PROJECT FACT SHEET
Local Projects in Egypt
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 1
1- Water Projects
Project # 1
Project Name Water Supply in Arish City – North Sinai Governorate
Project Location Arish City – North Sinai Governorate
Client NOPWASD
Contractor Arab Contractors “Osman Ahmed Osman”
Year 2010
Project Description The project includes the following tasks:
Prepare the hydraulic analysis using WaterCAD software for water
distribution network in Arish city for years 2010, 2030 and year
2050
Prepare the detail drawings of water distribution networks (plans
and profiles, thrust blocks, road crossings and valve chamber
details)
Prepare the technical specifications and bill of quantities
Prepare the electrical and mechanical details of water site, ground
reservoirs in New South Massed pumping station. Design of two
storage reservoirs each 10000 m3
Prepare the electrical and mechanical details of water site, ground
reservoirs in New Safa pumping station. Design of two storage
reservoirs each 20000 m3
Prepare the electrical and mechanical details of water site, ground
reservoirs in old South Massed pumping station. Design ofone
storage reservoir with 5000 m3 capacity
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Project # 2
Project Name Water Treatment Plant in Shatoura village – Tahta Markaz - Sohag
Governorate – capacity 1200 liter/second
Project Location Shatoura village – Tahta Markaz - Sohag Governorate
Client NOPWASD
Contractor Al Abd Company
Year 2008
Project Description The project includes the following tasks:
Prepare the hydraulic calculation and sizing of treatment units
Prepare the layout and hydraulic profile of the plant
Prepare the electrical, mechanical , structural and architectural
design and detail drawings of the following buildings: (intakes –
raw water pumping station – rapid mixing tank – calriflocculators –
rapid sand filters – ground reservoirs – high lift stations –
generators – transformers – chlorination building – chemical
building and other building in the plant
Prepare the structural calculation sheet
Prepare the pipe yard
Prepare the technical specifications of electromechanical and civil
works
Prepare the dewatering design and calculation sheets
Prepare the sheet pile design and calculation sheet
Solve problems at site
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Project # 3
Project Name Water Distribution Network in Shatoura village – Tahta Markaz - Sohag
Governorate
Project Location Shatoura village – Tahta Markaz - Sohag Governorate
Client NOPWASD
Contractor Mokhtar Ibrahim Company
Year 2008
Project Description The project includes the following tasks:
Prepare the hydraulic analysis using WaterCAD software for water
distribution network in Tahta Markaz
Prepare the detail drawings of water distribution networks (plans
and profiles, thrust blocks, road crossings and valve chamber
details) – Pipe diameter ranges from 1200mm to200mm with total
length of about 100km.
Prepare the technical specifications and bill of quantities
Prepare the design of 5 elevated storage tanks with capacities 1000,
2000 and 3000 m3
Prepare the dewatering design and calculation sheets
Prepare the sheet pile design and calculation sheet
Solve problems at site
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Project # 4
Project Name Water Distribution Network for 15 villages in Shatoura village – Tahta
Markaz - Sohag Governorate
Project Location Shatoura village – Tahta Markaz - Sohag Governorate
Client NOPWASD
Contractor Mokhtar Ibrahim Company
Year 2008
Project Description The project covers the following villages; Nag Mansour, Al Swama Gharb, El
Shiekh Zain El Din, Benga, Bani Harb, Nag Hamouda, Al Haredat, Nag
Hamad, El Shiekh Masoud, Arab Negwag and Al Kim Al Asfar.
The length of pipes about 150 km with diameters ranges from 100 to 400 mm
The project includes the following tasks:
Survey works
Prepare the hydraulic analysis using WaterCAD software for water
distribution network in Tahta Markaz
Prepare the detail drawings of water distribution networks (plans
and profiles, thrust blocks, road crossings and valve chamber
details) – Pipe diameter ranges from 1200mm to200mm with total
length of about 100km.
Prepare the technical specifications and bill of quantities
Prepare the dewatering design and calculation sheets
Prepare the sheet pile design and calculation sheet
Solve problems at site
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Project # 5
Project Name Water Treatment Plant in Bani Ahmed – Minia Governorate –
capacity 1200 liter/second
Project Location Bani Ahmed Minia Governorate
Client NOPWASD
Contractor Al Handasah & Tarkebat Al Mechanikiya Company – Sami Zakhary
Year 2008
Project Description The project includes the following tasks:
Prepare the hydraulic calculation and sizing of treatment
units
Prepare the layout and hydraulic profile of the plant
Prepare the electrical, mechanical , structural and
architectural design and detail drawings of the following
buildings: (intakes – raw water pumping station – rapid
mixing tank – calriflocculators – rapid sand filters –
ground reservoirs – high lift stations – generators –
transformers – chlorination building – chemical building
and other building in the plant
Prepare the structural calculation sheet
Prepare the pipe yard
Prepare the technical specifications of electromechanical
and civil works
Prepare the dewatering design and calculation sheets
Prepare the sheet pile design and calculation sheet
Solve problems at site
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Project # 6
Project Name Expansion of Al Bostan Water Treatment Plant – Damietta
Governorate – capacity 600 liter/second
Project Location Al Bostan Damietta Governorate
Client NOPWASD
Contractor Arab Contractors “Osman Ahmed Osman”
Year 2009
Project Description The project includes the following tasks:
Prepare the hydraulic calculation and sizing of treatment
units
Prepare the layout and hydraulic profile of the plant
Prepare the electrical and mechanical design and detail
drawings of the following buildings: (intakes – raw water
pumping station – rapid mixing tank – calriflocculators –
rapid sand filters – ground reservoirs – high lift stations –
generators – transformers – chlorination building –
chemical building and other building in the plant
Prepare the pipe yard
Prepare the technical specifications of electromechanical
works
Solve problems at site
Project # 7
Project Name Rehabilitation of Al Bostan Water Treatment Plant 2400 liter/sec
(14 filters and two sedimentation tanks)
Project Location Al Bostan Damietta Governorate
Client NOPWASD
Contractor Arab Contractors “Osman Ahmed Osman”
Year 2010
Project Description The project includes the following tasks:
Assessment and evaluation of existing structures (14
filters and two sedimentation tanks. The existing
structures have many cracks and rust of steel bars
Prepare the recommendations for rehabilitation
Prepare the core tests for existing structure
Prepare the structural drawings of rehabilitation works
Prepare the drawings of mechanical and electrical works
Prepare the specification of structural, architectural works
Prepare the specification of electrical and mechanical
works
Prepare bill of quantities
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 1
Project # 8
Project Name Rehabilitation of Kafr Soliman Water Treatment Plant 120000 m3/d
Project Location Kafr Soliman -Damietta Governorate
Client NOPWASD
Contractor Arab Contractors “Osman Ahmed Osman”
Year 2009
Project Description The project includes the following tasks:
Assessment and evaluation of existing structures. The
existing structures have many cracks and rust of steel bars
Prepare the core tests for existing structure
Prepare the documents of removal of existing buildings
because these buildings in very bad conditions
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Project # 9
Project Name Abo Diab Water Treatment Plant (2160 m3/d) – Qena Governorate
Water Pipeline 300mm diameter and 7 km length
Project Location Qena Governorate
Client NOPWASD
Contractor Mokhtar Ibrahim Company
Year 2009
Project Description The project includes the following tasks:
Prepare the hydraulic calculation sheets for water
treatment plant 25 liter/sec
Prepare the hydraulic design and calculation sheet of
water transmission pipeline with diameter 300mm and 7
km length
Prepare the structural , mechanical and electrical detail
drawings for water treatment plant
Prepare the detail drawings for water transmission frce
main (plan and profile)
Prepare the technical specifications
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Project # 10
Project Name Review the Master Plan Works in the Holding Company of Water
and Wastewater
Project Location Holding Company of Water and Wastewater
Client HCWW
Year 2007
Project Description Professor Dr. Mohamed Shabaan Negm (President of Senior) work as
