TRANSNET PIPELINESTENDER NUMBER: PYP/W1/6/21/1646DESCRIPTION OF THE WORKS: CONSTRUCTION OF THE FIRE PROTECTION SYSTEM UPGRADE FOR THEFUEL HANDLING AREAS OF THE TARLTON DEPOT AND IRP REFRACTIONATOR ONLY INCLUSIVE OFDEMOLITION, CIVIL, STRUCTURAL, BUILDING, MECHANICAL, ELECTRICAL, INSTRUMENTATION AND CONTROLSYSTEM SUPPLY, INSTALLATION AND COMMISSIONING
Contract PAGE 1 Part C2: Pricing DataPRO-FAT-0216 Rev02 Part C2.1: Pricing Instructions ECC Option B
PART 2: PRICING DATA
Documentreference
Title No ofpages
C2.1 Pricing instructions: Option B 3
C2.2 The bill of quantities 48
TRANSNET PIPELINESTENDER NUMBER: PYP/W1/6/21/1646DESCRIPTION OF THE WORKS: CONSTRUCTION OF THE FIRE PROTECTION SYSTEM UPGRADE FOR THEFUEL HANDLING AREAS OF THE TARLTON DEPOT AND IRP REFRACTIONATOR ONLY INCLUSIVE OFDEMOLITION, CIVIL, STRUCTURAL, BUILDING, MECHANICAL, ELECTRICAL, INSTRUMENTATION AND CONTROLSYSTEM SUPPLY, INSTALLATION AND COMMISSIONING
Contract PAGE 1 C2.1Part C2: Pricing Data Pricing instructions ECC3 Option B
C2.1 Pricing instructions: Option B
1. The conditions of contract
1.1. How the contract prices work and assesses it for progress paymentsClause 11 in NEC3 Engineering and Construction Contract, June 2005 (ECC3) Option B states:
Identified anddefined terms
1111.2 (21) The Bill of Quantities is the bill of quantities as changed in accordance
with this contract to accommodate implemented compensation events and foraccepted quotations for acceleration.(22) Defined Cost is the cost of the components in the Shorter Schedule ofCost Components whether work is subcontracted or not excluding the cost ofpreparing quotations for compensation events.(28) The Price for Work Done to Date is the total of the quantity of the work which the Contractor has completed for each item
in the Bill of Quantities multiplied by the rate and a proportion of each lump sum which is the proportion of the work covered
by the item which the Contractor has completed.
Completed work is work without Defects which would either delay or becovered by immediately following work.
(31) The Prices are the lump sums and the amounts obtained by multiplyingthe rates by the quantities for the items in the Bill of Quantities.
This confirms that Option B is a re-measurement contract and the bill comprises only items measured usingquantities and rates or stated as lump sums. Value related items are not used. Time related items are itemsmeasured using rates where the rate is a unit of time.
1.2. Function of the Bill of QuantitiesClause 55.1 in Option B states, “Information in the Bill of Quantities is not Works Information or SiteInformation”. This confirms that instructions to do work or how it is to be done are not included in the Bill, butin the Works Information. This is further confirmed by Clause 20.1 which states, “The Contractor Providesthe Works in accordance with the Works Information”. Hence the Contractor does not Provide the Works inaccordance with the Bill of Quantities. The Bill of Quantities is only a pricing document.
1.3. Guidance before pricing and measuringEmployers preparing tenders or contract documents, and tendering contractors are advised to consult thesections dealing with the bill of quantities in the NEC3 Engineering and Construction Contract (June 2005)Guidance Notes before preparing the bill of quantities or before entering rates and lump sums into the bill.
Historically bill of quantities based contracts in South Africa have been influenced by the differentapproaches of the civil engineering and building sectors of the industry through their respective disciplinebased standard forms of contract and methods of measurement. This is particularly apparent in theapproach to the Preliminary and General bill. On the other hand, because ECC3 caters for a number ofdisciplines in the same contract, including electrical works, a different approach not currently found in localmethods of measurement to the Preliminary & General bill items may have been used.
TRANSNET PIPELINESTENDER NUMBER: PYP/W1/6/21/1646DESCRIPTION OF THE WORKS: CONSTRUCTION OF THE FIRE PROTECTION SYSTEM UPGRADE FOR THEFUEL HANDLING AREAS OF THE TARLTON DEPOT AND IRP REFRACTIONATOR ONLY INCLUSIVE OFDEMOLITION, CIVIL, STRUCTURAL, BUILDING, MECHANICAL, ELECTRICAL, INSTRUMENTATION AND CONTROLSYSTEM SUPPLY, INSTALLATION AND COMMISSIONING
Contract PAGE 2 C2.1Part C2: Pricing Data Pricing instructions ECC3 Option B
The NEC approach to the P & G bill assumes use will be made of method related charges for Equipmentapplied to Providing the Works based on durations shown in the Accepted Programme, fixed charges forthe use of Equipment that is required throughout the construction phase, time related charges for peopleworking in a supervisory capacity for the period required, and lump sum charges for other facilities orservices not directly related to performing work items typically included in other parts of the bill.
2. Measurement and payment
2.1. Symbols
The units of measurement described in the Bill of Quantities are metric units abbreviated as follows:
Abbreviation Unit% percenth hourha hectarekg kilogramkl kilolitrekm kilometrekm-pass kilometre-passkPa kilopascalkW kilowattl litrem metremm millimetrem2 square metrem2-pass square metre passm3 cubic metrem3-km cubic metre-kilometreMN meganewtonMN.m meganewton-metreMPa megapascalNo. numberProv sum1 provisional sumPC-sum prime cost sumR/only Rate onlysum Lump sumt ton (1000kg)W/day Work day
1 Provisional Sums should not be used unless absolutely unavoidable. Rather include specifications andassociated bill items for the most likely scope of work, and then change later using the compensationevent procedure if necessary. This is because tenderers cannot programme effectively for unknownscopes of work
TRANSNET PIPELINESTENDER NUMBER: PYP/W1/6/21/1646DESCRIPTION OF THE WORKS: CONSTRUCTION OF THE FIRE PROTECTION SYSTEM UPGRADE FOR THEFUEL HANDLING AREAS OF THE TARLTON DEPOT AND IRP REFRACTIONATOR ONLY INCLUSIVE OFDEMOLITION, CIVIL, STRUCTURAL, BUILDING, MECHANICAL, ELECTRICAL, INSTRUMENTATION AND CONTROLSYSTEM SUPPLY, INSTALLATION AND COMMISSIONING
Contract PAGE 3 C2.1Part C2: Pricing Data Pricing instructions ECC3 Option B
2.2. General assumptions
2.2.1. Unless otherwise stated, items are measured net in accordance with the drawings, and noallowance has been made in the quantities for waste.
2.2.2. The Prices and rates stated for each item in the Bill of Quantities shall be treated as being fullyinclusive of all work, risks, liabilities, obligations, overheads, profit and everything necessary asincurred or required by the Contractor in carrying out or providing that item.
2.2.3. Clause 63.13 in Option B provides that these rates and Prices may be used as a basis forassessment of compensation events instead of Defined Cost.
2.2.4. Where this contract requires detailed drawings, designs or other information to be provided, andno rates or prices are included in the bill specifically for such matters, then the Contractor isdeemed to have allowed for all costs associated with such requirements within the tenderedrates and Prices in the Bill of Quantities.
2.2.5. An item against which no Price is entered will be treated as covered by other Prices or rates inthe bill of quantities. If a number of items are grouped together for pricing purposes, this will betreated as a single lump sum.
2.2.6. The quantities contained in the Bill of Quantities may not be final and do not necessarilyrepresent the actual amount of work to be done. The quantities of work assessed and certifiedfor payment by the Project Manager at each assessment date will be used for determiningpayments due and not the quantities given in the Bill of Quantities.
2.2.7. The short descriptions of the items of payment given in the bill of quantities are only for thepurposes of identifying the items. More detail regarding the extent of the work entailed undereach item is provided in the Works Information.
2.3. Amplification of or assumptions about measurement itemsFor the avoidance of doubt the following is provided to assist in the interpretation of descriptions given inthe method of measurement. In the event of any ambiguity or inconsistency between the statements inthe method of measurement and this section, the interpretation given in this section shall be used.
TRANSNET PIPELINESTENDER NUMBER: PYP/W1/6/21/1646DESCRIPTION OF THE WORKS: CONSTRUCTION OF THE FIRE PROTECTION SYSTEM UPGRADE FOR THEFUEL HANDLING AREAS OF THE TARLTON DEPOT AND IRP REFRACTIONATOR ONLY INCLUSIVE OFDEMOLITION, CIVIL, STRUCTURAL, BUILDING, MECHANICAL, ELECTRICAL, INSTRUMENTATION AND CONTROLSYSTEM SUPPLY, INSTALLATION AND COMMISSIONING
Contract PAGE 1 Part C2: Pricing DataPRO-FAT-0216 Rev02 C2.2: Bill of quantities
C2.2 the bill of quantities
Use this page as a summary page or as a cover page to the bill of quantities.
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
BILL NO. 1 - PRELIMINARY AND GENERAL ITEMS
NOTES
This Bill of Quantities of measured in accordance with the StandardSystem of Measuring Building Work 2013 (Sixth Edition, Second Revision)unless noted otherwise in these Bills of Quantities.
