PATHUMTHANI Bangkok : Area 1,568.7 km Population 5.69 ... · 3. Financial • BMA 1. Onsite WWTP...

Preview:

Citation preview

• 300 Sampling Points in 165 major canals and9 Sampling Points in Chao Praya River

• Major Sources of Wastewater 1. Domestic 75%2. Industry 20%3. Agriculture 5%

• Measures undertaken

Water Quality Monitoring Program in Bangkok

Year 2014

1. Construction- Onsite WWTP- Community WWTP- Central WWTP

2. Non-construction- Law - Public Relation

75%

20%

5%

NONTHABURI

PATHUMTHANI

SAMUT PRAKAN

SAMUT SONGKRAM

BANGKOK

THAILANDBANGKOK MAP

• Bangkok : Area 1,568.7 km2 Population 5.69 million (2014)

• Surface Water: Canal 1,682 canals Length 2,604 km• Chao Praya River 372 km (Total Length) Bangkok 35 km • Source of Water Supply to Bangkok and vicinity:

Upstream of Chao Praya River at Sam Lae, Pathum Thani • Water Consumption Rate in Bangkok (2014) : 2.5 mil.

m3/day

BangsueEECC

1.Year of

operation:

August 2014

2.Service

Area:

20.7km2

3.Population

223,990

4.Capacity120,000

m3

/d

Source: JICA, 2011

4 WWTPs Implementation 15 WWTPs in Future Plan8 WWTPs under O&M

• Capacity 1.12 mil m3/d• 71.3% of WW generation• Construction Cost 34,088 mil B• O&M Cost 485 mil. Baht/year

• Capacity 1.12 mil m3/d• 96.7% of WW generation• Construction Cost 71,033 milB• O&M Cost 1,190 mil. Baht/year

Wastewater 2.5 mil m3/d

Wastewater 2.54 mil m3/d

Future Wastewater 3.55 mil m3/d

Year 2014Year 2022 Year 2042

• To serve WWTP 100% of developed area in Bangkok

1. Policy Target

•Domestic WW(75%) and Agriculture(5%) are responsible by “BMA”

•Industrial WW(20%)responsible by Ministry of Industry

2. Institutional

• Construction cost sharing of Central Government and BMA vary between 75:25 to 40:60

• O&M Cost 100% by BMA

3. Financial• BMA

1. Onsite WWTP(Household) Regulation control2. Community WWTP (NHA)3. Central WWTP Control by BMA

4. Good Practices

• Capacity 1.12 mil m3/d• 45.5% of WW generation• Construction Cost 24,603 milB• O&M Cost 559 mil. Baht/year

Bangsue Education and Environmental Conservation Center

• The 1st underground WWTP of Bangkok with capacity 120,000 m3/day (2,000 m3/day treated by membrane technology and use for water fall in front of the building and supply to the park)

• Construction Year 2008 to 2014 and Construction Cost 4,732 million Baht from BMA (year 2008 to 2014)

• Education and Environmental Conservation Center (Meeting room, Exhibition hall, History room of Sewerage System and Water Quality Management and Environmental Library)

• Royal initiated project (the Chaipattanaaerator, and growing plant in the pond for wastewater treatment purpose)

Both Community WWTP and Central WWTP should be served to all developed area in Bangkok

• “Public Private Partnership (PPP)” should be implemented for the future projects in order to solve the financial problems

• “Collecting fee” is another source of fund for the operation and maintenance of wastewater treatment projects

• “Treated Wastewater” is the alternative water for using in some specific activities (6% of treated wastewater using for watering plant, cleaning the road, flushing system etc.)

• “People Participation” will pay an important role to improve the surface water quality

• “Energy Saving Technology” for Wastewater Treatment System should be studied and applied for solving global warming

• Wastewater Treatment Plant implementation and O&M are the good practice not only for engineers, scientists, students and people in Thailand but also in various countries especially in ASEAN countries

• Cooperation among experts, officials, administrators or policy markers in various activities, for example : Training Program, StudyVisit, Seminar, Research andStudy, Sharing technologyetc.

Recommended