a member in the committee for reviewing the master plans documents
submitted from different consultants for whole governorates. The
following documents were reviewed:
Present and future population studies
Present and future water and wastewater flows
Planning of water/wastewater networks
Hydraulic analysis of water/wastewater networks
Master Plan works for water and wastewater
High priority projects
Investment plans
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Project # 11
Project Name Water Distribution Network for 13 villages in Bani Ahmed – Minai
Governorate
Project Location Bani Ahmed - Minia Governorate
Client NOPWASD
Contractor Al Bad Company
Year 2009
Project Description The project covers the following villages; Bani Ahmed, Tala, Dair Attia,
Demsha we Hashem, Ezbet Al Hakim, Reeda, Al Hwslia, Tahnash, Saft Al
Sharkya, Bihdal, Damsheer, Edmo and Maquossa
The length of pipes about 50 km with diameters ranges from 200 to 800 mm
The project includes the following tasks:
Prepare the hydraulic analysis using WaterCAD software for water
distribution network
Prepare the detail drawings of water distribution networks (plans
and profiles, thrust blocks, road crossings and valve chamber
details)
Prepare the detail drawings of crossing of 800mm pipe under
railway and Ibrahimia canal
Prepare the technical specifications and bill of quantities
Prepare the dewatering design and calculation sheets
Prepare the sheet pile design and calculation sheet
Solve problems at site
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Project # 12
Project Name Water Treatment Plant in Matai – Minia Governorate – capacity 1200
liter/second
Project Location Matai Minia Governorate
Client NOPWASD
Contractor Al Handasah & Tarkebat Al Mechanikiya Company – Sami Zakhary
Year 2008
Project Description The project includes the following tasks:
Prepare the hydraulic calculation and sizing of treatment
units
Prepare the layout and hydraulic profile of the plant
Prepare the electrical, mechanical , structural and
architectural design and detail drawings of the following
buildings: (intakes – raw water pumping station – rapid
mixing tank – calriflocculators – rapid sand filters –
ground reservoirs – high lift stations – generators –
transformers – chlorination building – chemical building
and other building in the plant
Prepare the structural calculation sheet
Prepare the pipe yard
Prepare the technical specifications of electromechanical
and civil works
Prepare the dewatering design and calculation sheets
Prepare the sheet pile design and calculation sheet
Solve problems at site
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Project # 13
Project Name Rehabilitation and Expansion of Water Treatment Plants and Water
Distribution Networks in Alexandria – High Priority Projects (EUM /
Alex HPP) - USAID GRANT No. 263-0270.02
Project Location Alexandria Governorate
Client AWGA - USAID
Main Consultant Montgomery Watson Harza
Year 2003- 2005
Project Description The project includes the following tasks:
Review Drawings and submittals of water treatment plants in
Alexandria Water Company. The work includes also the
Analysis of Variation Orders and Review the submittals from
Contractor.
The Project includes the analysis of variation orders and
negotiation of the contractor and issue the final VOR.
The work also includes reviewing of the submittals submitted
from Contractor for rehabilitation of water treatment plants.
The reviewed drawings, submittals, calculation sheets, O&M
manuals of water treatment plants are:
Manshia Water Treatment Plant with capacity 370,000 m3/d
Siouf Water Treatment Plant with capacity 860,000 m3/d
Rond Point Water Treatment plant with capacity 590,000 m3/d
Nozha Water Treatment Plant with capacity 170,000 m3/d
Borg Al Arab Water Treatment Plant with capacity 550,000
m3/d
Nobaria Water Treatment Plant with capacity 460,000 m3/d
Mamoura Water Treatment Plant with capacity 210,000 m3/d
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Project # 14
Project Name Rehabilitation and Expansion of Water Treatment Plants and Water
Distribution Networks in Alexandria – High Priority Projects (EUM /
Alex HPP) - USAID GRANT No. 263-0270.02
Project Location Alexandria Governorate
Client AWGA - USAID
Main Consultant Montgomery Watson Harza
Year 2003- 2005
Project Description The project includes the following tasks:
Review Drawings and submittals of carrier pipelines in
Alexandria Water Company. The work includes also the
Analysis of Variation Orders and Review the submittals from
Contractor.
The Project includes the analysis of variation orders and
negotiation of the contractor and issue the final VOR.
The work also includes reviewing of the submittals submitted
from Contractor for the following pipelines
Pipes with diameter 100mm and 38 Km length
Pipes with diameter 150mm and 11 Km length
Pipes with diameter 200mm and 14 Km length
Pipes with diameter 300mm and 16 Km length
Pipes with diameter 500mm and 10 Km length
Pipes with diameter 700mm and 12 Km length
Pipes with diameter 1000mm and 7.3 Km length
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Project Name Damietta Water Supply System
Project Location Water Supply System to feed 52 buildings and
recreational area in Damietta
Client NOPWASD
Contracted By Senior Consult ing Engineers
Project Duration 2008
Required Expertise Prepare design and tender documents for water supply
system
Project Description The Project includes preparation of design and tender
documents of water supply system and Supervision of
construction activity
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 1
Project Name Belbeis Industrial City (150 Feddans located at the road
connects between 10t h
Ramadan and Belebis ci ty)
Project Name Belbeis Industrial City (150 Feddans located at the road
connects between 10t h
Ramadan and Belebis ci ty)
Project Location Belbeis Industrial City (150 Feddans located at the road
connects between 10t h
Ramadan and Belebis ci ty)
Client Al Sharkia Water and Sanitary Company
Contracted By Senior Consult ing Engineers
Project Duration 2008
Required Expertise Prepare tender documents for water si te and water
distribution network
Project Description The Project includes preparation of tender documents of
water si tes which includes water wells, ground
reservoirs, high l if t pump station, chlorination building,
transformer and generator. The work includes the design
the water distribution network. The work includes the
preparation of technical specifications and bil ls of
quanti t ies.
Project Name Belbeis Industrial City (150 Feddans located at the road
connects between 10t h
Ramadan and Belebis ci ty)
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 2
Project Name New Cairo WTP 500,000 m3/day (PPP).
Project Location New Cairo WTP in New Cairo, Cairo, Egypt
Client European Commission, Ministry of Housing, Ministry of
Finance, Holding Company for water and wastewater
Contracted By (Parsons Brinckerhoff / MWH Consortium)
Project Duration 2008
Required Expertise Prepare the Private public Partnership (PPP) ender
documents for water si te and water distribution network
Project Description Prepare and help the HCWW and Ministry of Housing to
develop operate, buil t and transfer for new Cairo water
treatment plant 500,000 m3/day. The main tasks are
review the exist ing technical due dil igence report;
provide the technical input for the legal documentation;
and support the marketing of the project to potential
investors as well as answer technical questions raised by
potential bidders . Review the exist ing technical due
dil igence report;
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 3
Project Name Potable Water Pipeline in El Marg 1600/1400 mm
Diameter
Project Location From El Marg Water Treatment Plant to El Salam
District
Client Arab Contractor – Osman Ahmed Osman
Contracted By Senior Consult ing Engineers
Project Duration 2007
Required Expertise Prepare shop drawing for pipeline 1600 / 1400 mm with
total length of about 3.6 km.
Project Description The Project includes preparation of work shop drawing
of potable water pipelines 1600 mm diameter with length
1.6 km and pipeline 1400mm diameter with length 2 km.
The work also includes the details of valve chambers
and thrust blocks.
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 4
Project Name Raw Water Pipeline in El Marg 1800mm Diameter
Project Location From Ismailia Canal to El Marg East to Cairo
Client Arab Contractor – Osman Ahmed Osman
Contracted By Senior Consult ing Engineers
Project Duration 2006
Required Expertise Prepare shop drawing for two pipe l ine 1800 mm length
and each about 7 km length
Project Description The Project includes preparation of work shop drawing
of raw water pipelines each with diameter 1800 mm and
7 km length. The work also includes the details of valve
chambers, canal crossings and thrust blocks and
structural details.
