Multi-Modal Intelligent Traffic Signal System
Project Management Plan Development of Concept of Operations, System
Requirements, System Design, and Test Plan
University of Arizona (Lead) University of California PATH Program
Savari Networks, Inc. SCSC
Econolite Kapsch
Volvo Technology
Version 2.0
4/30/2012
Pooled Fund Project - PMP
Pooled Fund Project - PMP UA_PFP_PMP
Page 1 of 28
RECORD OF CHANGES
A – Added, M- Modified, D - Deleted
Version Number
Date Identification of Figure, Table, or
Paragraph Title or Brief Description
Change Request Number
1.0
3/29/12
N/A
Initial Draft submitted for review and feedback.
CDRL
2.0
4/30/12
All
(1) Reformatted for ease of reading and referencing. (2) Feedback from Review Panel integrated as requested. (3) Project Plan included as an appendix. (4) Acronym listed expanded and included as an appendix
Draft
Review Process
Pooled Fund Project - PMP
Pooled Fund Project - PMP UA_PFP_PMP
Page 2 of 28
Table of Contents 1 OVERVIEW ............................................................................................................................................ 4
1.1 Project Summary ........................................................................................................................... 4
1.1.1 Purpose Scope and Objectives ................................................................................................. 6
1.1.2 Assumptions and Constraints ................................................................................................... 6
1.1.3 Project Deliverables .................................................................................................................. 6
1.1.4 Master Schedule ....................................................................................................................... 7
1.2 DOCUMENT STRUCTURE .......................................................................................................... 8
2 REFERENCES ...................................................................................................................................... 9
2.1 STANDARDS AND DOCUMENTS ............................................................................................... 9
2.2 DEVIATIONS AND WAIVERS ...................................................................................................... 9
3 PROJECT ORGANIZATION .................................................................................................................. 9
3.1 EXTERNAL INTERFACES ........................................................................................................... 9
3.2 INTERNAL STRUCTURE ........................................................................................................... 11
4 MANAGEMENT PROCESS ................................................................................................................ 12
4.1 START-UP .................................................................................................................................. 12
4.2 BUDGET AND COST CONTROL ............................................................................................... 12
4.3 QUALITY CONTROL .................................................................................................................. 13
4.4 RISK MANAGEMENT ................................................................................................................. 13
4.5 HUMAN RESOURCE MANAGEMENT ....................................................................................... 16
4.6 SCOPE MANAGEMENT ............................................................................................................. 17
5 SUPPORTING PROCESSES .............................................................................................................. 17
5.1 COMMUNICATIONS MANAGEMENT ........................................................................................ 17
5.2 CONFIGURATION MANAGEMENT ........................................................................................... 18
6 APPENDICES ...................................................................................................................................... 20
APPENDIX A: TASK DESCRIPTIONS ................................................................................................... 20
APPENDIX B: ACRONYMS .................................................................................................................... 23
APPENDIX C: PROJECT PLAN ............................................................................................................. 24
Pooled Fund Project - PMP
Pooled Fund Project - PMP UA_PFP_PMP
Page 3 of 28
Figure 1 – Master Project Schedule Roll-up ................................................................................................. 8 Figure 2 – External Organization Interfaces ............................................................................................... 10 Figure 3 – Functional Management Organization ....................................................................................... 12 Figure 4 – Risk Management Process ........................................................................................................ 14
Table 1 – List of Deliverables and Due Dates............................................................................................... 6 Table 2 – Programmatic Roles and Responsibilities .................................................................................. 11 Table 3 – Risk Tracking Matrix.................................................................................................................... 15 Table 4 – Project Roles and Responsibilities.............................................................................................. 16 Table 5 – Communication Activities ............................................................................................................ 18 Table 6 – CM File Naming Conventions ..................................................................................................... 19
Pooled Fund Project - PMP
Pooled Fund Project - PMP UA_PFP_PMP
Page 4 of 28
1 OVERVIEW This Project Management Plan (PMP) is intended to provide guidance on the management of the
Cooperative Transportation System Pooled Fund Study (CTS PFS): Multi-Modal Intelligent Traffic Signal
System (MMITSS) project. Originally, the plan utilized the template from the Space and Naval Warfare
(SPAWAR) Systems Center (SSC) San Diego Project Management Plan Template, TM-PP-01. The
template conforms to the Institute of Electrical and Electronics Engineers (IEEE) Standard for Software
Project Management Plans, IEEE Std 1058-1998, for format and content. The template and its standard
were selected as they are flexible enough to be applied to any type of project. The management,
technical, and supporting processes comply with the guidance provided by Standard for Information
Technology - Software Life Cycle Processes, IEEE/Electronic Industries Association (ETA) 12207 Series;
Systems Engineering — System Life Cycle Processes, International Organization for Standardization
(ISO)/International Electrotechnical Commission (IEC) 15288; or the Processes for Engineering a System,
Electronic Industries Alliance (EIA) Standard 632; and the SSC San Diego Systems/Software Engineering
Management Policy. Incorporating feedback from the PMP Draft review, this document has been modified
to meet the needs and expectations of the Multi-Modal Intelligent Traffic Signal System (MMITSS) project.