The agreement is to be the NEC 3, June 2005, and other contractdocuments that together form the contract between the employer andcontractor
The preliminaries are to be based on the NEC3 contract and shall bedeemed to be incorporated herein
Tenderers are referred to the abovementioned documents for the fullintent and meaning of each clause thereof (hereinafter referred to byheading and clause number only) for which such allowance must bemade as may be considered necessary
Where standard clauses or alternatives are not entirely applicable to thiscontract such modifications, corrections or supplements as will apply aregiven under each relevant clause heading
Where any item is not relevant to this specific contract such item ismarked N/A (signifying "not applicable")
1.1 Fixed Charge Items
1.1.1 Contractual Requirements Sum
1.1.2 Project Manager/Supervisor site facilities Sum
1.1.3 Offices and storage sheds Sum
1.1.4 Site notice board Sum
1.1.5 Workshops Sum
1.1.6 Laboratories Sum
1.1.7 Ablution and latrine facilities Sum
1.1.8 Tools and equipment Sum
1.1.9 Water supplies, electric power and communications Sum
1.1.10 Dealing with water (Sub clause 5.5 SABS 1200 A-1986) Sum
1.1.11 Access (Sub clause 5.8 SABS 1200 A-1986) Sum
1.1.12 Plant Sum
1.1.13 Temporary Fencing and Access Control Sum
1.1.14 Remove Contractor's Site establishment on completion Sum
1.1.15 Reinstatement of Laydown Area to Existing Condition Sum
Carried forward
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 1 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 2 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Brought forward
1.1.16 Environmental Sum
1.1.17 Other fixed-charge obligations Sum
1.2 Time Related Items
1.2.1 Contractual Requirements Sum
1.2.2 Offices and storage sheds Sum
1.2.3 Project Manager/Supervisor site facilities Sum
1.2.4 Workshops Sum
1.2.5 Laboratories Sum
1.2.6 Ablution and latrine facilities Sum
1.2.7 Tools and equipment Sum
1.2.8 Water supplies, electric power and communications Sum
1.2.9 Dealing with water (Sub clause 5.5) Sum
1.2.10 Access (Sub clause 5.8) Sum
1.2.11 Plant Sum
1.2.12 Temporary fencing and access control Sum
1.2.13 Reinstatement of laydown area to existing condition Sum
1.2.14 Supervision Sum
1.2.15 Company and head office overhead costs Sum
1.2.16 Environmental Sum
1.2.17 Other time-related obligations Sum
Daywork
Labourer Hr Rate only
Unskilled Labourer Hr Rate only
Semi-skilled Labourer Hr Rate only
Artisan Hr Rate only
Foreman / Supervision Hr Rate only
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 3 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNTTOTAL CARRIED TO SUMMARY
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 4 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
BILL NO. 2 - EARTHWORKS
NOTE: Tenderers are required to study the Model Preambles forTrades before pricing this Bill
Note
GENERAL NOTES TO TENDERERS
Tenderers are to inspect the drawings issued with these Bills ofQuantities and to satisfy themselves as to the nature and therequirements of the Contract works. Failure to do so will be thecomplete responsibility of the Tenderer and no claims whatsoever will beentertained in this regard
Note
Tenderers are to read the descriptions, which are intended as a means ofidentifying various facets of the work, in conjunction with the drawings.Tenderers shall allow for all costs in connection with the various itemstaking full cognisance of both the drawings and the Bills of Quantities
Note
Tenderers shall notify the Quantity Surveyor in writing of anydiscrepancies encountered upon which clarification will be given by theQuantity Surveyor in writing to the Tenderer. Failure to do so will be thecomplete responsibility of the Tenderer and no claims whatsoever will beentertained in this regard
Note
Tenderers are to note that setting out of the works will be the completeresponsibility of the Tenderer and they should therefore acquaintthemselves with the site boundaries, site co-ordinates, datum levels etc.Failure to do so will be the complete responsibility of the Tenderer andno claims whatsoever will be entertained in this regard
GENERAL Note
Note: The cost for prescribed density tests on filling and sending them toan approved laboratory for testing and pay all charges in connectiontherewith, shall be allowed for in the compaction and filling rates
Note
Note: Due to the nature of the site, All Excavation to Trenches and Holesshall be by hand unless noted otherwise. Excavation shall be paid forbased on actual quantity of material excavated, taking into account asafe angle of repose.
Note
Note: Excavation to Pipe Trenches shall be measured in accordance withSANS 1200
Note
Note: As far as possible excavation shall be battered to a safe angle, andthe excavation Volume in batters shall be measured as extra over, as perthe depth categories above, this angle of repose shall be based on thesoil stability. Where obstructions or excavations close to existingstructures or roads necessitate shoring, this shall be approved by theEngineer
Note
Note: The Entire site is deemed freehaul Distance, a stockpile area withinthe site, or immediately adjacent to the site shall be made available tothe contractor for temporary stockpiling of material, etc, all excavationrates shall include for handling of material to the stockpile, whereintended for re-use as filling on site shall include for loading andtransport from stockpile to the designated work areas
Note
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 5 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNTIf the contractor considers that any of the excavations are more difficultin nature than excavations in "earth", he shall immediately notify theEngineer and quantity surveyor in writing. If the contractor fails to makesuch notification, the excavations shall be deemed to be in "earth" andshall be measured, and valued, accordingly
Note
The contractor shall protect the excavations from the ingress of water.Any water which occurs in the excavations, whether as a result ofseepage, rain, or other causes, shall immediately be removed by baling,pumping, or other approved means
Note
Note: Prior to backfilling sections of pipe, a pressure test carried out forthat section of pipe shall be submitted to the Engineer for BackfillingRelease. No payment for backfilling shall be made until this is submitted.
Note
2.1 DEMOLITION AND SITE CLEARANCE
2.1.1 Demolition of premix surfacing
2.1.1.1 Sawcut into Premix Surfacing 50mm deep m 741
2.1.1.2 Demolition and removal of Premix Surfacing 50mm thick, remove anddispose from site to a dumping site located by the contractor includingall charges
m2 1 228
2.1.2 Demolition of Concrete
2.1.2.1 Sawcut 200-250mm deep into Concrete for demolition m 110
2.1.2.2 Demolition of 200-250mm Concrete, Including Carting off site to a dumpsite located by the Contractor, Including all Charges
m3 28
2.1.3 Removal of Existing Above Ground Fire Reticulation
2.1.3.1 Removal of Existing above ground Fire Reticulation Systems once NewFire System has been Commissioned and handed over to operations
Sum 1
2.1.3.2 Strip out Existing Pump House Building and Set Aside Equipment for useby Client. (See attached photographs for a general idea of whatequipment is to be set aside).
Sum 1
2.1.4 Demolition of Buildings
2.1.4.1 Demolition of Existing Pump House Building, Including Disposal off Siteto a Dumping Site Located by the Contractor, including all Charges.(Concrete/brick structure ± 124m², half double storey, concrete slabroof. See attached photographs).
Sum 1
2.1.5 Removal of Existing Dam Lining
2.1.5.1 Removal of Existing Plastic Dam Lining, Including Disposal off Site to aDumping Site Located by the Contractor, including all Charges
m2 1 350
2.1.6 Fencing & barricading
2.1.6.1 Option 1 - 1.8m high hoarding comprising 150mm diameter x 2.4m highgumpoles @ 2.4m centres including 500 × 500 × 600mm deep concretefoundation and covered with and including IBR sheeting
m 200
Carried forward
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 6 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 7 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Brought forward
2.1.6.2 Option 2 - 1.8m high hoarding comprising 150mm diameter x 2.4m highgumpoles @ 2.4 centres including 500 × 500 × 600mm deep concretefoundation and covered with and including bonnex mesh wire fencingwith shade cloth
m 200
2.2 EXCAVATION, FILLING, ETC
2.2.1 Excavate in compacted pickable material as defined not exceeding 2 mdeep below reduced or filled up ground level and deposit on site wheredirected - Machine Excavation
2.2.1.1 Bulk Excavation (No Interim Stockpiling, ie Cut to Spoil) m3 3 193
2.2.1.2 Bulk Excavation m3 1 320
2.2.1.3 Reduce Levels in Roadways m3 369
2.2.1.4 Holes (Bases, etc) m3 637
2.2.1.5 Trenches (Strip footings, ground beams, etc) m3 136
2.2.2 Excavate in compacted pickable material as defined exceeding 2 m andnot exceeding 4m deep below reduced or filled up ground level, anddeposit on site where directed - Machine Excavation
2.2.2.1 Bulk Excavation (No Interim Stockpiling, ie Cut to Spoil) m3 845
2.2.2.2 Bulk Excavation m3 420
2.2.2.3 Holes (Bases, etc) m3 155
2.2.2.4 Trenches (Stip footings, ground beams, etc) m3 25
2.2.3 Excavation for Pipe Trenches - Excavation measured net, Batteringmeasured elsewhere as extra over - Hand Excavation
2.2.3.1 0 - 1 m deep m3 4 646
2.2.3.2 1 - 2 m deep m3 1 821
2.2.3.3 2 - 3 m deep m3 24
2.2.4 Extra Over Pipe Trench Excavation for Battering of sides to a slope asagreed by the engineer - Hand Excavation
2.2.4.1 0 - 1 m deep m3 2 948
2.2.4.2 1 - 2 m deep m3 251
2.2.4.3 2 - 3 m deep m3 2
2.3 WORKING SPACE EXCAVATIONS
2.3.1 Back excavation of vertical sides of excavation in earth for working space,including backfilling compacted to 93% Mod AASHTO density
Carried forward
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 8 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 9 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Brought forward
2.3.1.1 Exceeding 500mm and not exceeding 1500mm deep for placing andremoving formwork to walls etc. 500mm away from excavated face
m2 524
2.3.1.2 Exceeding 1500mm and not exceeding 3000mm deep for placing andremoving formwork to walls etc. 500mm away from excavated face
m2 132
2.4 EXCAVATIONS IN STRATA OF A MORE DIFFICULT CHARACTER
2.4.1 Extra over trench and hole excavations in earth for excavation in Rock bymeans of:
2.4.1.1 Compressors - m3 550
2.4.1.2 Establishment (for Compressor) No 14
2.4.1.3 Daily Standby Rate (for Compressor) days 33
2.4.1.4 TLB, Small Excavator Access - m3 550
2.4.1.5 Establishment (for TLB, Small Excavator Access) No 14
2.4.1.6 Daily Standby Rate (for TLB, Small Excavator Access) days 33
2.4.1.7 20t Excavator Access - m3 550
2.4.1.8 Establishment (for 20t Excavator Access) No 14
2.4.1.9 Daily Standby Rate (for 20t Excavator Access) days 33
2.4.2 Extra over all excavations for carting away
2.4.2.1 Surplus material from excavations and/or stock piles on site to adumping site to be located by the contractor
m3 10 483
2.4.3 Risk of collapse of excavations
2.4.3.1 Sides of trench and hole excavations not exceeding 1,5m deep m2 524
Sides of trench and hole excavations exceeding 1,5m. m2 132
2.4.4 Keeping excavations free of water
2.4.4.1 Keeping excavations free of water Item 1
2.5 FILLING ETC
2.5.1 Earth filling obtained from the excavations and/or prescribed stock pileson site, compacted to 93% Mod AASHTO density
2.5.1.1 Backfilling to trenches, holes, etc m3 6 523
2.5.2 G2 Crusher Run Earth filling supplied by the contractor, compacted to98% Mod AASHTO density
Carried forward
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 10 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 11 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Brought forward
2.5.2.1 Under floors, steps, pavings, etc and roadworks m3 260
2.5.3 G5 Earth filling supplied by the contractor, compacted to 95% ModAASHTO density
2.5.3.1 Under floors, steps, pavings, etc m3 5 144
2.5.3.2 Extra over 2.5.3.1 for cement stabilisation to C4 m3 280
2.5.3.3 Extra over 2.5.3.2 for cement provision t 24
2.5.4 G7 Earth filling supplied by the contractor, compacted to 95% ModAASHTO density
2.5.4.1 Under floors, steps, pavings, etc and roadworks m3 474
2.5.5 G9 Earth filling supplied by the contractor, compacted to 95% ModAASHTO density
2.5.5.1 Under floors, steps, pavings, etc and roadworks m3 795
2.5.6 Compaction of surfaces
2.5.6.1 Compaction of ground surface under floors, steps, pavings, etc includingscarifying for a depth of 150mm, breaking down oversize material,adding suitable material where necessary and compacting to 95% ModAASHTO density
m2 2 153
2.5.7 Prescribed density tests on filling
2.5.7.1 Modified AASHTO Density test as requested by Engineer No 110
2.6 BEDDING TO PIPE TRENCHES
2.6.1 Placing and finish to level bedding available from trench excavationswithin freehaul distance
2.6.1.1 Selected Material approved by Engineer m3 1 665
2.6.2 Placing and finish to level bedding imported from Commercial sources
2.6.2.1 Selected granular material for Bedding and Blanket (River sand) m3 3 345
2.6.2.2 Dust free 19mm stone aggregate m3 500
2.7 PREMIX, KERBING, AND STONE CHIP SURFACING
2.7.1 Premix
2.7.1.1 40mm Premix Surfacing to Roads, Including Prime Coat m2 1 515
2.7.2 Kerbing and Channelling
2.7.2.1 Kerb (SABS 927 fig. 6) 125 x 230mm high with 150 x 150 x 200mmconcrete haunching at back of each joint and bedding, includingexcavation, backfilling, etc
m 784
Carried forward
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 12 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 13 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Brought forward
2.7.3 Stone Chip Surfacings
2.7.3.1 26mm Stone Chip Surfacing 75mm thick m2 14 126
2.7.4 Paving
2.7.4.1 Carefully remove 80mm interlocking concrete pavers for re-instatementlater
m2 20
2.7.4.2 Re-install 80mm interlocking concrete pavers previously removed, withopen joints on, and including, 25mm thick river sand bed with sand andcement mixture swept into joints, hosed down and pointed with slightlykeyed joints, including preparation of ground, or filling
m2 20
2.7.4.3 Supply and install 80mm interlocking pavers to match existing, with openjoints on, and including, 25mm thick river sand bed with sand andcement mixture swept into joints, hosed down and pointed with slightlykeyed joints, including preparation of ground, or filling
m2 20
2.8 SOIL POISONING
2.8.1 Soil insecticide
2.8.1.1 Under floors etc including forming and poisoning shallow furrows againstfoundation walls etc, filling in furrows and ramming
m2 2 153
2.8.1.2 To bottoms and sides of trenches etc m2 3 335
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 14 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNTTOTAL CARRIED TO SUMMARY
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 15 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
BILL NO. 3 - LATERAL SUPPORT
NOTE: Tenderers are required to study the Model Preambles forTrades before pricing this Bill
Note
GENERAL NOTES TO TENDERERS
General notes, described in "BILL NO. 2 - EARTHWORKS", shall equallyapply to this Bill