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 5
Project Name Water Treatment Plants for Iron and Manganese
Removal (25 l /s) – Menofiya Governorate
Project Location Menofiya Governorate
Client NOPWASD
Contracted By Senior Consult ing Engineers
Project Duration 2005
Required Expertise Review Civi l and Electromechanical drawings and
submittals for Five (5) water treatment plants for iron
and Manganese removal in Menofiya governorate.
Project Description Review Civil and Electromechanical drawings and
submittals for Five (5) water treatment plants for iron
and Manganese removal in Menofiya governorate The
water treatment plant capacity is 25 l /s. These plants are
located in the followings vil lages:
Toukh Tanbasha
Gaza
Allafy
Aldaw
Baraks
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 6
Project Name Water Treatment Plants for Iron and Mangane se Removal
(50 l /s) – Menofiya and Sohag Governorate
Project Location Menofiya Kaliubyia and Sohag Governorate
Client NOPWASD
Contracted By Senior Consult ing Engineers
Project Duration 2005
Required Expertise Review Civil and Electromechanical drawings and
submittals for Twelve (12) water treatment plants for iron
and Manganese removal in Menofiya , Kaliubyia and Sohage
governorate.
Project Description Review Civil and Electromechanical drawings and
submittals for Twelve (12) water treatment plants for iron
and Manganese removal in Menofiya and Sohag governorate
The water treatment plant capacity is 50 l /s. These plants
are located in the followings vil lages:
Bahnay, Zaweit Bem, Saft Gzam, Meet Fares
Kamshoush
Bahada, Shoubra Shehab, Al Mounera, Kafr Ramada,
Al Monshaa Al Kobra, Kafr Mouis
Al Harga Kebly
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 7
Project Name Water Treatment Plants for Iron and Manganese Removal
(50 l /s) – Menofiya and Sohag Governorate
Project Location Menofiya and Sohag Governorate
Client NOPWASD
Contracted By Senior Consult ing Engineers
Project Duration 2005
Required Expertise Review Civil and Electromechanical drawings and
submittals for six (6) water treatment plants for iron and
Manganese removal in Menofiya, Kaliubyia and Sohage
governorate.
Project Description Review Civil and Electromechanical drawings and
submittals for six (6) water treatment plants for iron and
Manganese removal in Menofiya and Sohag governorate The
water treatment plant capacity is 50 l /s. These plants are
located in the followings vil lages:
Bakhaty, Al raheb, Monshat Al Nour, Al Tolihat .
Al Eghata, Om Dos
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 8
Project Name Water distribution networks and water treatment plant in
Belbeis ci ty, Sharqyia governorate
Project Location Sharqyia Governorate
Client NOPWASD
Contracted By Senior Consult ing Engineers
Project Duration 2005
Required Expertise Review Civil and Electromechanical drawings, submittals
and designs for water distribution works and water
treatment plant
Project Description Review Civil and Electromechanical drawings submittals
and design for water distribution networks and water
treatment plant in Belbeis ci ty
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 9
Project Name Abu Swair Distribution Network and Water
Treatment Plant
Project Location Abu Swair city – Ismailia Governorate – Egypt
Client NOPWASD
Contracted By Arab Contractors – Consulting Engineering & Technical
Services Department – Environmental Engineering Division
Project Duration 1998 – 2002
Required Expertise Detailed Engineering Design for water distribution system and
water treatment plant
Project Description
The Project includes the design of water distribution network, elevated tank, dewatering system, intake,
water treatment plant.
The water distribution pipe diameters range from 100mm to 400mm with lengths about 29500 m (29.5
km). The elevated tank with capacity 500 m3. The water treatment plant with design capacity of 400 l/s.
the plant comprises of intake structure, intake conduit, raw pump station, flash mixing tank, alum
solution tanks, calri-flocculators, rapid sand filters, ground reservoirs, high lift pump, standby
generator, transformer, chlorine and chemical building.
The work includes the following tasks:
Preparation of preliminary report of water distribution network, water treatment plant and elevated
tank.
Tender documents which includes:
Detail drawings (Mechanical, electrical, structural, architectural)
Technical specifications
Bill of Quantities
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 10
Project Name China Project in Free Zone in Suez Gulf
Project Location Suez Gulf – Egypt
Client Egyptian – China Company
Contracted By Arab Contractors – Consulting Engineering & Technical
Services Department – Environmental Engineering Division
Project Duration 2002
Required Expertise Detailed Engineering Design for ground water supply tanks and
high lift pumping station.
Project Description The Project includes the design of ground storage tanks and
high lift pumping station with capacity of 18,000 m3/d. The
work includes the preparation of the detail drawings of the
auxiliary facilities such as generators, transformers, fuel tanks,
etc.
The work includes the following tasks:
Prepare the tender documents for water and wastewater
works which includes general and special conditions,
technical specifications, preamble and bills of quantities
Evaluation of the bids of the contractors.
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 11
Project Name Middle Egypt Project (USAID Project)
Project Location Minia Governorate – Egypt
Client Montgomery Watson Harza – American Consulting Firm
Contracted By Senior Consulting Engineers
Project Duration 2001
Required Expertise Design of slow sand filter water treatment plant in Sultan
village
Project Description Prepare the conceptual design of water treatment plant in Sultan
village in Minia governorate. The plant consists of roughing
filter, water intake from river Nile, raw water pump station,
slow sand filter units, ground reservoirs, sludge lagoons,
auxiliary buildings, finished water pumping station. The work
includes the design of water carrier pipeline 300 mm diameter
and 3500 m length to the elevated tanks in Sawada village. The
work also includes the calculation sheet and basis of design
report.
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 12
Project Name Middle Egypt Project (USAID Project)
Project Location Minia, Fayoum and Beni Suef governorates – Egypt
Client Montgomery Watson Harza – American Consulting Firm
Contracted By Senior Consulting Engineers
Project Duration 2001
Required Expertise Assessment of water facilities
Project Description Participation in the assessment of water treatment plants in
Fayoum, Minia and Beni Suef Governorates. The assessment
study covers the hydraulic and organic loads, assessment of the
existing electromechanical equipment. Identify the problem in
each plant and the required additional work to upgrade the
plant
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 13
Project Name Bulk Meters in Secondary Cities Project
Project Location Nuweiba, Luxor, Aswan, Mansoura, Sharm El Shiekh
Client Chemonics International – American Consulting Firm
Contracted By Senior Consulting Engineers
Project Duration 2000
Required Expertise Prepare the tender documents
Project Description Prepare a report identifying the required water meter to
measure the amount of water at different places in Luxor,
Nuweiba, Mansoura, Aswan and Sharm El Shiekh Cities. The
work also include the preparation of the detailed drawings,
technical specification and bills of quantities.
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 14
Project Name Raw Water Pipeline 1800 mm Dia from Berkash to
Shiekh Zayed WTP
Project Location Cairo – Egypt
Client Industrial and Engineering Projects Company
Contracted By Senior Consulting Engineers
Project Duration 2000
Required Expertise Prepare the workshop drawings
Project Description Prepare the workshop drawings for the two pipelines each 1800
mm diameter from GRP to transfer the raw water from Nile in
Berkash to Shiekh Zayed water treatment plant in 6th
October
city. The work also includes the preparation of workshop
drawings for crossing under Mansouria Canal and Alex – Cairo
desert road. The work also includes the mechanical and
structural workshop drawings of anti hammer devices and valve
chambers.
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 15
Project Name Bayad Al Arab Distributon Network
Project Location Bayad Al Arab – Beni Suef Industrial City – Egypt
Client Ministry of Housing
Contracted By Faculty of Engineering – Ain Shams University
Project Duration 2002
Required Expertise Detailed Engineering Design for water distribution system and
elevated tank
Project Description The Project includes the design of water distribution network,
elevated tank.
The water distribution pipe diameters ranges from 100mm to
700mm with lengths about 30000 m. The elevated tank with
capacity of 1000 m3.
The work includes the following tasks:
Preparation of preliminary report of water distribution
network, water treatment plant and elevated tank.
