1.10 USCALCULATING OEE WORKSHEETOverall Equipment EffectivenessLine / Cell :OEEProcess :Machine :0.0%Date :OEE DATAShift Length (Minutes) :aNumber of Shift(s) :bShort Breaks per Shift (Minutes) :Each (Minutes) :Nb :Total :0cMeal Break per Shift (Minutes) :Each (Minutes) :Nb :Total :0dDown Time (Minutes) :eIdeal Rate :(Pieces/Hour) :(Pieces/Minute) :0fTotal Pieces Produced per Shift :gRejected Pieces per Shift :hOEE VARIABLES CALCULATIONPlanned Production Time (Minutes) :0i=(a-(c+d))*bOperating Time (Minutes) :0j=i-(e*b)Good Pieces per Shift :0k=g-hOEE FACTORS CALCULATIONAvailability0.0%90.0%l=j/iPerformance0.0%95.0%m=g/(f*j)Quality0.0%99.9%n=k/gOverall OEE0.0%85.4%o=l*m*n

&L&9File : &FCopyright 2004-2008 - Philippe Magnier&R&9Form Release : &A

1.10 US

Calculated FactorWorld ClassRate