Note
3.1 PLANKING, STRUTTING AND SHORING, ETC.
Note: Where agreed with the Supervisor, Shoring shall be installed.Shoring shall be designed and comply with all statutory requirements.The Shoring method shall be provided by the Contractor as part of thetender, taking into account that unknown services could be located up toa depth of 2.5m and the number of Pipes to be installed within a trench,Shoring shall be measured as the vertical surface area of trench side wallsupported, according to the total depth category, for example a trenchthat is 100m long, 2m deep shall have a surface area of shoring of400m2 (100m x 2m x 2 sides), should both sides of the trench wallrequire support
Note
3.1.1 Design, Supply and Install Shoring to Trench Excavations, with TrenchWidth less than 5m , where Battering of Trench Excavations is notPossible
3.1.1.1 0 - 1 m deep m2 20
3.1.1.2 1 - 2 m deep m2 3 069
3.1.1.3 2 - 3 m deep m2 92
3.1.2 Design, Supply and Install Sheet Piling to prevent undermining of existingstructures
3.1.2.1 2 - 3 m deep (Excavated face depth) m 55
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 16 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNTTOTAL CARRIED TO SUMMARY
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 17 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
BILL NO. 4 - PILING
NOTE: Tenderers are required to study the Model Preambles forTrades before pricing this Bill
Note
GENERAL NOTES TO TENDERERS
General notes, described in "BILL NO. 2 - EARTHWORKS", shall equallyapply to this Bill
Note
4.1 SUPPLEMENTARY PREAMBLES
INDEMNITY
The Contractor shall take full responsibility for piling work and shallguarantee that piling work will support the calculated loads laid down bythe Engineer without injurious settlement. The actual lengths of pilesshall be determined on site by the Contractor in consultation with theEngineer who will give all assistance possible. This does not in any wayrelieve the Contractor of his responsibility or obligation to provide thespecified guarantee
The Contractor shall indemnify the Employer against any injury to ordeath of any person and all loss or damage to all structures resultingfrom the failure of any pile. In the event of the failure of any pile theContractor shall make good such pile and all consequent damage at hisown expense
The Contractor shall insure in a policy, approved by the Engineer, againstrisks arising out of the responsibilities, guarantee and indemnitiesspecified. The Contractor shall pay all premiums in respect of thisinsurance policy
4.2 PILING, ETC.
4.2.1 Guarantee and Insurance
4.2.1.1 Provision of the specified piling guarantee and insurance Sum
4.2.2 Design, Supply and Install Piling Complete
4.2.2.1 Installation of 500kN Piles, average 7.5m deep, Including Establishment,Drilling, Grouting, etc.
m 545
4.2.2.2 Trim Back Piles to Expose Rebar, including 50mm Sawcut to preventspalling
m3 21
4.2.3 Testing
4.2.3.1 Transporting and establishment on site of necessary testing plant for theexecution of the work and removal thereof on completion
Sum 1
4.2.3.2 Integrity Testing of Piles m 545
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 18 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNTTOTAL CARRIED TO SUMMARY
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 19 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
BILL NO. 5 - CONCRETE, FORMWORK AND REINFORCEMENT
NOTE: Tenderers are required to study the Model Preambles forTrades before pricing this Bill
Note
GENERAL NOTES TO TENDERERS
General notes, described in "BILL NO. 2 - EARTHWORKS", shall equallyapply to this Bill
Note
5.1 SUPPLEMENTARY PREAMBLES
Cost of tests
The costs of making, storing and testing of concrete test cubes asrequired under clause 7 "Tests" of SABS 1200 G shall include the cost ofproviding cube moulds necessary for the purpose, for testing costs andfor submitting reports on the tests to the engineer. The testing shall beundertaken by an independent firm or institution nominated by thecontractor and to the approval of the engineer. (The cost of the testcubes are to be included in the concrete rates)
5.2 UNREINFORCED CONCRETE CAST AGAINST EXCAVATED SURFACES
5.2.1 10MPa/19mm concrete
5.2.1.1 Surface blinding under footings and bases m3 64
5.3 REINFORCED CONCRETE
5.3.1 30MPa/19mm concrete (350kg/m3 Cement Content)
5.3.1.1 Bases m3 481
5.3.1.2 Thrust Blocks m3 299
5.3.1.3 Raft Slabs m3 275
5.3.1.4 Ground beams / footings m3 157
5.3.1.5 Walls m3 301
5.3.1.6 Bund Walls m3 2
5.3.1.7 Plinths m3 18
5.3.1.8 Slabs, Including Beams m3 90
5.4 CONCRETE SUNDRIES
5.4.1 Finishing top surfaces of concrete smooth with a power float
5.4.1.1 Surface beds, slabs, etc m2 20
5.4.2 Finishing top surfaces of concrete smooth with a steel trowel
5.4.2.1 Tops of Surface beds, slabs m2 1 626
5.4.2.2 Tops of columns & plinths m2 20
Carried forward
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 20 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 21 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Brought forward
5.4.3 1:3 cement Screed
5.4.3.1 Screeds to Falls, Average 75mm thick m2 16
5.4.4 40 MPa non-shrink grout
5.4.4.1 Non shrink cementitious grout prostruct 531 or similar approved forbedding base plate including chamfered edges all round
m3 2
5.4.5 Asphalt Layer to Tank Base
5.4.5.1 50mm continuously graded asphalt layer to Tank including Prime Coat m2 236
5.5 SMOOTH FORMWORK (DEGREE OF ACCURACY 1)
5.5.1 Smooth formwork to sides
5.5.1.1 Bases m2 299
5.5.1.2 Thrust Blocks, including fitting around pipes, etc m2 1 257
5.5.1.3 Circular Groundbeams, exceeding 1m radius m2 136
5.5.1.4 Walls m2 2 807
5.5.1.5 Plinths m2 63
5.5.1.6 Circular Plinths m2 11
5.5.1.7 Edges, risers, ends and reveals not exceeding 300mm high or wide m 1 021
5.5.2 Smooth formwork to soffits
5.5.2.1 Slabs propped up exceeding 3,5m and not exceeding 5m high m2 404
5.5.2.2 Slabs propped up exceeding 5m and not exceeding 6,5m high m2 20
5.5.3 Boxing in smooth formwork to form
5.5.3.1 25 x 25mm chamfers to all exposed concrete edges m 1 117
5.5.3.2 60 x 100mm chamfers m 851
5.5.4 Smooth formwork to form
5.5.4.1 50 x 50 x 100mm Deep pockets No 739
5.6 MOVEMENT JOINTS ETC
5.6.1 Expansion joints with bitumen-impregnated softboard between verticalconcrete surfaces
5.6.1.1 10mm Joints not exceeding 300mm high or wide m 80
5.6.2 Saw cut joints
Carried forward
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 22 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 23 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Brought forward
5.6.2.1 50 x 3mm Saw cut joints in top of concrete, reamed out to 6 x 6mm m 101
5.7 CAST IN ITEMS
5.7.1 Hot Dipped Galvanised Mild Steel
5.7.1.1 100mm x 12mm thick Bearing plate with 20mm dia grout breather holesdrilled at 800mm centres, including 100 x 30 x 6mm fishtail lugs at500mm centres
m 426
5.7.1.2 45 x 45 x 5mm Angle including 100 x 30 x 3mm fishtail lugs at 500mmcentres
m 87
5.8 REINFORCEMENT (PROVISIONAL)
5.8.1 Mild and High tensile steel reinforcement to structural concrete work
5.8.1.1 8mm - 32mm Diameter bars t 194
5.8.2 Drill and Dowel with Prostruct 618
5.8.2.1 Y12, 200mm deep, rebar elsewhere No 220
5.8.2.2 Y16, 200mm deep, rebar elsewhere No 220
5.8.2.3 Y20, 200mm deep, rebar elsewhere No 220
5.8.3 Fabric reinforcement
5.8.3.1 Type 193 fabric reinforcement in concrete surface beds, slabs, etc m2 165
5.8.3.2 Type 395 fabric reinforcement in concrete surface beds, slabs, etc m2 928
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 24 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNTTOTAL CARRIED TO SUMMARY
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 25 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
BILL NO. 6 - PRECAST CONCRETE
NOTE: Tenderers are required to study the Model Preambles forTrades before pricing this Bill
Note
GENERAL NOTES TO TENDERERS
General notes, described in "BILL NO. 2 - EARTHWORKS", shall equallyapply to this Bill
Note
SUPPLEMENTARY PREAMBLES
Reinforced brick lintels
Lintels shall bear at least 160mm onto adjacent walling. Where suchbearing cannot be obtained due to the proximity of adjacent openingsthe lintel shall be continuous
Note
6.1 PRECAST CONCRETE
6.1.1 Precast concrete Lintels
6.1.1.1 110 x 70mm Lintels in lengths not exceeding 3m m 30
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 26 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNTTOTAL CARRIED TO SUMMARY
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 27 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
BILL NO. 7 - MASONRY
NOTE: Tenderers are required to study the Model Preambles forTrades before pricing this Bill
Note
SUPPLEMENTARY PREAMBLES
Sizes in descriptions
Where sizes in descriptions are given in brick units, "one brick" shallrepresent the length and "half brick" the width of a brick
Note
Face bricks
Bricks shall be ordered timeously to obtain uniformity in size and colour Note
GENERAL NOTES TO TENDERERS
General notes, described in "BILL NO. 2 - EARTHWORKS", shall equallyapply to this Bill
Note
7.1 BRICKWORK
SUPERSTRUCTURE
7.1.1 Brickwork of NFP bricks in class II mortar
7.1.1.1 One brick walls m2 399
7.1.2 Brickwork reinforcement
7.1.2.1 150mm Wide reinforcement built in horizontally m 1 171
7.2 FACE BRICKWORK
7.2.1 Extra over brickwork for facings (PC R6,000/1000 nett delivered to siteexcluding VAT) and pointing with recessed horizontal and vertical joints
7.2.1.1 Extra over brickwork for face brickwork m2 797
7.2.1.2 Extra over face brickwork for brick-on-edge header course lintel m 30
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 28 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNTTOTAL CARRIED TO SUMMARY
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 29 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
BILL NO. 8 - WATERPROOFING
NOTE: Tenderers are required to study the Model Preambles forTrades before pricing this Bill
Note
GENERAL NOTES TO TENDERERS
General notes, described in "BILL NO. 2 - EARTHWORKS", shall equallyapply to this Bill
Note
8.1 Waterproofing
8.1.1 Waterproofing of roofs, basements, etc shall be laid under a ten yearguarantee. Waterproofing to roofs shall be laid to even falls to outletsetc with necessary ridges, hips and valleys. Descriptions of sheet ormembrane waterproofing shall be deemed to include additional labourto turn-ups and turn-downs
8.2 DAMPPROOFING OF WALLS AND FLOORS
8.2.1 One layer of 375 micron "Consol Plastics Brikgrip DPC" embossed dampproof course
8.2.1.1 In walls m2 21
8.2.2 One layer of 250 micron "Consol Plastics Gunplas USB Green"waterproof sheeting sealed at laps with "Gunplas Pressure SensitiveTape"
8.2.2.1 Under surface beds m2 313
8.3 WATERPROOFING TO ROOFS, BASEMENTS, ETC
8.3.1 One layer Derbigum CG4, with 100mm side and 150mm end laps, sealedtogether and to primed surface by `torch - fusion`. Waterproofing to beinstalled by an approved Derbigum Contractor under a 10 year Derbigumguarantee.