The MMITSS Principal Investigator (Professor Larry Head) assumes responsibility for this document and
updates it as required to meet the needs of the project, Program Manager, and PFS Review Panel.
Updates to this document are performed in accordance with the MMITSS Configuration Management
Process.
1.1 Project Summary The MMITSS project is part of the Cooperative Transportation System Pooled Fund Study (CTS PFS)
entitled “Program to Support the Development and Deployment of Cooperative Transportation System
Applications.” The CTS PFS was created by a group of state and local transportation agencies and the
Federal Highway Administration (FHWA), with the Virginia Department of Transportation (VDOT) serving
as the lead agency. The University of Virginia’s Center for Transportation Studies is supporting VDOT on
the Pooled Fund Study, serving as the technical and administrative lead for the effort. The focus of the
CTS PFS is on prototyping and testing practical infrastructure oriented applications that lead to
deployment rather than developing theoretical applications. More information about the CTS PFS and the
scope of the project can be found at http://cts.virginia.edu/CTSPFS_1.html.
The United States Department of Transportation (US DOT) has recently identified ten high-priority
mobility applications under the Dynamic Mobility Applications (DMA) program for the connected vehicle
environment where high-fidelity data from vehicles, infrastructure, pedestrians, etc. can be shared
through wireless communications (Further information is available at
http://www.its.dot.gov/dma/index.htm). Among the ten identified high-priority applications, three
applications (Intelligent Traffic Signal System, Transit Signal Priority, and Mobile Accessible Pedestrian
Signal System) are related to transformative traffic signal operations. Since a major focus of the CTS
PFS members – who are the actual owners and operators of transportation infrastructure – lies in traffic
signal related applications, the CTS PFS team is leading the project described in this RFP, entitled “Multi-
Modal Intelligent Traffic Signal System” in cooperation with US DOT’s Dynamic Mobility Applications
Program.
Multi-Modal Intelligent Traffic Signal System
This project aims to conduct the foundational analysis and design necessary to prepare for the
development and field testing or demonstration of a Multi-Modal Intelligent Traffic Signal System, which is
Pooled Fund Project - PMP
Pooled Fund Project - PMP UA_PFP_PMP
Page 5 of 28
defined as a comprehensive traffic signal system taking advantage of the connected vehicle environment
for multiple transportation modes, including general passenger vehicles, transit, emergency vehicles,
freight vehicles, and pedestrians. The Multi-Modal Intelligent Traffic Signal System incorporates, at a
minimum, the arterial traffic signal applications identified through the DMA template process of US DOT.