Tender documents which includes:
Detail drawings (Mechanical, electrical, structural,
architectural)
Technical specifications
Bill of Quantities
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 16
Project Name Marsa Alam Water Resources
Project Location Marsa Alam – Hurgada – Red Sea Governorate – Egypt
Client Red Sea Governorate
Contracted By Horse Company
Project Duration 1999
Required Expertise Assessment report for water resources in Marsa Alam in Red
Sea governorate.
Project Description A study report to assess the water resources and water demand
in Marsa Alam to provide the tourist villages by water supply.
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 17
Project Name South Sinai Water Resources
Project Location South Sinai governorate – Egypt
Client South Sinai Governorate
Contracted By Horse Company
Project Duration 1999
Required Expertise Assessment report for water resources in South Sinai in Red
Sea governorate.
Project Description A study report to assess the water resources and water demand
in South Sinai to provide the tourist villages by water supply.
Project Name Fire Fighting Network in Hospital
Project Location Nasr City – Cairo - Egypt
Client Insurance Hospital – Nasr City – First District
Contracted By Senior Consulting Engineers
Project Duration 1998
Required Expertise Tender documents
Project Description Prepare the design and tender documents for fire fighting
network in Insurance hospital in Nasr City. The work also
includes the rehabilitation of the ground reservoir. The work
includes the supervision on the contractor and test of the pipes
in the field.
The work includes the quality control during the supervision
period. The work includes the auditing work for the ongoing
tests of construction materials such as sands, gravel, concrete
test, steel bar, pipe tests in the factory and in the field and issue
the certificate of completion.
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 18
Project Name Desouk Water Treatment Plant
Project Location Desouk City – Egypt
Client National Organization of Potable Water and Sanitary Drainage
Contracted By Al Asoake Al Tugaria Company - Contractor
Project Duration 2002
Required Expertise Redesign of the Rapid Sand Filter Gallery
Project Description Redesign of the pipe gallery and rapid sand filters in Desouk
water treatment plant and prepare the hydraulic calculation
sheet.
Project Name Motobas Water Treatment Plant
Project Location Motobas City – Egypt
Client National Organization of Potable Water and Sanitary Drainage
Contracted By Al Asoake Al Tugaria Company - Contractor
Project Duration 2002
Required Expertise Redesign of the Rapid Sand Filter Gallery
Project Description Redesign of the pipe gallery and rapid sand filters in Motobas
water treatment plant and prepare the hydraulic calculation
sheet.
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 19
B – Wastewater Projects
Project Name Wastewater Collection System for 11 vil lages in Quesna
(Menofiya Governorate)
Project Location Quesna Markaz – Menofiya Governorate
Client NOPWASD
Contracted By Senior Consult ing Engineers
Project Duration 2008
Required Expertise Design the wastewater collection system in 11 vil lages in
Quesna Markaz in Menofiya Governorate . These vil lages
are Taha Shoubra, Om Khnan, Agayza, Kafr El Arab, Kafr
Absheesh, Shoubra Qubala, Munshaat Om Khnan, Kafr Zein
El Deen, Oshleem, Kafr Oshlee m, Kafr Al Salamiya. Senior
Also supervising the construction activit ies of sewer
pipelines, Manholes, force mains and pump stations
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 20
Project Name Wastewater Collection System for 9 vil lages in Assuit
Governorate
Project Location Assuit Governorate
Client NOPWASD
Contracted By Senior Consult ing Engineers
Project Duration 2008
Required Expertise Design the wastewater collection system in 9 vil lages in
Assuit Governorate. These vil lages are Bani Ghaleb, Garf
Sarhan, Bani Magd, Al wasta, Magrees, Al Hamam, Al
Eqaal, Al Quasir . Senior Also supervising the construction
activit ies of sewer pipelines, Manholes, force mains , Pump
stations, and wastewater treatment plants
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 21
Project Name Scada System for Aranaa 250000 m3/day in Makkah Al
Mukarramah, Kingdom of Saudi Arabia
Project Location Makkah Al Mukarramah, Saudi Arabia
Client Abdul Salam Ogab Al Thagafi , Engineering Bureau, Civil
Consultations
Contracted By Senior Consult ing Engineers
Project Duration 2008
Required Expertise Design the philosophy of Scada system in Aranaa
wastewater treatment plant in Makkah Al Mukaramah, KSA.
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 22
Project Name Wastewater project in Warak El Hadar Village Giza, Egypt
Project Location Warak El Hadar Island, Giza Governorate, Egypt
Client CAPW
Contracted By Senior Consult ing Engineers
Project Duration 2007
Required Expertise Design the complete wastewater collection system, force
mains and pump station. Prepare the tender documents and
environmental impact assessment.
Project Description Prepare the preliminary report and complete calculation
sheets for sewerage network. Environmental impact
assessment studies and complete tender documents.
Including album of drawings, general conditions, special
conditions and technical specifications and bil ls of
quanti t ies.
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 23
Project Name Gabal Al Asfar Wastewater Treatment Plant – Contract # 19
Project Location Cairo – Egypt
Client Degremont Company
Contracted By Senior Consult ing Engineers
Project Duration 2005
Required Expertise Auditing the construction and O&M Procedures
Project Description Study Contract Documents to learn of the contractual
requirements for quality control and audit of quality control.
Review all inspection reports, procurement reports, testing
reports, condition reports, non-conformance reports, and shop
drawing submittals to determine any deficiencies.
Recommend corrective action for these deficiencies.
Review punch lists of all features.
Review as-built drawings for completeness.
Review additional documentation for completeness such as O
& M Manuals and preventive maintenance programs.
Submit a Complete Audit Report without attaching copies of
the reviewed material.
Current status of the project versus stated goals as related to
schedule, construction costs.
Future status which shall cover the estimate total cost of
project, expected time of completion.
The scope of the audit would include all phases of operations
and maintenance, including procurement, training, use of
spare parts, preventative maintenance, safety, and operation
performance through laboratory testing.
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 24
Project Name Wastewater project in Menofiya in vil lages; Heet, Seroheet ,
Kafr Fisha, Fisha Al Kobra, Kamshoush
Project Location Menofiya Governorate
Client NOPWASD
Contracted By Senior Consult ing Engineers
Project Duration 2004
Required Expertise Review Civil and Electromechanical drawings and
submittals for wastewater projects in Menofiya governorate
Project Description Review Civil and Electromechanical drawings and
submittals for wastewater projects in Men ofiya
governorate. The project includes sewerage system,
force mains, pump stations and wastewater treatment
plants.
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 25
Project Name Sludge Management in Greater Cairo
Project Location Greater Cairo
Client General Organization for Sanitary Drainage in Gr eater
Cairo
Contracted By Senior Consulting Engineers
Project Duration 24 Months starts from June 2003
Required Expertise Sludge treatment facilities and master plan for sludge
treatment, disposal and reuse in greater Cairo
Project Description
Greater Cairo has 6 wastewater treatment facilities and it produces 300,000 tons
dry solids per year and it is expected to increase up to 500,000 tons per year in
year 2022. Cairo GOSD suffers from disposing this sludge in a way which is not
complying with environmental regulation in Egypt which causes a lot of
environmental problems.
The project includes the following tasks:
Evaluation of the exist ing sludge treatment facil i t ies.
Carry out the pilot study to monitor the proposed sludge treatment methods
suitable for Cairo
Prepare the master plan for the sludge treatment facil i t ies
Marketing study for produced sludge
Prepare the training programs for staff in Cairo GOSD
Carry out the insti tutional work and Establish a management department for sludge
handling issue
Prepare the tender documents for the sludge treatment facil i t ies for greater Cairo.
Prepare the public awareness programs for farmers whom are going to use the
treated sludge.