8.3.1.1 On walls including softboard protection where filling required m2 20
8.3.2 Bagging and 2 Coats Brixeal
8.3.2.1 On walls. m2 20
8.4 JOINT SEALANTS ETC
8.4.1 Thioflex 600 two-part grey polysulphide sealing compound includingbacking cord, bond breaker, primer, etc
8.4.1.1 10 x 10mm In joints in floors m 80
8.4.1.2 6 x 6mm In Sawcut joints in floors m 101
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 30 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNTTOTAL CARRIED TO SUMMARY
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 31 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
BILL NO. 9 - ROOF COVERINGS
NOTE: Tenderers are required to study the Model Preambles forTrades before pricing this Bill
Note
GENERAL NOTES TO TENDERERS
General notes, described in "BILL NO. 2 - EARTHWORKS", shall equallyapply to this Bill
Note
SUPPLEMENTARY PREAMBLES
Note : All roof coverings installed are to comply with SABS Code ofPractice 0237 as applicable
Note
Guarantee:
The manufacturer shall comply with ISO9002 Quality ManagementSystem. Sheeting shall be laid in strict accordance with themanufacturer’s specifications by an approved contractor
Note
A written and approved fifteen (15) year guarantee of site-workmanshipand water tightness shall be issued after final inspection of roofs andcladding by the manufacturer
Note
Erection, handling and storage:
Every precaution shall be taken to prevent damage to roof sheets duringall stages of construction. Duck boards should be used when necessaryto protect the sheeting from damage. Sheeting which has becomedeformed or damaged in any way, shall be replaced
Note
The contractor shall exercise special care when handling long lengthsheeting, particularly in windy conditions. Should work be interrupted forany reason, all loose sheeting and incomplete sections must beadequately secured against possible movement by wind and gravity
Note
The contractor shall ensure that all materials used on site for cladding,etc., are transported, handled and stored in accordance with themanufacturer’s recommendations. Material damaged shall be rejectedand replaced with undamaged material at the contractor’s expense.Repair of damaged material will not generally be permitted. Rates are toinclude for preventing damage and protecting sheets through all stagesof construction
Note
Cleaning, etc:
All debris, swarf, etc., arising from the fixing of the cladding shall beremoved from the sheeting as the fixing progresses. In addition, off-cutsof insulation, surplus fasteners and sealants, mandrels from pop rivets,off-cuts of flashings and sheeting, surplus flashing, food packaging,cartons, bottles, cans, etc., shall not be left on the roof or in the gutters
Note
Care shall be taken to ensure that no such material enters, blocks orpartially impedes the flow of water into the outlets, down pipes, etc.
Note
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 32 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
9.1 0,8mm IBR profile Z275 spelter galvanised steel troughed sheeting with"Chromadek" (or equally approved) finish on one side, in single lengthsfixed to purlins or rails and 0,6mm galvanised steel accessories with"Chromadek" (or equally approved) finish on one side
9.1.1 Roof sheeting (Rate to include all ridge capping, cranking, bull noses,flashing, closers, polyclosers, etc)
m2 452
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 33 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
TOTAL CARRIED TO SUMMARY
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 34 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
BILL NO. 10 - CARPENTRY AND JOINERY
NOTE: Tenderers are required to study the Model Preambles forTrades before pricing this Bill
Note
GENERAL NOTES TO TENDERERS
General notes, described in "BILL NO. 2 - EARTHWORKS", shall equallyapply to this Bill
Note
10.1 Doors and frames
10.1.1 Solid core door size 813 x 2032mm No 4
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 35 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNTTOTAL CARRIED TO SUMMARY
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 36 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
BILL NO. 11 - IRONMONGERY
NOTE: Tenderers are required to study the Model Preambles forTrades before pricing this Bill
Note
GENERAL NOTES TO TENDERERS
General notes, described in "BILL NO. 2 - EARTHWORKS", shall equallyapply to this Bill
Note
11.1 Locks, deadbolts, hinges, etc
11.1.1 3 Lever lockset No 4
11.1.2 Dead bolt No 4
11.1.3 Door hinges No 20
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 37 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNTTOTAL CARRIED TO SUMMARY
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 38 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
BILL NO. 12 - STRUCTURAL STEELWORK
NOTE: Tenderers are required to study the Model Preambles forTrades before pricing this Bill
Note
GENERAL NOTES TO TENDERERS
General notes, described in "BILL NO. 2 - EARTHWORKS", shall equallyapply to this Bill
Note
12.1 HOT DIPPED GALVANISED MILD STEEL
12.1.1 Provide lump sum and rates per tonne for the supply, fabrication,delivery and erection of the structural steelwork listed below. Steelworkto be Grade S355 (unless otherwise noted) in accordance with SANS1200, SANS 1921 and SANS 2001. Rates to include for the preparation offabrication drawings for approval.
Note
12.1.2 The prices are to include for all normal fabrication labours associatedwith the type of member described in the Bill, e.g. includes for normalchamfering and notching of flanges on beam to beam and beam tocolumn connections. Weights of notches and holes etc, will not bededucted and weight of welding will not be added.
Note
12.2.1 Hot Dip Galvanised Walkways and Platforms Comprising:
12.2.1.1 UB 305 x 165 x 54kg/m t 15
12.2.1.2 UC 152 x 152mm x 23kg/m t 1
12.2.1.3 PFC 180 x 70 x 21.1kg/m t 12
12.2.1.4 PFC 100 x 50 x 10.1kg/m t 2
12.2.1.5 Angle Bracing 30 x 30 x 3mm x 1.36kgs/m t 0.2
12.2.1.6 Rectagrid RS30 x 3.0mm x 25.23kg/m2 t 1
12.2.1.7 Rectagrid RS40 x 4.5mm x 42.88kg/m2 t 4
12.2.1.8 Connections t 4
12.2.1.9 Bolts t 2
12.3.1 Hot Dip Galvanised Pipe Supports
12.3.1.1 Pipe Supports t 6
12.4.1 Hot Dip Galvanised mild steel ball type handrails and accessories asmanufactured and supplied by Andrew Mentis (Pty) Ltd or other equaland approved, erected in strict accordance with the manufacturer'sinstructions and specifications
12.4.1.1 42,9mm Diameter type (MT 90) stanchion 1180mm long, welded to 150x 60 x 10mm plate, bolted in position to steelwork
No 17
12.4.1.2 34,1mm Diameter x 2,5mm wall thickness handrailing cut to lengths m 15
Carried forward
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 39 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 40 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Brought forward
12.4.1.3 Closures m 5
12.4.1.4 Bends, etc m 22
12.5.1 Crawl Beam, including supply, installation and certification
12.5.1.1 UB 305 x 165 x 54kg/m t 2
12.5.1.2 10T Electric Crawl Trolley - to meet all SANS and OHS Act requirements.Refer to specification.
No 1
12.5.1.3 10T Electric Hoist - to meet all SANS and OSHAct requirements. Refer tospecification.
No 1
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 41 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNTTOTAL CARRIED TO SUMMARY
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 42 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
BILL NO. 13 - METALWORK
NOTE: Tenderers are required to study the Model Preambles forTrades before pricing this Bill
Note
GENERAL NOTES TO TENDERERS
General notes, described in "BILL NO. 2 - EARTHWORKS", shall equallyapply to this Bill
Note
13.1.1 Louvres
13.1.1.1 5450 x 700mm Louvres. 2 UL type Louvre, Fully galvanised construction,Bird and Insect Proof
No 4
13.1.1.2 5450 x 1200mm Louvres. 2 UL type Louvre, Fully galvanisedconstruction, Bird and Insect Proof
No 4
13.1.2 Purpose Made Doors
13.1.2.1 3000 wide x 5000mm high Door. Centre split, side hung (double hung)corrosion and fire resistant.
No 1
13.1.2.2 2500 wide x 5000mm high Door. Centre split, side hung (double hung)corrosion and fire resistant.
