Phase 1 Works 26 th July 2010 to 15 th October 2010 – 12w Phase 5 Works 1 st August 2011...

Preview:

DESCRIPTION

UNIVERSITY of DURHAM - SCIENCE SITE ENVIRONMENTAL IMPROVEMENTS. 6. 4. 2. 1. 5. 3. Phase 1 Works 26 th July 2010 to 15 th October 2010 – 12w Phase 5 Works 1 st August 2011 to 26 th August 2011 – 5w - PowerPoint PPT Presentation

Citation preview

3

1

5

4

6

Phase 1 Works 26th July 2010 to 15th October 2010 – 12w Phase 5 Works 1st August 2011 to 26th August 2011 – 5w

Phase 2 Works 18th October 2010 to 17th December 2010 – 9w Phase 6 Works 25th June 2012 to 03rd August 2012 – 6w

Phase 3 Works 20th December 2010 to 18th March 2011 – 9w

Phase 4 Work 21st March 2011 to 29th July 2011 – 19w

2

UNIVERSITY of DURHAM - SCIENCE SITE ENVIRONMENTAL IMPROVEMENTSUNIVERSITY of DURHAM - SCIENCE SITE ENVIRONMENTAL IMPROVEMENTS

REV.10

11/06/2010

SSEI PHASE 126th July 2010 to 16th October 2010

ACCESS / EGRESS DURING PHASE 1 WORK

University to Have Personnel Available During Access & Egress of

Wagons