MVRPC TRAC Project OverviewBrian O. Martin Executive Director
October 13, 2015
11
22
MVRPCTRAC PRIORITIES
2. US-35 Improvements from Shakertown Road to Xenia Bypass
1. US-35 Widening from Livingston Avenue to I-675
PROJECTS TRAC REQUESTUS-35 Widening from Livingston Avenue to I-675 (MOT-35)
$29.52MConstruction
US-35 Improvements from Shakertown Road to Xenia Bypass (GRE-35)
$6M Right of Way$26M
ConstructionTOTAL $61,520,000
MVRPC TRAC Projects
Video
Miami Valley Region: What has changed Since 2014?
• MVRPC SIB Loan Repayment Policy Adopted (April 2014)– Up to $775,000 of annual MVRPC STP (7% of annual STP)– $400,000 max per project– $15M minimum construction cost– Construction Only– Requires MVRPC Board Approval
Miami Valley Region: What has changed Since 2014?
• Collaboration among local jurisdictions– Greene US 35
• Beavercreek, Beavercreek Township, Xenia, Greene County, ODOT D8
• Inclusive design process Business, Government, and Others
• $800,000 local investment for Right of Way
• Tier 2 Right of Way for Factory/Orchard; Tier 1 Construction for Valley/Trebein
• Right of Way donation from private partner
– MOT US 35
• Dayton, Riverside, Montgomery County, ODOT D7
• Shovel Ready Project
• Letters of Support – Businesses, Chamber, WPAFB
Total project cost: $38.04M
TRAC request: Tier 1 fundingNew TRAC amount: $29.52M Construction
Construction: SFY 2012 – SFY 2019
US-35: Livingston Avenue to I-675
Presentation by:Ben Wiltheiss, ODOT District 7 Planner
Total project cost: $125.74M
TRAC request: Tier 2 Right of Way for Factory/Orchard; Tier 1 Construction for Valley/Trebein
New TRAC amount: $6M Right of Way & $26M Construction
Begin Construction in: SFY 2018
US-35 Improvements from Shakertown Road to Xenia Bypass
Presentation by:
Keith Smith, Environmental Engineer District 8
PROJECTS TRAC REQUEST
US-35 Widening from Livingston Avenue to I-675 (MOT-35)
$29.52MConstruction
US-35 Improvements from Shakertown Road to Xenia Bypass (GRE-35)
$6M Right of Way & $26M Construction
TOTAL $61,520,000
MVRPC TRAC Projects
Recommended