North Eastern RegionUrban Development Program
13th National Steering Committee Meeting28th April 2014
Summary of Project Progress•All contracts awarded valued at Rs156 cr•Cumulative expenditure of Rs 98.9 cr (63 % )• Mizoram has finished its projects, Gangtok near completion,•Tranche-I to be completed for 2014-15
Tranche-I205 Cr
•26 out of 32 total contracts/LoAs valued at Rs 341 cr•Cumulative expenditure Rs 65.47 cr or 19% of the Tranche-II•Target for 2014-15,: 60% of Tranche-II
Tranche-II463 Cr
•Tentative dates: Loan negotiations by September 2014, Loanagreement by March 2015•State wise list of projects decided. However, so far 5 DPRs
out of 13 projects received. ( Meghalaya , Mizoram, Sikkim)
Tranche-III1038 Cr
Key issues identified in last NSC heldon 20.11.2014
Improve Fund Flows
Organize CapacityBuilding Workshop
Expedite Reforms
•States are expediting transfer of funds toSIPMIUs.•Full Budget allotted ( 50cr) FY 13-14 was utilized•Additional funds to States for Loan Component& Imprest could not be released .
• Recommendations given by IDCs, butimplementation lacking. States have to fulfillcovenants.
• Extension of IDCs only upon commitmentsby States
•One day workshop on Urbanization was heldin February 2014 at Guwahati with 118participants.•Two days Workshop on Finance was alsoorganized at Guwahati•Three workshops are planned during thisyear at Shillong/Guwahati
State wise expenditure vs targets2013-14
Agartala Aizawl Gangtok Kohima ShillongTarget 36.1 24.3 18.1 31.7 8.63Actual 24.4 22.1 15.5 19.3 4.16
05
10152025303540
RsCr
ores
Percent 68% 91% 86% 61% 48%
Project Progress Tranche-I
36%
100%
56%
35%
7%
85%
100%95%
55%
40%
Agartala Aizawl Gangtok Kohima Shilong
Progress during 2013-14April '13 March '14
Key issues in Tr-1• Kohima needs to speed up:
– Water Treatment Plant: Target commissioning by 15-3-14. Delayedagain (Target: Aug 14) . WS: Only 7 out of 18 tanks completed. Work 12m behind schedule.: (Target Aug 14)
– SWM: Site development and building work still in progress. Erection ofcompost plant and construction of landfill cell much behind schedule.(Target: Sept 14)
• Shillong SWM:– Landfill work to pick up speed after revised contract. (Target : Aug 14)
• Gangtok WS:– Household connections to be given before project is considered
commissioned.
Project Progress Tranche-IICity Total
PackagesPackages
to beawarded
%progress
Physical progress
Agartala 8 1 25% 5 GWTP & 6 OH tanks underconstruction
Aizawl 10 0 20% 5 packages completed, work on WSNetwork and sewerage network tostart.
Gangtok 9 4 10% Physical work started in only 1package
Kohima 2 1 05% Physical work started
Shillong 3 0 20% All primary and secondary collectionvehicles received. Supply ofhousehold bins to start
Total 32 6 19% Overall progress-Physical work inmost states in initial stages
Key issues in Tranche-II
Agartala needs to expedite physical works◦ Work awarded even 9-10 months before have just
started e.g. WS distribution network awarded in Dec.2012 completed only 20%
Gangtok progress is slow◦ Physical work has just started on WS distribution and
just started in SLFS package. Contracted 7 months ago.◦ 3 packages of SWM still to be contracted
Kohima progress needs speeding up:◦ WS project awarded 8 months ago, only 3.5%
completed.
Reforms• 74th CAA-Implement decentralizationInstitutional Reforms
• Reforms for efficient service delivery of Water Supply &SewerageService Delivery
• Issue of Government Order for NRW reduction program andvolumetric metering
Improving operationalefficiency
• Issue regulations for enforcing household to connect to sewerage system andprohibiting waste discharge & Solid Waste Management
Regulatorycompliance
• ULBs to migrate to Accrual AccountingImproving ULB’sFinancials
• Introduce self assessment & unit area based property tax system &85% Property Tax realization
Property TaxImprovements
• Implement SW collection charges to cover 100% of SWM O&M costs & WaterTariff to collect 100% WS&S O&M costs
Rationalization ofuser charges
Reforms under JnNURMS.No.
ULB LevelReforms
S.No.
State Level Reforms S.No.
Optional Reforms
1 Implementation of 74thCAA 8 E-Governance set up 14 Introduction of Property Title Certification System in ULBs
2Integration of CityPlanning & DeliveryFunctions
9 Shift to Accrual based Double Entry Accounting 15 Revision of Building Bye laws – streamlining the Approval Process
3 Reform in Rent Control 10 Property Tax (85% coverage & 90 % CollectionEfficiency) 16 Revision of Building Bye laws – To make rain water harvesting
mandatory
4 Stamp DutyRationalization to 5% 11 100% Cost Recovery (Water Supply &SWM) 17 Earmarking 25% developed land in all housing projects for EWS/LIG
5 Repeal of ULCRA 12 Internal Earmarking of Funds for Services to Urban Poor 18 Simplification of Legal and Procedural framework for conversion ofagricultural land for non-agricultural purposes
6 Enactment of CommunityParticipation Law 13 Provision of Basic Services to Urban Poor 19 Introduction of computerized process of Registration of land and
Property
7 Enactment of PublicDisclosure Law 20 Byelaws on Reuse of Recycled Water
21 Administrative Reforms
22 Structural Reforms
23 Encouraging Public Private Participation
JnNURM Reforms Achievement
0
10
20
30
40
50
60
70
80
90
100
Tripura Mizoram Sikkim Nagaland Meghalaya
JnNURM Level Reforms %
ULB Level
State Level
Optional
Status of Reforms under NERUDP
Variation proposals from States
• Seven Cost variation proposals from 4 statesamounting to Rs 40 cr
• Variations due to modifications in scope of workin Tranche-I/Tranche-II proposals earlier approved& awardedRecommendation:– Only variations essential to complete ongoing projects
may be approved as no surplus funds in scheme– MoUD can absorb up to 10% cost variation under
contingencies. Balance by the States.
Variation proposals to be consideredS.No. Proposal Variance
(Rs Cr% of contractvalue
Amount tobe borne byMoUD (10%)(Rs cr)
Amount tobe borneby State(Rs lakhs)
1. Kohima WS –Feeder lines fromcommon storage tank 1.65 22.6% 0.73 0.92
2. Kohima SWM- Retaining Wallsand storm water drainage 4.25 10.86% 3.91 0.39
3. Shillong SWM- Additional worksfor Garage cum workshop 0.35 25% 0.13 0.22
4. Aizawl Sewerage- Revisedalignment of approach road 0.30 20.7% 0.15 0.16
Total 6.55 13.3% 4.92 1.63
Preparations for Tranche-III• Tranche-III scoped at Rs 1038 cr with 13 projects valued at Rs
778 cr
• Only 5 DPRs from Meghalaya , Mizoram, Sikkim. Need toexpedite.
• ADB’s approval for Tranche-III is dependent on progress ofTranche-II,
• Target: Loan negotiations by September 2014 & loanagreement by March 2015.
Aizawl Tr-I: Armed-veng Reservoir & Office
Before After
Thank You