Brief descriptions of these applications, modified from the DMA applications description document, are
provided below:
1. Intelligent Traffic Signal System (ISIG):
This application will make use of high-fidelity data collected from vehicles through wireless
communications to accurately predict lane-specific platoon flow, platoon size, and other driving
characteristics. The proposed application with high-fidelity data, in real-time has the potential to
transform how traffic signal systems are designed, implemented and monitored. Developing new systems
that use data via V2V and V2I wireless communications to control signals in order to maximize flows in
real-time can significantly improve traffic conditions. The ISIG application also plays the role of an over-
arching system optimization application, accommodating transit or freight signal priority, preemption, and
pedestrian movements to maximize overall arterial network performance. In addition, the interface (or
data flow) between arterial signals and ramp meters (essentially traffic signals installed on freeway
onramps) must also be considered (note, however, that the development of ramp metering algorithms —
the metering rates to optimize freeway flow — is not included in the scope of this application).
2. Transit Signal Priority (TSP):
Transit Signal Priority strategy is suggested to allow transit agencies to manage bus service better by
adding the capability to grant buses priority based on a number of different factors. The proposed
application provides a mechanism by which transit vehicles equipped with on-board equipment can
communicate information such as passenger count data, service type, scheduled and actual arrival time
and heading information to roadside equipment via DSRC.
3. Mobile Accessible Pedestrian Signal System (PED-SIG):
This application will integrate information from roadside or intersection sensors and new forms of data
from wirelessly connected pedestrian-carried mobile devices, and then wirelessly communicate with the
traffic signal controller to obtain real-time Signal Phase and Timing (SPaT) information, which will then be
used to inform the visually impaired pedestrian as to when to cross and how to remain aligned with the
crosswalk. The application will allow an “automated pedestrian call” to be sent to the traffic controller
from the smart phone of registered blind users after confirming the direction and orientation of the
roadway that the pedestrian is intending to cross. To the extent that these new data are useful, this
application may also support the accommodation of safe and efficient pedestrian movement of a more
general nature.
4. Emergency Vehicle Preemption (PREEMPT):
The proposed application will be functionally similar to current signal preemption systems but may be
viewed as a replacement of optical, 900 MHz, and other technologies used for signal preemption with
integrated V2V and V2I communication systems. The application would adjust preemption and signal
recovery cycles to account for non-linear effects of multiple emergency responses through the same
traffic network.
5. Freight Signal Priority (FSP):
Pooled Fund Project - PMP
Pooled Fund Project - PMP UA_PFP_PMP
Page 6 of 28
Freight Signal Priority concept provides signal priority along an arterial corridor near a freight facility
based upon current and projected freight movements into and out of the freight facility. The goal of freight
signal priority application is to reduce delays and increase travel time reliability for freight traffic, and
enhance safety at intersections around the freight facility.
1.1.1 Purpose Scope and Objectives The final goal of the CTS PFS team is to field-test or demonstrate a Multi-Modal Intelligent Traffic Signal
System. This project, constructed as a first step, will develop a concept of operations (ConOps) and
system requirements specification (SyRS) in general and include a conceptual system design and a test
plan for the selected locations.
The objectives of this project are:
• To develop a concept of operations, systems requirements specification, and system design for a
comprehensive traffic signal system that services multiple modes of transportation, including
general vehicles, transit, emergency vehicles, freight fleets and pedestrians; and
• To prepare for field testing or demonstration of the developed Multi-Modal Intelligent Traffic
Signal System.
1.1.2 Assumptions and Constraints This project is being conducted under a larger umbrella Pooled Fund program titled “Program to Support
the Development and Deployment of Cooperative Transportation Systems Applications”. As such, the
system under consideration will operate within the cooperative “Connected Vehicle System” where
vehicles communicate to an equipped infrastructure. The communications will include, but are not limited
to 5.9 GHz DSRC and will use messages consistent with the SAE J2735 standards being developed as
well as US DOT efforts for SPaT and MAP messages and NTCIP standards for traffic management and
control.
1.1.3 Project Deliverables The deliverables created in this project will support the full development of a deployable Multi-Modal
Intelligent Traffic Signal System. The deliverables are summarized in Table 1 below. All deliverables in
this project are documents (reports) and will be submitted in PDF format by email to the Project Manager.