No 1
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 43 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNTTOTAL CARRIED TO SUMMARY
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 44 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
BILL NO. 14 - STORAGE TANKS
14.1 TANKS
14.1.1 Diesel Tank
14.1.1.1 Design, Supply and Install Diesel Storage Tank, 1.0m3 each No 3
14.1.2 Foam Concentrate Storage Tanks
14.1.2.1 Design, Supply and Install Foam Storage Tanks, 15.45m3 each No 2
14.1.3 Water Storage Tanks
14.1.3.1 Design, Supply and Install Welded Tanks, 850m3 each No 2
14.1.4 Temporary Water Storage Tanks
14.1.4.1 Design, Supply and Install Galvanised Steel Panel Tanks, volume 600m3Each, Including all Level Indicators, Catladders, etc.
No 3
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 45 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNTTOTAL CARRIED TO SUMMARY
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 46 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
BILL NO. 15 - FIRE RETICULATION
15.1 PUMPS
15.1.1 Supply and Install the following Pumps in accordance with the relevanttechnical specifications and data sheets issued For Construction.
15.1.1.1 Fire Pump; diesel drive - 13000 /min - 12 bars No 315.1.1.2 Jockey Pump - 50 /min - 12 bars No 115.1.1.3 Water Driven Foam Induction Pump - 15000 l/min No 115.1.1.4 Foam concentrate circulation Pump - 200 /min - 3 bars No 1
15.1.2 Supply only in accordance with the relevant technical specifications anddata sheets.
15.1.2.1 Water Driven Foam Induction Pump - 15000 l/min No 1
15.2 VALVES
Tenderer to provide make and valve specification with Tender forAdjudication
Note
15.2.1 Supply and Install Butterfly Valves, Including All Gaskets and Bolts wherenecessary (Amri Isoria or Similar) Design: SANS 1849, EN593, SIO10631 or FM or UL approved Full lug Wafer type body PN 16 Possible downstream dismantling and end of line service Spherical machined disc ensures perfect upstream/ downstream sealing: zero leakage visible to the naked eye Face--to--face dimensions in accordance with: ISO 5752 series 20, EN 558--1 series 20. All valves, DN150 or larger shall be gear operated Materials: Body :- Spheroïdal graphite cast iron Shaft :- Stainless steel Disc :- Stainless steel Liner :- EPDM
15.2.1.1 80NB No 2015.2.1.2 100NB No 3415.2.1.3 150NB No 9015.2.1.4 200NB No 1315.2.1.5 250NB No 615.2.1.6 300NB No 115.2.1.7 350NB No 4
15.2.2 Supply and Install Gate Valves, Including All Gaskets and Bolts wherenecessary (Rapid Drop or Similar) Gate Valve OS&Y UL listed or FM Approved PN16 Resilient wedge gatevalve ductile iron body and wedge, conforms to AWWA C509
15.2.2.1 50NB No 215.2.2.2 150NB No 1015.2.2.3 250NB No 615.2.2.4 300NB No 615.2.2.5 350NB No 715.2.2.6 400NB No 315.2.2.7 600NB No 2
Carried forward
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 47 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 48 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Brought forward
15.2.3 Supply and Install Ball Valves, Including All Gaskets and Bolts wherenecessary Stainless steel 2 piece full bore ball valve flanged to ANSI 150#
15.2.3.1 40NB No 215.2.3.2 50NB No 2715.2.3.3 65NB No 615.2.3.4 100NB No 3
15.2.4 Supply and Install Check Valves, Including All Gaskets and Bolts wherenecessary Wafer type double door cast iron check valve PN16 with stainless steeldoor and nitrile seat
15.2.4.1 50NB No 215.2.4.2 65NB No 115.2.4.3 80NB No 815.2.4.4 100NB No 1615.2.4.5 150NB No 115.2.4.6 350NB No 4
15.2.5 Supply and Install UL Listed Inline Repairable Electrically ControlledOn/Off Deluge Valves, Including All Gaskets and Bolts where necessary.(Bermad Model FP-400E-3D or Similar)
15.2.5.1 350NB No 1
15.2.6 Supply and Install Deluge Valves, Including All Gaskets and Bolts wherenecessary. (Inbal or Similar)
15.2.6.1 80NB No 915.2.6.2 100NB No 1115.2.6.3 150NB No 3315.2.6.4 200NB No 1315.2.6.5 250NB No 415.2.6.6 300NB No 1
15.2.7 Supply and Install Flow Indicators, Including All Gaskets and Bolts wherenecessary
15.2.7.1 50NB No 315.2.7.2 65NB No 215.2.7.3 80NB No 115.2.7.4 100NB No 415.2.7.5 150NB No 6
15.2.8 Supply and Install , Globe Valves Including All Gaskets and Bolts wherenecessary
15.2.8.1 50NB No 1
15.2.9 Supply and Install Level Control Valves with Bi-Level Vertical Float,Including All Gaskets and Bolts where necessary (Bermad Model FP-450-66 or Similar)
15.2.9.1 150NB No 2
Carried forward
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 49 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 50 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Brought forward
15.2.10 Supply and Install Flow Measure Valve, Including All Gaskets and Boltswhere necessary
15.2.10.1 250NB No 1
15.2.11 Supply and Install , Globe Valves Including All Gaskets and Bolts wherenecessary
15.2.11.1 50NB No 1
15.2.12 Supply and Install Level Control Valves with Bi-Level Vertical Float,Including All Gaskets and Bolts where necessary (Bermad Model FP-450-66 or Similar)
15.2.12.1 150NB No 2
15.2.13 Supply and Install Flow Measure Valve, Including All Gaskets and Boltswhere necessary
15.2.13.1 250NB No 1
15.3 FIRE SPRINKLER SYSTEM
15.3.1 Supply and Install the following Sprinkler heads, Including stub pipe, andstubbing into piping and welding according to specification
15.3.1.1 Water Deluge Sprinkler head - (K Value = 25) No 60215.3.1.2 Water Deluge Sprinkler head - (K Value = 45) No 9015.3.1.3 Tanker High level Foam Deluge Sprinkler head - (K Value = 40) No 13615.3.1.4 Tanker low Level Foam Deluge Sprinkler head - (K Value = 20) No 58
15.4 BUND FOAM POURERS
15.4.1 Supply and Install the following Bund Foam Pourers
15.4.1.1 Manual Pourer - 1800 l/min No 415.4.1.2 Manual Pourer - 1200 l/min No 1515.4.1.3 Manual Pourer - 600 l/min No 75
15.5 TOP POURERS
15.5.1 Supply and Install the following Top Foam Pourers
15.5.1.1 Manual Pourer - Angus TPS50 or similar No 915.5.1.2 Manual Pourer - Angus TPS80 or similar No 1515.5.1.3 Manual Pourer - Angus TPS100 or similar No 3
15.6 MONITORS
15.6.1 Supply and Install the following Monitors
15.6.1.1 Oscillating Flange (AKRON 3531 oscillating flange or similar) No 1215.6.1.2 Monitor (AKRON 3528 Monitor or similar) No 1215.6.1.3 Foam Nozzle (AKRON 3626 Foam Tube or similar) No 12
Carried forward
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 51 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 52 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Brought forward
15.7 FIRE HYDRANTS
15.7.1 Supply and Install
15.7.1.1 65mm Hydrant including Fibreglass Outlet box, 2No 30m hoses, couplingand nozzle complete
No 78
15.7.1.2 Fibreglass Outlet box, 2No 30m hoses, coupling and nozzle complete No 15
15.8 CARBON STEEL PIPING
All Above Ground Carbon Steel piping shall be SANS 62 -medium up to150NB, SANS 719 - 4.5mm WT up to 250NB, SANS 719 6.0mm WT above300NB, Fabricated to SABS 1476
All Carbon Steel Fittings (Bends, Tees, Caps, Reducers etc) shall be ASTMA234 WPB, Standard Weight
All Flanges shall be Carbon Steel according to SANS 1123, Class 1600Table 3, All Blind Flanges shall be Class 1600 Table 8
All the Rates shall include for hot-dip galvanizing in accordance with thepiping specification.