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 26
Project Name Middle Egypt Project
Project Location Minia, Fayoum and Beni Suef Governorate
Client Earth- Tech (American Consultant Firm)
Contracted By Chemonics / Senior Consulting Engineers
Project Duration 6 months
Required Expertise Design the sewerage network and water pipelines and
force mains
Project Description This project includes the preparation of the final
design and workshop drawings for Beni Ibyed village,
water pipelines and force mains in Minia city.
The project includes the following tasks:
Calculation sheets by using Sewer CAD.
General and Special details
Plans and profiles of the force mains
Canal crossings
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 27
Project Name Farshut Wastewater Works
Project Location Farshut city – Qena Governorate – Egypt
Client NOPWASD
Contracted By Arab Contractors – Consulting Engineering & Technical
Services Department – Environmental Engineering Division
Project Duration 1999 – 2002
Required Expertise Detailed Engineering Design for sewage collection system,
force mains, sewage pumping stations and wastewater
treatment plants
Project Description The Project includes the design of sewage collection works,
force mains and 3 sewage pump stations and wastewater
treatment plants.
The area of Farshut city is 900 feddans. The length of sewers is
40200 m with diameters range from 200mm to 1200 mm and
the manhole numbers are 2584. The force mains are four force
mains
Force main with diameter 300 mm and 320 m length
from pump station NO. 1 to the sewer system of main
pump station
Force main with diameter 350 mm and 500 m length
from pump station No. 2 to the sewer system of main
pump station.
Two force mains with diameter 800 mm and 12000 m
(12 km) length from main pump station to the
wastewater treatment plant.
The project includes the design of three pump stations with
design flow of 100 l/s, 115 l/s and 960 l/s. The pump station
site includes the design of transformer, standby generator,
electrical equipment,…..etc.
The wastewater treatment plant is oxidation pond system with
capacity of 45000 m3/d.
The work includes the following tasks:
Preparation of preliminary report of sewage collection system,
pump stations, force mains and wastewater treatment plants.
Tender documents which includes:
Detail drawings (Mechanical, electrical, structural,
architectural)
Technical specifications
Bill of Quantities
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 28
Project Name China Project in Free Zone in Suez Gulf
Project Location Suez Gulf – Egypt
Client Egyptian – China Company
Contracted By Arab Contractors – Consulting Engineering & Technical
Services Department – Environmental Engineering Division
Project Duration 2002
Required Expertise Detailed Engineering Design for sewage pumping station and
wastewater treatment plant
Project Description The Project includes the design of raw wastewater pumping
station, force main and wastewater treatment facilities with
capacity of 14000 m3/day. The wastewater treatment system is
activated sludge process (extended aeration system). The work
includes the preparation of the detail drawings of the auxiliary
facilities such as generators, transformers, fuel tanks, etc.
The work includes the following tasks:
Prepare the tender documents for water and wastewater
works which includes general and special conditions,
technical specifications, preamble and bills of quantities
Evaluation of the bids of the contractors.
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 29
Project Name Rayssa and El Obour Districts
Project Location Al Arish City- North Sinai – Egypt
Client Ministry of Housing
Contracted By Arab Contractors – Consulting Engineering & Technical
Services Department – Environmental Engineering Division
Project Duration 2002
Required Expertise Detailed Engineering Design for 4 sewage pumping stations
with different capacities.
Project Description The Project includes the design of four sewage pumping
stations with different capacities ranging from 25 liter/sec to 80
liter/sec. The work includes the preparation of mechanical,
electrical, architectural and structural detail drawings. The
works includes preparation of the details of auxiliary facilities
such as generators, transformers, fuel tanks, etc.
The work includes to prepare the tender documents for sewage
pumping stations which includes mechanical, electrical,
architectural and structural detail drawings. The work also
includes general and special conditions, technical
specifications, preamble and bills of quantities
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 30
Project Name Middle Egypt Project (USAID Project)
Project Location Minia, Fayoum and Beni Suef governorates – Egypt
Client Montgomery Watson Harza – American Consulting Firm
Contracted By Senior Consulting Engineers
Project Duration 2001
Required Expertise Conceptual Engineering Design for wastewater collection
system, force mains and two sewage pumping stations in Beni
Ibyed village, Abu Qurqas, Minia governorates
Project Description The Project includes the conceptual design of wastewater
collection system, force mains and two wastewater pumping
stations
The work includes the following tasks:
Prepare the conceptual design of wastewater collection
system. The design flow is 80 liter/sec and the total sewer
pipe length is about 20 km with diameters ranges from
200mm to 400 mm.
Prepare the conceptual design of two force mains. The
first force main is 100 m length and 160 mm diameter.
The second force main is 4500 m length and 300 mm
diameter.
Prepare the conceptual design of wastewater pumping
stations; in-system pump station and main pump station.
The capacity of in-system pump station is 25 liter/sec and
the design flow of main pump station is 80 liter/sec. The
design includes the auxiliary facilities such as generators,
transformers, fuel tanks and control panels
Prepare the basis of design report
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 31
Project Name Middle Egypt Project (USAID Project)
Project Location Minia, Fayoum and Beni Suef governorates – Egypt
Client Montgomery Watson Harza – American Consulting Firm
Contracted By Senior Consulting Engineers
Project Duration 2001
Required Expertise Conceptual Engineering Design for wastewater pumping
stations and force mains in Minia city.
Project Description The Project includes the conceptual design of wastewater
pumping stations (PS#1, PS#2 and PS#4). The design capacity
of pump station #1 is 100 l/s, PS#2 320 l/s and PS#4 900 l/s.
The work includes the following tasks:
Prepare the conceptual design of wastewater pumping
stations and single line diagrams
Prepare the conceptual design of force mains between
pump stations and to the wastewater treatment plant.
Force main from PS#1 to PS#3 is 300 mm diameter
with 1200m length. Force main from PS#2 to PS#4 is
500 mm diameter with 3500 m length. Force main from
PS # 4 to WWTP is 800 mm diameter and 4800 m
length.
Prepare the basis of design report
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 32
Project Name Middle Egypt Project (USAID Project)
Project Location Minia, Fayoum and Beni Suef governorates – Egypt
Client Montgomery Watson Harza – American Consulting Firm
Contracted By Senior Consulting Engineers
Project Duration 2001
Required Expertise Conceptual Engineering Design for wastewater treatment in
Beni Suef city
Project Description The Project includes the conceptual design of wastewater
treatment plant in Beni Suef city with capacity of 50000 m3/d.
The treatment process is activated sludge process (extended
aeration system). The conceptual design includes the return
sludge pumps and excess sludge pumps. The sludge treatment
includes gravity thickeners and sludge drying beds.
The work includes the following tasks:
Prepare the conceptual design of wastewater treatment
process with capacity of 50000 m3/d. prepare the single
line diagrams.
Prepare the basis of design report
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 33
Project Name Middle Egypt Project (USAID Project)
Project Location Minia, Fayoum and Beni Suef governorates – Egypt
Client Montgomery Watson Harza – American Consulting Firm
Contracted By Senior Consulting Engineers
Project Duration 2001
Required Expertise Master Plan for water and wastewater facilities
Project Description Participation in the master plan studies. The work includes the
Preparation of the design criteria of water and wastewater
works. Conceptual design of water treatment plants with
different capacities, the ground water wells and elevated tanks.
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 34
Project Name Middle Egypt Project (USAID Project)
Project Location Minia, Fayoum and Beni Suef governorates – Egypt
Client Montgomery Watson Harza – American Consulting Firm
Contracted By Senior Consulting Engineers
Project Duration 2001
Required Expertise Assessment of wastewater facilities
Project Description Participation in the assessment of wastewater treatment plants
in Fayoum, Minia and Beni Suef Governorates. The assessment
study covers the hydraulic and organic loads, assessment of the
existing electromechanical equipment. Identify the problem in
each plant and the required additional work to upgrade the
plant.
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 35
Project Name Force Main Crossing Under Bahr Youssef Canal
Project Location Fayoum governorates – Egypt
Client General Economic Authority for Water and Sanitation
Contracted By Senior Consulting Engineers
Project Duration 2003
Required Expertise Design of Force Mains Crossings
Project Description The consulting work includes the preparation of tender
documents of two sleeves concrete pipes with 2000 mm
diameter and 30 m length for each sleeve pipe. The work
includes design of the two force mains 1000 mm diameter each.
