Pasadena Water and Power

Pasadena Non-Potable Water Project

Public Meeting

Pasadena Water and Power December 6, 2016

Pasadena Water and Power

2

Pasadena Non-Potable Water Project Phase 1

• Supply - 700 AFY • Customers - 4 • Pipelines - 5 miles • Reservoirs - 2, 1 in Glendale • Pressure reducing station - 1 • Upgrades to Glendale pumping

system

Pasadena Water and Power

Community Concerns During EIR

3

• Linda Vista Community > Impact to Canary Island Pine trees on Laurel Street > Cost increase due to buried utilities > Disruption to residents

• Sheldon Area Community > Disruption to residents

• Feb 22, 2016 - EIR Public Hearing > City Council directed staff to evaluate two alternative

pipeline routes

Pasadena Water and Power

Discussion Topics

4

• Alternative Routes – reputable consultants > RMC - pipeline evaluation and environmental > ESA - arborist report > W. A. Rasic Construction - costs and schedule > Amec Foster Wheeler - geotechnical review

• Grant application > Archaeological report > Gnatcatcher survey

• Basin Salt & Nutrient Management Plan

Pasadena Water and Power

1. Alignment evaluation technical memo > Contractor’s cost estimate & schedule > Geotechnical engineering review

2. Arborist report 3. Environmental evaluation of the

alternatives - CEQA memo 4. Archaeological testing report 5. Gnatcatcher survey

Reports Available Online - October 31, 2016

5

Pasadena Water and Power

Alternative Pipeline Routes Map

6

Pasadena Water and Power

Arborist Report

7

Certified Senior Arborist with extensive experience • Tree assessments, health risk

assessments & tree appraisals

• Expert witness testimony

• Services to cities of Los Angeles, Malibu, Calabasas, Agoura Hills, Thousand Oaks, Santa Clarita, Commerce, to counties of Los Angeles, Ventura, and San Luis Obispo

Pasadena Water and Power

Arborist Report

8

• 160 trees surveyed with canopies within 30 feet of pipeline

• Tree rating based on distance to pipeline, exposed surface roots, lifting of soil and pavement, leaning

• Roots seek water, oxygen, nutrients and soil space

• Most roots grow in top 18” soil

• Approved West Route - 58 trees

• Alternative West Route - 37 trees

• Less than 3% roots in trench zone

Pasadena Water and Power

Rendering of Laurel St. Looking East

9

Arborist findings - including the Canary Island Pine trees on Laurel • Canary Island Pines not impacted • Trees Less than 3% of the tree roots

expected in the trench zone • Tree roots limited in roads - soil

compaction, lack of water & oxygen • More trees along the approved

routes (58 vs. 37)

Pasadena Water and Power

• Environmental impacts of the Approved & Alternative Routes less than significant > Temporary issues: noise, traffic, dust, limited

access to properties during construction > Approved route impacts residents > Alternative route impacts recreational users near

Rose Bowl

• If Alternative Route Selected

> CEQA will have to be revised and approved by City Council - 4 to 5 months process

Environmental Evaluation - CEQA Memo

10

Pasadena Water and Power

• Cost estimates factor in: > Limited work hours (some streets): 8:30 am - 3:30 pm > Tree and tree roots > Existing utilities and residential services

• Approved west route - 2,900 feet > $1.32 million - estimated cost

• Alternative west route - 5,200 feet > $2.23 million - estimated cost

Contractor’s Estimates West Routes

11

Pasadena Water and Power

Minimize Pipeline Construction Impacts

12

• Location of utilities during design • Contractor will locate utilities &

services prior to pipeline excavation • Adjusted design before construction • Experienced contractor • Full-time construction inspection • Full-time certified arborist • Advanced notices to residents • Limited work hours in small streets • Construction Staging and Traffic

Management Plan • Noise and dust control

Pasadena Water and Power

Geologic Hazards - Liquefaction

13

• Alternative Route - longer pipeline in potentially liquefiable zones > Liquefaction - saturated

loose sandy soils can lose strength during an earthquake that causes settlement of the ground

> Storing water behind Devil’s Gate Dam may increase water table

Pasadena Water and Power

Construction Impacts

• Approved West Route > 10 weeks > Temporary impact to residents’ driveways - 1 to

3 days

• Alternative West Route > 14 weeks > One lane accessible for vehicular and bicyclists

14

Pasadena Water and Power

Alignment Evaluation Summary West Routes

15

Evaluation Criteria

Linda Vista Community

Approved Route

Alternative Route

Environmental Impacts = = Potential Impacts to Trees (& Canary Island Pines) + Geohazard Conditions - Liquefaction + Construction Challenges + Capital Cost * + Operations and Maintenance Cost + Schedule Impact + Potential Loss of State Funding + * The alternative route is more costly than the approved by ~$1 million Overall the Approved Route in the EIR is superior to the Alternative Route + Indicates the better option

Pasadena Water and Power

Other Reports

16

• Archaeological report > 5 trenches > 3 professional archaeologists > 7 letters sent out > 3 Native American monitors

¤ Andrew Salas, Gabrielino Band of Mission Indians - Kizh Nation ¤ Adrian Morales, Gabrielino Tongva San Gabriel Band of Mission

Indians ¤ Robert Dorame, Gabrielino Tongva Indians of California

> Findings: no prehistorical artifacts or features found

• Gnatcatcher survey - no gnatcatchers > Pre-construction surveys required

Pasadena Water and Power

Raymond Basin Salt & Nutrient Management Plan

17

• Raymond Basin Salt & Nutrient Management Plan > Assimilative Capacity (AC) = Objective limit – Existing conditions > State – A single project is not to exceed 10% of the AC > Up to 10% of salt & nutrient (“load”) in recycled water is projected to

reach the water table > AC for the Monk Hill Sub-basin is 225 acre feet per year (AFY) of load

& the Pasadena Sub-basin is 405 AFY of load

• Pasadena Non-Potable Water Project > Project buildout will provide 2,700 AFY for irrigation, 400 AFY in the

Monk Hill & 2,300 AFY in the Pasadena Sub-basin > Ten percent of the load or 40 AFY in the Monk Hill & 230 AFY in the

Pasadena Sub-basin will reach the aquifer which is less than the AC limits for each sub-basin

Pasadena Water and Power

18

Two Community Meetings

• Today, December 6, 2016 at 6 p.m. > Pipeline route: Linda Vista Ave., Laurel St., Parkview Ave. or

(alternative route) Salvia Canyon, West Dr.

• Thursday, January 12, 2017 at 6:30 p.m. > Pipeline route: Arroyo Blvd., Rose Bowl Dr. or (alternative

route) Rosemont Ave.

> Location: Brookside Golf Club, Arroyo Room

• Five reports available at: http://cityofpasadena.net/waterandpower/recycledwater/

Pasadena Water and Power

Questions?