All Carbon Steel Piping shall be fabricated and installed according toBS4677, and all welding shall be based on Full Argon Welding up to100NB, Argon Route and Stick welding filler and Capping above 100NB,10% X-Rays will be required by an independent Non Destructive Testingand Inspection Party
15.8.1 Supply and Install Piping Including Welding according to Specifications
15.8.1.1 25NB m 215.8.1.2 50NB m 62115.8.1.3 65NB m 3715.8.1.4 80NB m 95315.8.1.5 100NB m 1 27415.8.1.6 125NB m 2715.8.1.7 150NB m 69515.8.1.8 200NB m 27915.8.1.9 250NB m 141
15.8.1.10 300NB m 7415.8.1.11 350NB m 7315.8.1.12 400NB m 1815.8.1.13 600NB m 24
15.8.2 Supply and Install Seamless Piping Including Welding according toSpecifications
15.8.2.1 100NB m 3715.8.2.2 150NB m 3715.8.2.3 200NB m 215.8.2.4 250NB m 1615.8.2.5 350NB m 26
Carried forward
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 53 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 54 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Brought forward
15.8.2.6 400NB m 215.8.2.7 500NB m 14
15.8.3 Supply and Install 45deg Elbow (LR) Including Welding according toSpecifications
15.8.3.1 50NB No 3115.8.3.2 80NB No 4015.8.3.3 100NB No 2515.8.3.4 150NB No 915.8.3.5 200NB No 315.8.3.6 350NB No 315.8.3.7 600NB No 3
15.8.4 Supply and Install 90deg Elbow (LR) Including Welding according toSpecifications
15.8.4.1 50NB No 14215.8.4.2 65NB No 2215.8.4.3 80NB No 29415.8.4.4 100NB No 39815.8.4.5 125NB No 215.8.4.6 150NB No 21115.8.4.7 200NB No 6915.8.4.8 250NB No 5815.8.4.9 300NB No 37
15.8.4.10 350NB No 3315.8.4.11 600NB No 3
15.8.5 Supply and Install Concentric Reducers, Including Welding according toSpecifications
15.8.5.1 50NB x 32NB No 615.8.5.2 65NB x 50NB No 3115.8.5.3 80NB x 50NB No 4915.8.5.4 100NB x 80NB No 13515.8.5.5 125NB x 100NB No 4815.8.5.6 150NB x 80NB No 8415.8.5.7 200NB x 150NB No 8315.8.5.8 250NB x 200NB No 2815.8.5.9 300NB x 250NB No 2
15.8.5.10 350NB x 200NB No 415.8.5.11 350NB x 250NB No 2815.8.5.12 400NB x 250NB No 215.8.5.13 400NB x 300NB No 2115.8.5.14 500NB x 400NB No 2
15.8.6 Supply and Install Eccentric Reducers, Including Welding according toSpecifications
15.8.6.1 400NB x 250NB No 4
15.8.7 Supply and Install Equal Tees, Including Welding according toSpecifications
15.8.7.1 50NB No 615.8.7.2 65NB No 3
Carried forward
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 55 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 56 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Brought forward
15.8.7.3 80NB No 615.8.7.4 100NB No 2915.8.7.5 150NB No 2615.8.7.6 200NB No 815.8.7.7 250NB No 815.8.7.8 300NB No 915.8.7.9 350NB No 5
15.8.7.10 600NB No 3
15.8.8 Supply and Install UnEqual Tees, Including Welding according toSpecifications
15.8.8.1 80NB x 50NB No 215.8.8.2 100NB x 65NB No 715.8.8.3 100NB x 80NB No 1615.8.8.4 150NB x 100NB No 13615.8.8.5 200NB x 150NB No 1415.8.8.6 250NB x 100NB No 2115.8.8.7 250NB x 150NB No 215.8.8.8 300NB x 150NB No 4215.8.8.9 350NB x 200NB No 2
15.8.8.10 500NB x 350NB No 715.8.8.11 600NB x 400NB No 4
15.8.9 Supply and Install Caps, Including Welding according to Specifications
15.8.9.1 100NB No 715.8.9.2 150NB No 33
15.8.10 Supply and Install Backing Rings
15.8.10.1 75NB No 3315.8.10.2 80NB No 515.8.10.3 110NB No 5515.8.10.4 140NB No 8215.8.10.5 200NB No 6815.8.10.6 250NB No 2815.8.10.7 355NB No 2615.8.10.8 400NB No 21
15.8.11 Supply and Install Flanges, Including Welding according to Specifications
15.8.11.1 25NB No 315.8.11.2 32NB No 415.8.11.3 50NB No 30615.8.11.4 65NB No 5115.8.11.5 80NB No 50315.8.11.6 100NB No 64115.8.11.7 125NB No 5915.8.11.8 150NB No 58315.8.11.9 200NB No 206
15.8.11.10 250NB No 11715.8.11.11 300NB No 6215.8.11.12 350NB No 5515.8.11.13 400NB No 3515.8.11.14 600NB No 14
Carried forward
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 57 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 58 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Brought forward
15.8.12 Supply and Install Weldneck Flanges, Including Welding according toSpecifications
15.8.12.1 100NB No 4015.8.12.2 150NB No 4015.8.12.3 200NB No 615.8.12.4 250NB No 1615.8.12.5 300NB No 515.8.12.6 350NB No 6415.8.12.7 500NB No 13
15.8.13 Supply and Install Blind Flanges, including all gaskets, Bolts, nuts &washers
15.8.13.1 50NB No 315.8.13.2 200NB No 315.8.13.3 250NB No 915.8.13.4 300NB No 1415.8.13.5 500NB No 215.8.13.6 600NB No 3
15.8.14 Supply and Install Rubber Bellows, including all gaskets, Bolts, nuts &washers
15.8.14.1 25NB No 315.8.14.2 50NB No 715.8.14.3 65NB No 315.8.14.4 100NB No 315.8.14.5 200NB No 415.8.14.6 250NB No 415.8.14.7 350NB No 3
15.8.15 Extra Over for Intemescent Paint as per specification
15.8.15.1 25NB m 115.8.15.2 50NB m 31115.8.15.3 65NB m 1915.8.15.4 80NB m 47715.8.15.5 100NB m 63715.8.15.6 125NB m 1415.8.15.7 150NB m 34815.8.15.8 200NB m 14015.8.15.9 250NB m 71
15.8.15.10 300NB m 3715.8.15.11 350NB m 3715.8.15.12 400NB m 915.8.15.13 600NB m 12
15.8.16 Extra Over for corrosion protection by protective wrapping in accordancewith SANS 10129
15.8.16.1 25NB m 2215.8.16.2 50NB m 2215.8.16.3 65NB m 2215.8.16.4 80NB m 2215.8.16.5 100NB m 2215.8.16.6 125NB m 22
Carried forward
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 59 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 60 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Brought forward
15.8.16.7 150NB m 2215.8.16.8 200NB m 2215.8.16.9 250NB m 22
15.8.16.10 300NB m 2215.8.16.11 350NB m 2215.8.16.12 400NB m 2215.8.16.13 450NB m 2215.8.16.14 500NB m 2215.8.16.15 600NB m 22
15.9 Painting of all galvanised piping
Rates shall include for Painting according to SANS 12944 with Colourscompliant to SANS10140, SANS1091 and the TPL Standard. The TPLStandard shall take preference. All painting shall be completed inWorkshops and shall be prepared according to SANS 064, Code forPreparation of Steel Surfaces for Painting
15.9.1 Paint Piping according to Specifications including supply of materials(Piping measured above), preparation of material and any touch-uprequired on site.
15.9.1.1 25NB m 215.9.1.2 50NB m 62115.9.1.3 65NB m 3715.9.1.4 80NB m 95315.9.1.5 100NB m 1 27415.9.1.6 125NB m 2715.9.1.7 150NB m 69515.9.1.8 200NB m 27915.9.1.9 250NB m 141
15.9.1.10 300NB m 7415.9.1.11 350NB m 7315.9.1.12 400NB m 1815.9.1.13 600NB m 24
15.9.2 Paint Seamless Piping according to Specifications including supply ofmaterials (Piping measured above), preparation of material and anytouch-up required on site.
15.9.2.1 100NB m 3715.9.2.2 150NB m 3715.9.2.3 200NB m 215.9.2.4 250NB m 1615.9.2.5 350NB m 2615.9.2.6 400NB m 215.9.2.7 500NB m 14
15.9.3 Paint 45deg Elbow (LR) according to Specifications including supply ofmaterials (Piping measured above), preparation of material and anytouch-up required on site.
15.9.3.1 50NB No 3115.9.3.2 80NB No 4015.9.3.3 100NB No 2515.9.3.4 150NB No 9
Carried forward
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 61 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 62 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Brought forward
15.9.3.5 200NB No 315.9.3.6 350NB No 315.9.3.7 600NB No 3
15.9.4 Paint 90deg Elbow (LR) according to Specifications including supply ofmaterials (Piping measured above), preparation of material and anytouch-up required on site.
15.9.4.1 50NB No 14215.9.4.2 65NB No 2215.9.4.3 80NB No 29415.9.4.4 100NB No 39815.9.4.5 125NB No 215.9.4.6 150NB No 21115.9.4.7 200NB No 6915.9.4.8 250NB No 5815.9.4.9 300NB No 37
15.9.4.10 350NB No 3315.9.4.11 600NB No 3
15.9.5 Paint Concentric Reducers according to Specifications including supply ofmaterials (Piping measured above), preparation of material and anytouch-up required on site.
15.9.5.1 50NB x 32NB No 615.9.5.2 65NB x 50NB No 3115.9.5.3 80NB x 50NB No 4915.9.5.4 100NB x 80NB No 13515.9.5.5 125NB x 100NB No 4815.9.5.6 150NB x 80NB No 8415.9.5.7 200NB x 150NB No 8315.9.5.8 250NB x 200NB No 2815.9.5.9 300NB x 250NB No 2
15.9.5.10 350NB x 200NB No 415.9.5.11 350NB x 250NB No 2815.9.5.12 400NB x 250NB No 215.9.5.13 400NB x 300NB No 2115.9.5.14 500NB x 400NB No 2
15.9.6 Paint Eccentric Reducers according to Specifications including supply ofmaterials (Piping measured above), preparation of material and anytouch-up required on site.
15.9.6.1 400NB x 250NB No 4
15.9.7 Paint Equal Tees according to Specifications including supply of materials(Piping measured above), preparation of material and any touch-uprequired on site.
15.9.7.1 50NB No 615.9.7.2 65NB No 315.9.7.3 80NB No 615.9.7.4 100NB No 2915.9.7.5 150NB No 2615.9.7.6 200NB No 815.9.7.7 250NB No 815.9.7.8 300NB No 9
Carried forward
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 63 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 64 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Brought forward
15.9.7.9 350NB No 515.9.7.10 600NB No 3
15.9.8 Paint UnEqual Tees according to Specifications including supply ofmaterials (Piping measured above), preparation of material and anytouch-up required on site.
15.9.8.1 80NB x 50NB No 215.9.8.2 100NB x 65NB No 715.9.8.3 100NB x 80NB No 1615.9.8.4 150NB x 100NB No 13615.9.8.5 200NB x 150NB No 1415.9.8.6 250NB x 100NB No 2115.9.8.7 250NB x 150NB No 215.9.8.8 300NB x 150NB No 4215.9.8.9 350NB x 200NB No 2
15.9.8.10 500NB x 350NB No 715.9.8.11 600NB x 400NB No 4
15.9.9 Paint Caps according to Specifications including supply of materials(Piping measured above), preparation of material and any touch-uprequired on site.
15.9.9.1 100NB No 715.9.9.2 150NB No 33
15.9.10 Paint Backing Rings according to Specifications including supply ofmaterials (Piping measured above), preparation of material and anytouch-up required on site.
15.9.10.1 75NB No 3315.9.10.2 80NB No 515.9.10.3 110NB No 5515.9.10.4 140NB No 8215.9.10.5 200NB No 6815.9.10.6 250NB No 2815.9.10.7 355NB No 2615.9.10.8 400NB No 21
Carried forward
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 65 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 66 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Brought forward
15.10 STAINLESS STEEL PIPING
All Stainless Steel piping shall be ASTM A312, 316 grade, Schedule 20,fabricated in accordance with SABS 1476
All Stainless Steel Fittings (Bends, Tees, Caps, Reducers etc) shall beASTM/ASME SA/A WP-W (Welded Fittings), 316 grade, Schedule 20
All Flanges shall be Stainless Steel SANS 1123, Class 1600 Table 3, Grade316
All the Rates shall include for Pickling and Passivation of all stainless steelpiping in accordance with ASTM A967/A967M-13. Mild SteelContamination shall not be permitted, and the contractor shall replaceany pipe section which shows evidence of mild steel contamination
All Stainless Steel Piping shall be fabricated and installed according toBS4677, and all welding shall be based on Full Argon Welding, 10% X-Rays will be required by an independent Non Destructive Testing andInspection Party
15.10.1 Supply and Install Piping Including Welding according to Specifications
15.10.1.1 50NB m 62315.10.1.2 65NB m 13415.10.1.3 80NB m 125415.10.1.4 100NB m 110015.10.1.5 125NB m 1615.10.1.6 150NB m 30515.10.1.7 200NB m 1315.10.1.8 250NB m 615.10.1.9 350NB m 2
15.10.2 Supply and Install 45deg Bends (LR) Including Welding according toSpecifications
15.10.2.1 50NB No 8315.10.2.2 80NB No 136
15.10.3 Supply and Install 90deg Bends (LR) Including Welding according toSpecifications
15.10.3.1 50NB No 11415.10.3.2 65NB No 2615.10.3.3 80NB No 21215.10.3.4 100NB No 17915.10.3.5 150NB No 2215.10.3.6 200NB No 515.10.3.7 250NB No 2
15.10.4 Supply and Install Concentric Reducers, Including Welding according toSpecifications
15.10.4.1 65NB x 50NB No 9
Carried forward
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 67 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 68 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Brought forward
15.10.4.2 80NB x 50NB No 2915.10.4.3 100NB x 80NB No 4415.10.4.4 125NB x 100NB No 2115.10.4.5 150NB x 100NB No 315.10.4.6 200NB x 150NB No 315.10.4.7 250NB x 200NB No 315.10.4.8 350NB x 250NB No 2
15.10.5 Supply and Install Equal Tees, Including Welding according toSpecifications
15.10.5.1 50NB No 1315.10.5.2 65NB No 715.10.5.3 80NB No 1615.10.5.4 100NB No 615.10.5.5 150NB No 315.10.5.6 200NB No 2
15.10.6 Supply and Install UnEqual Tees, Including Welding according toSpecifications
15.10.6.1 150NB x 100NB No 315.10.6.2 250NB x 150NB No 3
15.10.7 Supply and Install Caps, Including Welding according to Specifications
15.10.7.1 50NB No 1415.10.7.2 80NB No 11
15.10.8 Supply and Install Flanges, Including Welding according to Specifications
15.10.8.1 50NB No 42115.10.8.2 65NB No 7515.10.8.3 80NB No 68215.10.8.4 100NB No 44015.10.8.5 125NB No 1915.10.8.6 150NB No 10515.10.8.7 200NB No 1015.10.8.8 250NB No 215.10.8.9 350NB No 2
15.11 Painting of stainless steel piping
Rates shall include for Painting according to SANS 12944 with Colourscompliant to SANS10140, SANS1091 and the TPL Standard. The TPLStandard shall take preference. All painting shall be completed inWorkshops and shall be prepared according to SANS 064, Code forPreparation of Steel Surfaces for Painting
15.11.1 Paint Piping according to Specifications including supply of materials(Piping measured above), preparation of material and any touch-uprequired on site.
