16
2 1E
Resource Loading using
Early Event Times
week
The schedule is infeasiblesince
weeks 1-4 require more than 12
programmers
Suppose maximum number of
programmers available forproject in any given week = 12
8/10/2019 PM Resource Leveling
11/17
Resource Leveling (contd)
Many activities are scheduled early in the project
Not all of these haveto be scheduled then
They can be delayed
Delaying activities defers need for resources
8/10/2019 PM Resource Leveling
12/17
1 2 3 4 5 6 7 8 9 10 11 12
A* E*
B*
C F G H
D
Use trial and error, delay activities along their slack ties, check impacton total required resources.
*For example, delay
A by 2 weeks
B by 4 weeks
E by 5 weeks
8/10/2019 PM Resource Leveling
13/17
Resource Leveling Viola!
Project can be completed in 11 weeks with no more than10 programmers per week
*Resource loading after rescheduling A, B, and E
1 2 3 4 5 6 7 8 9 10 11
C
D
G
10
8
6
4
2
FE*
H
Program
mers
A*
B*
B*
C F G H
D
A* E*
8/10/2019 PM Resource Leveling
14/17
Resource Leveling (contd)
Method is called resource leveling because it results in
leveling of peak requirements
Notice in example, if constraint on programmers had
been less than 10, project would not be able to complete
project in 11 weeks
1 2 3 4 5 6 7 8 9 10 11
C
D
G
108642
F
E*
H
A*B*
8/10/2019 PM Resource Leveling
15/17
Resource Leveling (contd)
When project has multiple constrained resources,
Repeat same analysis for each
All resources must be leveled simultaneously so no
resource exceeds constraints This is one application in which project management
software that is invaluable
When PM does not have direct authority over resources
Speak to managers of resources. Try to get suggestions abouthow to meet schedule with limited resources.
8/10/2019 PM Resource Leveling
16/17
Multi-Project Scheduling
Use similar approach to schedule multiple projects that share
constrained resources Create resource loadings for projects scheduled at same time.
Combined to yield multi-project loading.
AB
E
F
C
D
A
B
E
F
CD
Time
Tasks
Project A
Project B
Time
8/10/2019 PM Resource Leveling
17/17
24222018161412108642
Project A
Project B
Multi-Project Scheduling
If loading exceeds constraints, tasks within projects are delayedalong their slack times.
If that fails, then tasks in lower-priority projects are delayed further or
(lower priority projects are delayed in their entirety) Software for multi-project planning and scheduling have this
capability
Recommended