St. Croix Crossing Project

Project Development/Construction update:

Todd Clarkowski, P.E.St. Croix Crossing Project Coordinator

St. Croix Crossing Project Area

Bayport

The New St. Croix Crossing

The New St. Croix Crossing

The New St. Croix Crossing

The New St. Croix Crossing – night time

TH95 under Bridge

Roadway View

Roadway View – night time

The New St. Croix Crossing

http://youtu.be/wH058zyvHfU

Animations

Lift Bridge

New St. Croix Crossing

2014 River Bridge Construction

River Bridge Overview

2014 River Bridge Construction

2014/2015 River Bridge Construction

Column Blades and Crossbeam

Crossbeam Construction

Crossbeam Construction

Crossbeam Construction

Crossbeam Construction

Crossbeam Construction

2014 River Bridge Construction

2014/2015 River Bridge Construction

2014/2015 River Bridge Construction

2014/2015 River Bridge Construction

2014/2015 WI Construction

Minnesota Approach Bridge Piers–2014

Column

Footing

H-Piles

Future Groundline

Segments

Minnesota Approach Bridge Piers–2014

As of February 2015, 22 of 23 total land piers are at full height

Minnesota Approach Bridge Segments

approx. 40 ft.

10 ft.

- Approximately 350 pre-cast segments make up the Minnesota approach bridge superstructure

- Average weight: 90 tons- Average length: 8-1/2 feet

On-Site Casting Yard - OPH

On-Site Casting Yard - OPH

On-Site Casting Yard - OPH

Segment Placement - MN Approach Bridge

River Bridge Cross Section – Two Precast Box Segments

100 ft.

18 ft.

Segments

Grey Cloud Island Casting Yard

100’ x 600’ Building

Grey Cloud Island Casting Yard

River bridge segments- 5 casting beds- 656 segments- 18 ft. deep- 10 ft. long - 50 ft. wide- Weighs 180 tons- Barged on Mississippi and St. Croix rivers to project

site- Majority of segments placed in 2015

Segment Placement - River Bridge

Construction Sequence

Construction Sequence

Construction Sequence

Construction Sequence

Construction Sequence

2015 Construction

New River Bridge

Wisconsin roadway approach

Mitigation Items

NW ramp in Minnesota

Minnesota approach bridge

Schedule

− Mn Roadway – majority completed by 2015

− WI Roadway – completed by 2016

− New River Bridge – completed by 2016

− Mitigation items -implemented “before”, “during” or “after” construction

Project Information

Project Office1862 Greeley Street S., Stillwater

Project Website – Webcams and Weekly Update www.mndot.gov/stcroixcrossing/

Hotline1-855-GO-CROIX

E-mailstcroixcrossing.dot@state.mn.us

Facebook www.facebook.com/saintcroixcrossingmndot

Twitter @stcroixcrossing

Questions?

Recommended