15.11.1.1 50NB m 623
Carried forward
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 69 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 70 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Brought forward
15.11.1.2 65NB m 13415.11.1.3 80NB m 125415.11.1.4 100NB m 110015.11.1.5 125NB m 1615.11.1.6 150NB m 30515.11.1.7 200NB m 1315.11.1.8 250NB m 615.11.1.9 350NB m 2
15.11.2 Paint 45deg Bends (LR) according to Specifications including supply ofmaterials (Piping measured above), preparation of material and anytouch-up required on site.
15.11.2.1 50NB No 8315.11.2.2 80NB No 136
15.11.3 Paint 90deg Bends (LR) according to Specifications including supply ofmaterials (Piping measured above), preparation of material and anytouch-up required on site.
15.11.3.1 50NB No 11415.11.3.2 65NB No 2615.11.3.3 80NB No 21215.11.3.4 100NB No 17915.11.3.5 150NB No 2215.11.3.6 200NB No 515.11.3.7 250NB No 2
15.11.4 Paint Concentric Reducers according to Specifications including supply ofmaterials (Piping measured above), preparation of material and anytouch-up required on site.
15.11.4.1 65NB x 50NB No 915.11.4.2 80NB x 50NB No 2915.11.4.3 100NB x 80NB No 4415.11.4.4 125NB x 100NB No 2115.11.4.5 150NB x 100NB No 315.11.4.6 200NB x 150NB No 315.11.4.7 250NB x 200NB No 315.11.4.8 350NB x 250NB No 2
15.11.5 Paint Equal Tees according to Specifications including supply of materials(Piping measured above), preparation of material and any touch-uprequired on site.
15.11.5.1 50NB No 1315.11.5.2 65NB No 715.11.5.3 80NB No 1615.11.5.4 100NB No 615.11.5.5 150NB No 315.11.5.6 200NB No 2
15.11.6 Paint UnEqual Tees according to Specifications including supply ofmaterials (Piping measured above), preparation of material and anytouch-up required on site.
15.11.6.1 150NB x 100NB No 315.11.6.2 250NB x 150NB No 3
Carried forward
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 71 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 72 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Brought forward
15.11.7 Paint Caps according to Specifications including supply of materials(Piping measured above), preparation of material and any touch-uprequired on site.
15.11.7.1 50NB No 1415.11.7.2 80NB No 11
15.11.8 Paint Flanges according to Specifications including supply of materials(Piping measured above), preparation of material and any touch-uprequired on site.
15.11.8.1 50NB No 42115.11.8.2 65NB No 7515.11.8.3 80NB No 68215.11.8.4 100NB No 44015.11.8.5 125NB No 1915.11.8.6 150NB No 10515.11.8.7 200NB No 1015.11.8.8 250NB No 215.11.8.9 350NB No 2
15.12 Winterizing of all piping
All Rate for Piping up to and including 50NB shall include for winterisingto protect it from Freezing, with a temperature of 4°C to be maintainedat all times. The Contractor shall familiarise himself with the location ofthe Site and winter temperatures and allow for this in his rates.Insulation is to be designed and installed in accordance with SANS 9288and SANS 612. The piping Shall be subject to Ambient conditions, andcladding shall be non-flammable but need not provide protection againstheat or Flame Exposure
15.12.1 Insulate Piping according to Specifications including supply of materials(Piping measured above), preparation of material and any touch-uprequired on site.
15.12.1.1 25NB m 215.12.1.2 50NB m 1 244
15.12.3 Insulate 45deg Elbow (LR) according to Specifications including supplyof materials (Piping measured above), preparation of material and anytouch-up required on site.
15.12.3.1 50NB No 114
15.12.4 Insulate 90deg Elbow (LR) according to Specifications including supplyof materials (Piping measured above), preparation of material and anytouch-up required on site.
15.12.4.1 50NB No 256
15.12.5 Insulate Concentric Reducers according to Specifications including supplyof materials (Piping measured above), preparation of material and anytouch-up required on site.
Carried forward
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 73 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 74 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Brought forward
15.12.5.1 50NB x 32NB No 615.12.5.2 65NB x 50NB No 4015.12.5.3 80NB x 50NB No 78
15.12.6 Insulate Equal Tees according to Specifications including supply ofmaterials (Piping measured above), preparation of material and anytouch-up required on site.
15.12.6.1 50NB No 19
15.12.7 Insulate UnEqual Tees according to Specifications including supply ofmaterials (Piping measured above), preparation of material and anytouch-up required on site.
15.12.7.1 80NB x 50NB No 2
15.13 HDPE PIPING
Note: The Tenderer shall price for the supply of materials and specify thelengths he will be supplying, separate items have been scheduled forbutt-welding and electro fusion. Due to the nature of the site, thenumber of pipes in the trenches and the space constraints, acombination of jointing by butt-welding and electro fusion is envisaged.
Note
Note: The Price for Fittings shall include for the welding/jointing methodappropriate taking into account the number of welds/joints per fitting.
Note
Note: Prior to backfilling sections of pipe, a pressure test carried out forthat section of pipe shall be submitted to the Engineer for BackfillingRelease. No payment for backfilling shall be made until this is submitted.
Note
Note: The contractor shall take note of the specification contained in thistender
Note
15.13.1 Supply, handle, lay, bed PE 100 STR11, PN 16 pipes, Jointing Measuredelsewhere
15.13.1.1 75NB m 66315.13.1.2 90NB m 5415.13.1.3 110NB m 177915.13.1.4 140NB m 134915.13.1.5 200NB m 199115.13.1.6 280NB m 54215.13.1.7 355NB m 107015.13.1.8 400NB m 889
15.13.2 Buttwelding of straight Pipes
15.13.2.1 75NB No 5815.13.2.2 90NB No 715.13.2.3 110NB No 15015.13.2.4 140NB No 11515.13.2.5 200NB No 16815.13.2.6 280NB No 47
Carried forward
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 75 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 76 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Brought forward
15.13.2.7 355NB No 9115.13.2.8 400NB No 76
15.13.3 Electrofusion Couplers, Including electrofusion
15.13.3.1 75NB No 5815.13.3.2 90NB No 715.13.3.3 110NB No 15015.13.3.4 140NB No 11515.13.3.5 200NB No 16815.13.3.6 280NB No 4715.13.3.7 355NB No 9115.13.3.8 400NB No 76
15.13.4 Long Spigot 45deg Bends, Including Buttwelding
15.13.4.1 110NB No 1715.13.4.2 140NB No 815.13.4.3 200NB No 815.13.4.4 280NB No 515.13.4.5 355NB No 315.13.4.6 400NB No 2
15.13.5 Long Spigot 45deg Bends, Including Electrofusion Couplers and fusion
15.13.5.1 110NB No 1715.13.5.2 140NB No 815.13.5.3 200NB No 815.13.5.4 280NB No 515.13.5.5 355NB No 315.13.5.6 400NB No 2
15.13.6 Conventional Buttweld 90deg Bends, Including Buttwelding
15.13.6.1 75NB No 3115.13.6.2 90NB No 515.13.6.3 110NB No 8815.13.6.4 140NB No 7515.13.6.5 200NB No 5915.13.6.6 280NB No 2215.13.6.7 355NB No 3715.13.6.8 400NB No 32
15.13.7 Long Spigot 90deg Bends, Including Electrofusion Couplers and fusion
15.13.7.1 75NB No 3115.13.7.2 90NB No 515.13.7.3 110NB No 8815.13.7.4 140NB No 7515.13.7.5 200NB No 5915.13.7.6 280NB No 2215.13.7.7 355NB No 3715.13.7.8 400NB No 32
15.13.8 Conventional Equal Tees, Including Buttwelding
Carried forward
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 77 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 78 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Brought forward
15.13.8.1 140NB No 315.13.8.2 200NB No 2015.13.8.3 280NB No 715.13.8.4 355NB No 1015.13.8.5 400NB No 8
15.13.9 Long Spigot Equal Tees, Including Electrofusion Couplers and fusion
15.13.9.1 140NB No 315.13.9.2 200NB No 2015.13.9.3 280NB No 715.13.9.4 355NB No 1015.13.9.5 400NB No 8
15.13.10 Conventional Unequal Tees, Including Buttwelding
15.13.10.1 200NB x 140NB No 3
15.13.11 Long Spigot Unequal Tees including Electrofusion Couplers and fusion
15.13.11.1 200NB x 140NB (200-160 Unequal Tee/160-125 Reducer) No 3
15.13.12 Conventional Concentric Reducers, Including Buttwelding
15.13.12.1 200NB x 140NB No 515.13.12.2 280NB x 200NB No 1415.13.12.3 355NB x 200NB No 915.13.12.4 400NB x 355NB No 3
15.13.13 Long Spigot Concentric Reducers, Including Electrofusion Couplers andfusion
15.13.13.1 200NB x 140NB No 515.13.13.2 280NB x 200NB No 1415.13.13.3 355NB x 200NB No 915.13.13.4 400NB x 355NB No 3
15.13.14 Long Spigot Flange Adapter (Stub End), Including Buttwelding
15.13.14.1 75NB No 3315.13.14.2 110NB No 5515.13.14.3 140NB No 8215.13.14.4 200NB No 6815.13.14.5 280NB No 2815.13.14.6 355NB No 2615.13.14.7 400NB No 21
15.13.15 Long Spigot Flange Adapter (Stub End), Including Electrofusion Couplersand fusion
15.13.15.1 75NB No 3315.13.15.2 110NB No 5515.13.15.3 140NB No 8215.13.15.4 200NB No 6815.13.15.5 280NB No 2815.13.15.6 355NB No 2615.13.15.7 400NB No 21
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 79 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNTTOTAL CARRIED TO SUMMARY
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 80 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
BILL NO. 16 - ELECTRICAL, CONTROL AND INSTRUMENTATION
Note: The Contractor is referred to the Electrical, Control andInstrumentation Specifications for detailed description and specifications
Note
Note: The Contractor to include for all design required for the controland electrical system as indicated in the C3 Works Information.