The work also includes the design of two chambers (inlet
chamber and outlet chambers). The tender documents includes
the general and special conditions, technical specifications, bills
of quantities, detailed drawings.
The work includes the quality control and Supervision during
construction period. The work includes the auditing work for
the ongoing tests of construction materials such as sands,
gravel, concrete test, and steel bar, pipe tests in the factory and
in the field.
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 36
Project Name Three Force Mains in Fayoum City
Project Location Fayoum governorates – Egypt
Client General Economic Authority for Water and Sanitation
Contracted By Senior Consulting Engineers
Project Duration 2003
Required Expertise Design of Three Force Mains each with diameter 600 mm
diameter
Project Description The consulting work includes the preparation of tender
documents for three force mains each has diameter of 600 mm
and the total length is 3500 m. The tender documents includes
the general and special conditions, technical specifications, bills
of quantities and detailed drawings
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 37
C – Reuse Projects
Project Name Feasibility Study of Reuse of Treated Wastewater
and Sludge in Jeddah Ci ty
Project Location Jeddah City – Saudi Arabia
Client Water and Sanitary Drainage Authority (WSDA) in Makkah Al
Mukarama Region
Contracted By Zohair Fayez and Partners (Saudi Consulting Firm)
Project Duration 2001
Required Expertise Technical and economical study
Project Description The consulting work includes the followings:
Identify the present and future amount of generated
wastewater and sludge in Jeddah city.
Identify the present wastewater and sludge reuse and
disposal.
Identify the existing environmental regulations in Saudi
Arabia.
Identify the quality of wastewater and sludge and the
deficiency in wastewater treatment plants to produce
effluent can e reused safely.
Carry out the proposed reuse projects and prepare the
economical analysis which identify the optimistic
solution.
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 38
Project Name Reuse Project in Nuweiba City
Project Location Nuweiba City – South Sinai -Egypt
Client Chemonics International – American Consulting Firm
Contracted By Senior Consulting Engineers
Project Duration 2002
Required Expertise Tender Documents
Project Description The consulting work includes the followings:
Prepare the conceptual design of the proposed project
Outline specifications
Bill of quantities
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 39
Project Name Reuse Project in Nasr City
Project Location Naser City – Aswan Governorate – Egypt
Client Chemonics International – American Consulting Firm
Contracted By Senior Consulting Engineers
Project Duration 2002
Required Expertise Tender Documents
Project Description The consulting work includes the followings:
Prepare the conceptual design of the proposed prject
Outline specifications
Bill of quantities
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 40
E – Industrial Wastewater Treatment Projects
Project Name SM Company, Mehala El Kobra City, Egypt
Project Location Mehala El Kobra City, Egypt
Client Egypt Environmental Initiatives Fund (EEIF)-
The Environmental Management & Technology Fund (EM&T)
Contracted By Consultants for Development and Environment (CDE) – El-
Kholei and Associates
Project Duration 2003
Required Expertise Design the industrial wastewater treatment plant and
prepare the tender documents (Compact Units).
Project Description The work includes the design of industrial wastewater
treatment plant and prepare the tender documents. The tender
documents includes technical specification and bill of
quantities.
Project Name Dolci Factory in 6t h
October City, Egypt
Project Location Dolci Factory in 6t h
October City, Egypt
Client Dolci Factory in 6t h
October City, Egypt
Contracted By Howeidy Consulting Office
Project Duration 1998
Required Expertise Design the industrial wastewater treatment plant and
prepare the tender documents (Compact Unit).
Project Description The work includes the design of industrial wastewater
treatment plant and prepare the tender documents. The tender
documents includes technical specification and bill of
quantities.
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 41
Project Name Kimo Factory, Egypt
Project Location Kimo Factory, Egypt
Client Kimo Factory, Egypt
Contracted By Howeidy Consulting Office
Project Duration 1998
Required Expertise Design the industrial wastewater treatment plant and
prepare the tender documents (Compact Unit).
Project Description The work includes the design of industrial wastewater
treatment plant and prepare the tender documents. The tender
documents includes technical specification and bill of
quantities.
Project Name Lilly Factory, Egypt
Project Location Lilly Factory, Egypt
Client Lilly Factory, Egypt
Contracted By Howeidy Consulting Office
Project Duration 1998
Required Expertise Design the industrial wastewater treatment plant and
prepare the tender documents (Compact Unit)
Project Description The work includes the design of industrial wastewater
treatment plant and prepare the tender documents. The tender
documents includes technical specification and bill of
quantities.
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 42
F – Environmental Studies
Project Name
ENVIRONMENTAL IMPACT ASSESSMENT AND
ENVIRONMENTAL MANAGEMENT PLAN STUDY IN
EAST DELTA AGRICULTURAL SERVICES PROJECT
Project Location Egypt
Client East Delta Agricultural Project – Ministry of Agriculture and
World Bank
Project Duration 2004
Required Expertise Carry out Environmental Impact Assessment for Current
Activities in East Delta Region .
Project Description East Delta Agricultural Services Project [EDASP] is one of the
major land development schemes of Egypt which started
physically in May 1999. EDASP area is located south of Lake
Manzala alongside El Salam canal to the west and east of the
Suez Canal. This proposed project is designed to assist some
29,000 new settlers on an area of about 130,000 feddans under
the government sponsored reclamation schemes through
provision of credit and extension (IDA Credit 3002 EGT and
IFAD Loan 440 EG). The baseline costs are estimated at US$
40 million over an implementation period of five years.
The main purpose of this Environmental Impact Assessment
(EIA) and Environmental Management Plan (EMP) study is to
cover the main environmental hotspots in the EDASP project
area. The Environmental problems which reported in the TOR
are:
Using the polluted wastewater in Bahr Al Bakar in
irrigation and reclamation activities because the irrigation
water in El Salam canal is not used.
Disposal of untreated domestic and industrial wastewater at
water courses and open areas due to absence of wastewater
treatment facilities.
Scarcity of clean potable water.
Raising the livestock very close to the human
accommodation places.
The accumulation of domestic and agricultural solid waste
management
The environmental management plan of agricultural
chemicals (pesticides and fertilizers).
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 43
Project Name ENVIRONMENTAL, HEALTH AND SAFETY
COUNTRY PROFILE FOR EGYPT
Project Location Egypt
Client Environmental Policy Centre Europe (EPCE) – Member of the
LAWGIBB Group
Contracted By Senior Consulting Engineers
Project Duration 1999
Required Expertise Country Profile and Occupational Health & Safety
Project Description Develop a report describing the regulatory requirements
concerning occupational health & safety and partially
environmental currently in force or under development in
Egypt. The scope of work includes: (1) general E, H &S
principles; permits requirements; and administrations. (2)
Waste management (including hazardous waste). (3) General
H&S duty of care requirements (4) Emergency planning and
response. (5) Electrical safety, (6) first aid (7) accident
reporting and investigation. (8) Control of contractors.
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 44
Project Name Environmental Impact Assessment for Port Fouad
wastewater treatment plant
Project Location Port Fouad - Egypt
Client EEAA
Contracted By Arab Contractors – Osman Ahmed Osman
Project Duration 1998
Required Expertise Environmental Impact Assessment
Project Description Prepare an Environmental Impact Assessment report for Port
Fouad wastewater treatment plant and sewerage system in Port
Fouad city in Egypt.
