Presentation Outline

Requests from members of the committee

Feedback on questions

Saint-Jacques escarpment and green spaces

Work update

Saint-Jacques overpass

Closure of avenue Greene

Opening of route 136 est

Dismantling A-720 est

Questions

3

Feedback on Questions

1. Efficiency of the noise barriers

2. Safety of the noise barrier of rue Addington

3. Noise samples on the overpass of Upper-Lachine

4. Absorbent materials on retaining walls of autoroute 15

5. Grass cutting along autoroute 15

6. Noise barrier north of the future route 136 (Westmount)

7. Alternating meetings of NDG/Westmount

10.Extension of the temporary noise barriers of Addington and Prud’homme

11.Availability of the documents of the ministère de l’Environnement

City of Montreal

11.Crossing guard in the NDG area

12.Snow removal on rue Addington with the noise barriers in place

4

Height of structures

Glen / De Courcelle

BEFORE AFTER

East: 34,6 m 32,5 m

West: 42,3 m 35,3 m

Hallowell

BEFORE AFTER

East: 40,5 m 36,8 m

West: 43 m 43,5 m

Greene

BEFORE AFTER

East: 38,4 m 38,8 m

West: 41 m 41,5 m

Saint-Rémi

BEFORE AFTER

East : 36 m 30 m

West : 43 m 30 m

5

Saint-Jacques escarpment and

green spaces

6

Saint-Jacques escarpment

and green spaces

Saint-Jacques

escarpment

Ecoterritory

7

Saint-Jacques escarpment

and green spaces

Saint-Jacques escarpment and

green spaces at the completion of

the project

8 Saint-Jacques escarpment

and green spaces

Saint-Jacques escarpment –

City of Montreal

9

Green strip at the foot of the

escarpment – Ministry

Saint-Jacques escarpment

and green spaces

10

Landscaping along the A-20 –

Ministry

(Work carried out by KPH Turcot)

Saint-Jacques escarpment

and green spaces

11

Landscaping along the A-20

– Ministry (Work carried out by KPH Turcot)

St-Jacques escarpment –

City of Montreal

Green strip at the foot of

the escarpment – Ministry

Saint-Jacques escarpment

and green spaces

Highway

corridor

Railway

corridor

12

Work Update

13

Saint-Jacques Overpass

Temporary noise

barrier :

transparent

section put in

place

Construction of

temporary

retaining walls for

the dismantling of

two abutments

14

Closure of avenue Greene

From October 25 to November 14

15

Work in Progress

Construction of the ramp A-15 sud to R-136 est

Construction of the two first lanes of R-136 est

Construction of two temporary configurations

16

Hindrance to come

Opening of route 136 est

17

Dismantling of A-720 est

Distance between the new lanes and the existing A-720 est : varies

between 0,8 m and 2,8 m depending of the area

18 Dismantling A-720 est

Work Sequence

19

Pont d’étagement

Avenue Greene

Dismantling A-720 est

Hindrance on the Local Network

20

Construction of Route 136

21

Communications

Neighbourhood Committee NDG-Westmount

January 30, 2016 – Westmount City Hall (4333, rue Sherbrooke O.)

Neighbourhood Committee Sud-Ouest

November 29, 2016

Project Website: www.turcot.gouv.qc.ca

Twitter @MTQ_Turcot

Monthly electronic bulletin (Subscrition on the Turcot website)

Dedicated Phone line: 514 873-1372

Turcot email: turcot.commentaires@transports.gouv.qc.ca

22

turcot.gouv.qc.ca

Recommended