Note
16.1 FIRE CONTROL SYSTEM
16.1.1 Main Fire Panel: Design, Supply and Install
16.1.1.1 Stainless steel panels to house:the Fire Control System, a main mimic, a scenario mimic, UPS batteriesand control system, all output relays and all field terminations (allmeasured separately)
Sum 1
16.1.1.2 Stainless steel panels to house:a scenario mimic, I/O connection between main panel and scenariopanel.
ea 3
16.1.1.3 Main Mimic: including switches, indicators, mimic background ea 1
16.1.1.4 Scenario Mimic: including switches, indicators, mimic background ea 4
16.1.1.5 UPS system for supply to the Fire Control System:To be housed in panels of item 16.1.1.1.
Sum 1
16.1.1.6 Fire Control system Control System Complete(Det-Tronics EQP or Similar. FM 3010 and NFPA 72 approved)
Sum 1
16.1.2 Field Instrumentation: Design, Supply and Install
16.1.2.1 IR Flame Detector including mounting accessories ea 98
16.1.2.2 IR Fire Detector Stand ea 98
16.1.2.3 Point Heat Detector ea 19
16.1.2.4 Point Heat Detector Stand ea 19
16.1.2.5 Fire alarm beacon ea 4
16.1.2.6 Fire alarm siren ea 4
16.1.2.7 Break glass units ea 11
16.1.2.8 Break glass unit mounting ea 11
16.1.3 Field Cabling: Supply and Install, including field routing.Note: These quantities are based on a Det-Tronics system utilising a LONnetwork cable comminication system. If the Tenderer utilises any othersystem they shall be responsible for quantifying the requirements forcabling, cable racking, junction boxes, terminations etcetera andcompleting the price in accordance with this quantification.
Note
16.1.3.1 1Triad 1.5mm2 Dekabond Armoured m 6 11616.1.3.2 1Triad 1.5mm2 Dekabond Armoured termination ea 37916.1.3.3 1 Pr 1.0mm2 SWA LH m 369
Carried forward
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 81 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 82 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Brought forward
16.1.3.4 1 Pr 1.0mm2 SWA LH termination ea 2516.1.3.5 8 Pr 1.0mm2 SWA LH m 4416.1.3.6 8 Pr 1.0mm2 SWA LH termination ea 916.1.3.7 16 Pr 1.0mm2 SWA LH m 3 96516.1.3.8 16 Pr 1.0mm2 SWA LH termination ea 3316.1.3.9 LON Communication cable m 2 200
16.1.3.10 LON Communication cable termination ea 11016.1.3.11 Field Junction boxes - equipped ea 1416.1.3.12 300mm Cable Racking & clamps fitted to steel/slab as per TPL
specificationsm 440
16.1.3.13 300mm Cable Racking - bends as per TPL specifications ea 2216.1.3.14 300mm Cable Racking - T-Piece as per TPL specifications ea 316.1.3.15 150mm Cable Racking & clamps fitted to steel/slab as per TPL
specificationsm 1 540
16.1.3.16 150mm Cable Racking - bends as per TPL specifications ea 3316.1.3.17 150mm Cable Racking - T-Piece as per TPL specifications ea 516.1.3.18 Galvanised Angle Iron complete with bends and supports
40mmx40mmx3mmm 550
16.1.4 Control System Software Engineering
16.1.4.1 Fire control system software development sum 116.1.4.2 Fire control system factory acceptance testing sum 116.1.4.3 Fire control system commissioning sum 1
16.2 ELECTRICAL SYSTEM
16.2.1 Panels: Design, Supply, Manufacture and Install
16.2.1.1 Jockey Fire Pump DOL starter panel (7.5kW) fitted in existing sparebucket of main MCC panel.
ea 1
16.2.1.2 Foam Re-circ Pump DOL starter panel (4kW) fitted in existing sparebucket of main MCC panel.
ea 1
16.2.1.3 Fire pump house lighting & small power DB feeder, fitted in existingspare bucket of main MCC panel.
ea 1
16.2.1.4 Fire pump house fire system DB feeder, fitted in existing spare bucket ofmain MCC panel.
ea 1
16.2.2 Cabling & Racking: Supply and install, including field routing
16.2.2.1 4C 10mm2 PVC/SWA/PVC LH m 16516.2.2.2 4C 10mm2 PVC/SWA/PVC LH - termination ea 516.2.2.3 4C 6mm2 PVC/SWA/PVC LH m 16516.2.2.4 4C 6mm2 PVC/SWA/PVC LH - termination ea 516.2.2.5 4C 4mm2 PVC/SWA/PVC LH m 66016.2.2.6 4C 4mm2 PVC/SWA/PVC LH - termination ea 916.2.2.7 4C 1.5mm2 PVC/SWA/PVC LH m 1 54016.2.2.8 4C 1.5mm2 PVC/SWA/PVC LH - termination ea 3616.2.2.9 7C 1.5mm2 PVC/SWA/PVC LH m 495
16.2.2.10 7C 1.5mm2 PVC/SWA/PVC LH - termination ea 716.2.2.11 200mm Cable Racking & clamps fitted to steel/slab as per TPL
specificationsm 110
16.2.2.12 200mm Cable Racking - bends as per TPL specifications ea 5
16.2.3 Lighting & Small Power: Design, Supply and Install
16.2.3.1 Fire pump house lighting and small power DB ea 1
Carried forward
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 83 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 84 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Brought forward
16.2.3.2 Fire pump house fire system DB ea 116.2.3.3 Luminaires and fittings - fire pump house (SSO) ea 716.2.3.4 Luminaires and fittings - blast walls bulkheads ea 1116.2.3.5 Galvanised conduit & mounting fittings m 2216.2.3.6 3 way CCG boxes ea 10
16.2.4 Bonding, Earthing and Lightning Protection
16.2.4.1 Bond the complete installation as per SANS 10142-1 ea 1
16.2.4.2 Supply and install of earth strapping between pipes and earth points,including connection to earth
m 100
16.2.4.3 Supply and install terminations for earth straps to pipe flanges ea 9016.2.4.4 Supply and install 2.4m SABS approved earth rods (SANS 1063) ea 10
16.2.4.5 Measure earth resistivity, design, supply, test and certify, and installearth mat. To be done by a specialist subcontractor
ea 2
16.2.5 Miscellaneous
16.2.5.1 Earthing COC ea 116.2.5.2 Electrical installation COC ea 1
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 85 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNTTOTAL CARRIED TO SUMMARY
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 86 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
BILL NO. 17 - PAINTWORK - Floor
17.1.1 Epoxy paint for floor: Supply and Apply, including any preparation ofsurface required.
17.1.1.1 Epoxy paint floor - Prepare and prime solvent free primer, apply Hi-buildepoxy floor coating - nominal thickness 500 micron, and finish with a non-slip sealer coat.
m2 313
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 87 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNTTOTAL CARRIED TO SUMMARY
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 88 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
BILL NO. 18 - PROVISIONAL SUMS
NOTE: Tenderers are required to study the Model Preambles forTrades before pricing this Bill
Note
18.1 PROVISIONAL SUMS
18.1.1 Allow a Provisional Sum for the Relocation of Services
18.1.1.1 Allow a Provisional Sum for the Relocation of Existing Services Sum 1 3 000 000.00
18.1.1.2 Profit %
18.1.1.3 General attendance Sum
18.2 BUDGETARY ALLOWANCES
The following budgetary allowances are for work to be executed by theContractor
Note
Note: Budgetary allowances listed below are for work to be executed bythe Main Contractor and will be measured and evaluated in terms ofrates submitted against similar items in these bills and in terms of theconditions of contract
Note
Note: These items are to be taken into account in the pricing ofPreliminaries and General as they will not attract separate Preliminariesof their own
Note
18.2.1 Builders Work
18.2.1.1 Allow Provisional Sum for Builders Work Sum 1 200 000
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 89 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNTTOTAL CARRIED TO SUMMARY
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 90 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
BILL NO. 19 - COMMISSIONING
COMMISSIONING
19.1 Commissioning Services required of the contractor in the C3 WorksInformation
19.1.1 Sum for the completion of "pre", "cold" and "Hot" Commissioningservices required of the Contractor including all material, equipment,documentation and other resources and deliverables.
Sum 1
19.1.2 Final Pressure/Hydro testing of all piping systems and X-rays of 10% ofsteel pipe buttwelds.
Sum 1
19.2 Commissioning
19.2.1 Supply all spares and consumables required for commissioning Sum 1
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 91 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNTTOTAL CARRIED TO SUMMARY
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 92 of 93 C1: AGREEMENT AND CONTRACT DATA
Transnet PipelinesTender number: PYP/W1/6/21/1464Description of the Works: Tarlton Fire System Upgrade
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
CONTRACT SUM SUMMARY
BILL NO. 1 - PRELIMINARY AND GENERAL ITEMSBILL NO. 2 - EARTHWORKSBILL NO. 3 - LATERAL SUPPORTBILL NO. 4 - PILINGBILL NO. 5 - CONCRETE, FORMWORK AND REINFORCEMENTBILL NO. 6 - PRECAST CONCRETEBILL NO. 7 - MASONRYBILL NO. 8 - WATERPROOFINGBILL NO. 9 - ROOF COVERINGSBILL NO. 10 - CARPENTRY AND JOINERYBILL NO. 11 - IRONMONGERYBILL NO. 12 - STRUCTURAL STEELWORKBILL NO. 13 - METALWORKBILL NO. 14 - STORAGE TANKSBILL NO. 15 - FIRE RETICULATIONBILL NO. 16 - ELECTRICAL, CONTROL AND INSTRUMENTATIONBILL NO. 17 - PAINTWORK - FloorBILL NO. 18 - PROVISIONAL SUMSBILL NO. 19 - COMMISSIONING
SUB TOTAL (EXCL VAT) -
Allow a Budgetary Allowance calculated as 10% of the total Constructionvalue for Health and Safety. This will be paid based on proven cost andmay be deducted in part or in whole should it not be used
SUB TOTAL (EXCL VAT) -
VALUE ADDED TAX 14% -
TENDER AMOUNT (INCL VAT) -
NEC3 CONTRACTC2.2: BILL OF QUANTITIES Page 93 of 93 C1: AGREEMENT AND CONTRACT DATA
Recommended