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 45
Project Name Environmental Assessment – First Stage Investment Projects
Governorate of Beni Suef, EGYPT
Project Location Governorate of Beni Suef, EGYPT
Client Harza
Project Duration 2001
Required Expertise Environmental Impact Assessment
Project Description Participate in the Environmental Impact Assessment report for
water and wastewater projects in Beni Suef governorates in
year 2001. The project was funded by USAID. Project Number:
263-0270. The proposed projects includes
Expansion of water treatment of Beni Suef with design
capacity 300 l/s
New wastewater treatment plant with capacity 50000
m3/day
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Project Name Environmental Assessment – First Stage Investment Projects
Governorate of Minia, EGYPT
Project Location Governorate of Minia, EGYPT
Client Harza
Project Duration 2001
Required Expertise Environmental Impact Assessment
Project Description Participate in the Environmental Impact Assessment report for
water and wastewater projects in Minia governorates in year
2001. The project was funded by USAID. Project Number:
263-0270. The proposed projects includes
Expansion of water treatment of Minia with design
capacity 300 l/s
New water treatment plant 100 liter/second (slow sand
filter)
Sewerage system in beni Ibayed village – Abu Qurqas
Rehabilitation of some force mains and pump stations
and water mains in Minia
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Project Name Environmental Assessment – First Stage Investment Projects
Governorate of Fayoum, EGYPT
Project Location Governorate of Fayoum, EGYPT
Client Harza
Project Duration 2001
Required Expertise Environmental Impact Assessment
Project Description Participate in the Environmental Impact Assessment report for
water and wastewater projects in Fayum governorates in year
2001. The project was funded by USAID. Project Number:
263-0270. The proposed projects includes
New wastewater treatment plant in Kohafa 60000
m3/day
Sludge composting site
Sludge force mains 2 pipelines each 250mm
Sewage force mains 2 pipelines each 1000mm
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Project Name Environmental Assessment Study for the Tourist Places in KSA
Project Location Riyadh, KSA
Client SUPREME COMMISSION FOR TOURISM
Main Consultant Law GIBB – British Consultant
Project Duration 2001
Required
Expertise
Sustainable Tourism Programme – Overall Survey of
Environment related information and protection regulations and
Criteria.
Project
Description
The project included the following tasks:
- The structure plan in phase 1.4 will cover the required infra-
structure such as water supply, wastewater treatment, power
supply and solid waste disposal facilities.
- For each of the proposed scenario, infrastructures will be
taken into consideration if it is relevant to the potential
proposals.
- Establish of Environmental Condition Baseline. This will
include the review of all information regarding air and
water quality. This information will reflect current
environmental quality, and identify key trends and
pressures likely to influence the environment over the plan
period and beyond.
- Determination of the sustainable development indicators
that can be used define the environmental baseline. Use the
international recognised standards and approaches for
identifying significant effects using methods compliant with
World Bank, United Nations Environmental Program
(UNEP), United nations Educational Scientific & Cultural
Organization (UNESCO), World Conservation Union
(IUCN), World Wildlife Fund (WWF), Organisation for
Economic Cooperation and Development (OECD) and
European Commission (EC) guidelines.
- Applicable regulations and standards, national and
international
- Focus on identifying potential environmental constraints to
tourism and associated infrastructure development – and on
areas of opportunity and potential enhancement of
environmental quality either as mitigation for impacts or as
an integral part of increasing value.
- An iterative approach to the overall assessment during the
development of the structure plan so that the environmental
impact assessment contributes directly to shaping the
structure plan and provides positive input – identifying the
extent to which potential constraints could be overcome,
impacts mitigated and enhancement opportunities realized.
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 1
- Identify the potential sensitive sites and resources that may
be at risk from pressures exerted by tourism i.e. discharge
to the environment and the disposal of wastes, as well as
physical pressure and disturbance. Water resource
availability will be a key aspect.
- Use of the experience gained elsewhere in the
environmental assessment and management of tourism plan.
- Quantify environmental demands and inputs associated
with the three scenarios for tourism growth and will include
water resources requirements and wastes.
- Predict and quantify environmental impacts for each
scenario to cover water quality and resources.
- Advice on mitigation measures, residual effects and
comparison of options.
- Sustainable methods for minimizing physical risks to
tourists and operators.
- Sustainable Environmental Management Strategies
(developing the guidelines.
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Project Name Environmental Assessment Study for Warak Al Hadar Village
– Giza Governorate
Project Location Gezert Warak Al Hadar, Giza Governorate, EGYPT
Client CAPW
Project Duration 2007
Required Expertise Environmental Impact Assessment Study
Project Description Prepare the EIA study and report for sewerage system, pump
station and force main for Gezeret Warak Al Hadar in Giza
governorate. The total cost of the proposed project is 90 million
LE
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
L – Supervision Works (أعمال اإلشراف على التنفيذ)
Project Name Damietta Water Supply System
Project Location Water Supply System to feed 52 buildings and
recreational area in Damietta
Client NOPWASD
Contracted By Senior Consult ing Engineers
Project Duration 2008
Required Expertise Prepare design and tender documents for water supply
system
Project Description The Project includes preparation of design and tender
documents of water supply system and sewerage system
and Supervision of construction activit ies of water and
wastewater works
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 1
Project Name Wastewater Collection System for 11 vil lages in Quesna
(Menofiya Governorate)
Project Location Quesna Markaz – Menofiya Governorate
Client NOPWASD
Contracted By Senior Consult ing Engineers
Project Duration 2008
Required Expertise Design the wastewater collection system in 11 vil lages in
Quesna Markaz in Menofiya Governorate. These vil lages
are Taha Shoubra, Om Khnan, Agayza, Kafr El Arab, Kafr
Absheesh, Shoubra Qubala, Munshaat Om Khnan, Kafr Zein
El Deen, Oshleem, Kafr Oshleem, Kafr Al Salamiya. Senior
Also supervising the construction activit ies of sewer
pipelines, Manholes, force mains , valve chambers and pump
stations
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 2
Project Name Wastewater Collection System for 9 vil lages in Assuit
Governorate
Project Location Assuit Governorate
Client NOPWASD
Contracted By Senior Consult ing Engineers
Project Duration 2008
Required Expertise Design the wastewater collection system in 9 vil lages in
Assuit Governorate. These vil lages are Bani Ghaleb, Garf
Sarhan, Bani Magd, Al wasta, Magrees, Al Hamam, Al
Eqaal, Al Quasir . Senior Also supervising the construction
activit ies of sewer pipelines, Manholes, force mains , valve
chambers, force mains, 9 pump stations and three
wastewater treatment plants .
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 3
Project Name HVAC in Central Laboratory in Shoubra El
Kheima Water Treatment Plant
Project Location Cairo – Egypt
Client Holding Company for Water and Wastewater
Contracted By Senior Consulting Engineers
Project Duration 2008
Required Expertise Supervision Work
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 4
Project Name Wastewater project in Warak El Hadar Village Giza, Egypt
Project Location Warak El Hadar Island, Giza Governorate, Egypt
Client CAPW
Contracted By Senior Consult ing Engineers
Project Duration 2007
Required Expertise Design the complete wastewater collection system, force
mains and pump station. Prepare the tender documents and
environmental impact assessment.
Project Description Prepare the preliminary report and complete calculation
sheets for sewerage network. Environmental impact
assessment studies and complete tender documents.
Including album of drawings, general conditions, special
conditions and technical specifications and bil ls of
quanti t ies. The Task includes also the supervision of
construction activit ies of sewers, manholes for ce mains and
pump station.
Project Name Conference Hall in Arab Council for Childhood
and Development
Project Location Cairo – Egypt
Client Arab Council for Childhood and Development
Contracted By Senior Consulting Engineers
Project Duration 2005
Required Expertise Supervision Work
Project Description Our Task is to supervise the followings elements which were
under construction. The project was conference Hall at arab
work as quality control consultant. The work include the
supervision of the following tasks:
Electrical work
Decoration work which include (Marble and painting)
Furniture
HVAC
Audi system
Translation System
Wood Works
Fire fighting system
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 5
Project Name Rest House for His Excellency Prince Talal Bin
Abdel Aziz - Arab Council for Childhood and
Development
Project Location Cairo – Egypt
Client Arab Council for Childhood and Development
Contracted By Senior Consulting Engineers
Project Duration 2005
Required Expertise Supervision Work
Project Description Our Task is to supervise the followings elements which were
under construction. The project was rest house at Arab council
for childhood and development. Our work is supervise and
quality control consultant. The work include the supervision of
the following tasks:
Electrical work
Decoration work which include (Marble and painting)
Furniture
HVAC
Audi system
Translation System
Wood Works
Fire fighting system
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 6
Project Name Force Main Crossing Under Bahr Youssef Canal
Project Location Fayoum governorates – Egypt
Client General Economic Authority for Water and Sanitation
Contracted By Senior Consulting Engineers
Project Duration 2003
Required Expertise Quality Control Consultant
Project Description Our Task is to work as quality control consultant. The work
include the whole necessary test such as pipe tests, concrete
block tests, backfilling material tests, steel bar tests and final
water pressure tests for the two force mains.
The work also includes providing the daily report tests, request
for variation orders, request for clarifications, request for
information and as-built drawings.
Project Name Trade Center and Workshop
Project Location Cairo
Client PEUGEOT COMPANY, EGYPT
Contracted By Senior Consulting Engineers
Project Duration 1999
Required Expertise Quality Control Consultant
Project Description The work includes the quality control and inspection of the
daily work for finishing the Regional Office Trade Center and
workshop for Peugeot Company in Egypt which includes
painting, decoration, tiles, air conditioning, ceramic, internal
audio system, electricity, internal telephone circuit, lighting
apparatus, etc.
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 7
Project Name Villa Soheir
Project Location Cairo
Client PRIVATE
Contracted By Senior Consulting Engineers
Project Duration 1999
Required Expertise Design and Quality Control Consultant
Project Description Design and quality control consultant to inspect and supervisor
the plumbing sanitation work for a villa Soheir Al Hakim in
Pyramids area which includes the hot and cold water system,
fire fighting, water treatment for swimming pools.
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 8
Project Name El – Salam Tourist village
Project Location Nuweiba, South Sinai, Egypt
Client PRIVATE
Contracted By Senior Consulting Engineers
Project Duration 1999
Required Expertise Design and Quality Control Consultant for El Salam Tourist
Village in South Sinai
Project Description Design and supervise the extension of El Salam Tourist village
in Nuweiba city. The project includes, Architecture, civil, water
supply, sewerage, lighting, electrical, telephone and
landscaping
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 9
Project Name Tourist Compounds in North Coast in Alamein,
North Egypt
Project Location MIENESY AND KHIATE CONTRACTOR COMPANY
Client PRIVATE
Contracted By Senior Consulting Engineers
Project Duration 1999
Required Expertise Prepare the workshop drawings documents
Project Description Prepare the workshop drawings for plumbing and water supply
and sewerage networks for a tourist compounds in North Coast
in Alamein
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 10
Project Name Basatin Residential Compounds, Jeddah, Saudi
Arabia
Project Location JEDAH – SAUDI ARABIA
Client TRACO Contractor
Contracted By Senior Consulting Engineers
Project Duration 1999
Required Expertise Prepare the conceptual design
Project Description Prepare conceptual designs and bill of quantities for high-class
residential compound – 200 villas and services (Basatin
Compounds).
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 11
M – Training Programs Building Capacity
Project Name Sludge Management in Greater Cairo
Project Location Greater Cairo
Client General Organization for Sanitary Drainage in Greater
Cairo
Contracted By Senior Consulting Engineers
Project Duration 24 Months starts from June 2003
Required Expertise Sludge treatment facili ties and master plan for sludge
treatment, disposal and reuse in greater Cairo
Project Description
Senior held 7 training courses to train the staff in Cairo GOSD in lectures and
on Job training. Every Training Course is 5 working days and the number of
trainees about 15 persons in each course. The titles of courses are as follows:
Design of sludge treatment facil i t ies and environmental guidelines
Laboratory analysis of sludge and compost.
Methods of sludge treatment
Methods of using of composed sludge .
Operation and maintenance of equipment used in sludge composting
Marketing and management
Project Name Project Management for AGOSD staff
Project Location Alexandria
Client General Organization for Sanitary Drainage in Alexandria
Contracted By Career Development Center
Project Duration 2001
Required Expertise Project management Course and provide trainers
Project Description Prepare and submit the project management course of the
senior staff of Alexandria GOSD. The duration of Course was
17 days
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 12
Project Name Design of Sewage Collection System for AGOSD
Staff
Project Location Alexandria
Client General Organization for Sanitary Drainage in Alexandria
Contracted By Career Development Center
Project Duration 2001
Required Expertise Design of Sewerage System Course and provide trainers
Project Description Prepare and submit the design of sewage collection works to
the senior staff of Alexandria GOSD. The duration of Course
was 15 days
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 13
Project Name Operation and Maintenance of Water Treatment
Plants
Project Location Kafr El Shiekh - Egypt
Client Kafr El Shiekh Water Company
Contracted By Career Development Center
Project Duration 2002
Required Expertise Prepare the O & M of water treatment plants course and
provide trainers
Project Description Prepare and submit the course of O & M of water treatment
plants for Kafr El Shiekh Water Company staff. The duration of
Course was 12 days
Project Name Design of water distribution system
Project Location Kafr El Shiekh - Egypt
Client Kafr El Shiekh Water Company
Contracted By Career Development Center
Project Duration 2002
Required Expertise Prepare the design of water distribution system course and
provide trainers
Project Description Prepare and submit the course of design of water distribution
system for Kafr El Shiekh Water Company staff. The duration
of Course was 5 days
Project Name Master Planning of wastewater works in
Alexandria
Project Location Alexandria
Client General Organization for Sanitary Drainage in Alexandria
Contracted By Arab Designers
Project Duration 2002
Required Expertise Prepare the design of master plan of Alexandria course and
provide trainers
Project Description Prepare and submit the course of master planning of wastewater
works for AGOSD staff. The duration of Course was 12 days
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 14
Project Name Master Planning of Wastewater Works in Fayoum,
Minia and Beni Suef
Project Location Fayoum, Minia and Beni Suef
Client Development Training Phase II – American Consultant
Contracted By Senior Consultant Engineers
Project Duration 2002
Required Expertise Prepare the design of master plan of Fayoum, Minia and Beni
Suef course and provide trainers
Project Description Prepare and submit the course of master planning of water and
wastewater works for FEGAWS, MEGAWS, BEGAWS staff.
The duration of Course was 15 days
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 15
I – Road Projects
Project Name China Project in Free Zone in Suez Gulf
Project Location Suez Gulf – Egypt
Client Egyptian – China Company
Contracted By Arab Contractors – Consulting Engineering & Technical
Services Department – Environmental Engineering Division
Project Duration 2002
Required Expertise Detailed Engineering Design for Roads Inside the Plant
Project Description Prepare and submit the design of roads and cross section
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Project #
Project Name Roads to Abo Diab Village - Qena Governorate
Project Location Qena Governorate
Client NOPWASD
Contractor Mokhtar Ibrahim Company
Year 2009
Project Description The project includes the following tasks:
Prepare the design of road connecting between water
treatment plant and Abo Diab village with total length of
about 7 km and width of about 10m
Prepare the plan and profile details
Prepare the technical specifications
SSEENNIIOORR CCoonnssuullttiinngg EEnnggiinneeeerrss
PROJECT FACT SHEET
Municipal Hard Engineering Projects 1
J – Energy Conservation Studies
Project Name Energy Conservation Study
Project Location Minia, Fayoum and Beni Suef governorates – Egypt
Client PLANNING AND DEVELOPMENT COLLABORATIVE
INTERNATIONAL (PADCO) – American Consultant
Contracted By Senior Consulting Engineers
Project Duration 2002
Required Expertise Study and Implementation
Project Description The consulting work includes the followings:
Measurements of the power factor in water and
wastewater facilities in each governorate.
Measurement of pump efficiency in each facility
Identify the problems which led to high power cost.
Identify the solutions to reduce the electricity costs in
each facility.
Supervision the installations to minimize electricity
cost.
Recommended