Table 1 – List of Deliverables and Due Dates
TASK NAME AND
DELIVERABLE
DUE DATE Calendar Date
(Assuming a March 1,
2012 Start Date)
Task 1 – Project Management and Systems Engineering Management
Briefing Materials, Kick-Off Meeting Two weeks from Contract Award March 15, 2012
Draft PMP, Final PMP Four weeks from Contract Award March 29, 2012
Draft Project Schedule, Final Project Schedule Four weeks from Contract Award March 29, 2012
Quarterly Update Conference Calls and Minutes Every quarter from Contract Award June 1, September 1,
December 1
Monthly Progress Reports Every month from Contract Award 1st Day of Month
Team Meetings Summaries Within 1 week after each meeting -
Briefing Materials, Closeout Meeting 52 weeks from Contract Award February 28, 2013
Pooled Fund Project - PMP
Pooled Fund Project - PMP UA_PFP_PMP
Page 7 of 28
Task 2 – Develop Concept of Operations (ConOps)
Subtask 2.1 – Assessment of Relevant Prior and Ongoing Research
Outline of Draft Report on Assessment of
Relevant Research
Four weeks from Contract Award March 29, 2012
Draft Report on Assessment of Relevant
Research
Six weeks from Contract Award April 12, 2012
Briefing on Assessment of Relevant Research Six weeks from Contract Award April 12, 2012
Final Report on Assessment of Relevant
Research
Eight weeks from Contract Award April 26, 2012
Subtask 2.2 – Solicit Stakeholder Input
Presentation Materials for Stakeholder Meetings Eight weeks from Contract Award April 26, 2012
Technical Memorandum from Each Meeting 10 weeks from Contract Award May 10, 2012
Draft Report on Stakeholder Input 12 weeks from Contract Award May 24, 2012
Final Report on Stakeholder Input 14 weeks from Contract Award June 7, 2012
Subtask 2.3 – Develop Concept of Operations (ConOps)
Draft Concept of Operations (ConOps) 16 weeks from Contract Award June 21, 2012
Revised Concept of Operations (ConOps) 18 weeks from Contract Award July 5, 2012
Walkthrough Workbooks for Walkthrough Review 19 weeks from Contract Award July 12, 2012
Walkthrough Comment Resolution Report 22 weeks from Contract Award August 2, 2012
Final Concept of Operations (ConOps) 24 weeks from Contract Award August 16, 2012
Task 3 – Develop System Requirements
Draft System Requirements 28 weeks from Contract Award September 13, 2012
Revised System Requirements 32 weeks from Contract Award October 11, 2012
Walkthrough Workbooks for Walkthrough Review 34 weeks from Contract Award October 25, 2012
Walkthrough Comment Resolution Report 38 weeks from Contract Award November 22, 2012
Final System Requirements 40 weeks from Contract Award December 6, 2012
Task 4 – Conduct System Design
Draft System Design 44 weeks from Contract Award January 3, 2013
Final System Design 46 weeks from Contract Award January 17, 2013
Task 5 – Prepare a Deployment and Field
Test Plan
Draft Deployment and Field Test Plan 50 weeks from Contract Award February 14, 2013
Final Deployment and Field Test Plan 52 weeks from Contract Award February 28, 2013
1.1.4 Master Schedule The Master Project Schedule is shown in Figure 1 below. The schedule will be updated monthly to track
task progress, for cost estimation monitoring, and to reflect and changes in start/end dates. An expanded
version of the Master Project Schedule can be found in Appendix C.
Pooled Fund Project - PMP
Pooled Fund Project - PMP UA_PFP_PMP
Page 8 of 28
Figure 1 – Master Project Schedule Roll-up
1.2 DOCUMENT STRUCTURE The Project Management Plan is organized into the following sections and appendices:
Section 1, Project Overview. This section provides an overview of the scope and objectives of the
project, the project’s assumptions and constraints, reference to the project deliverables, schedule
and budget, and a description of the evolution of the plan.
Section 2, References. This section provides a list of all documents, policies, templates,
processes, and other sources of information referenced in the plan.
Section 3, Project Organization. This section identifies interfaces to organizational entities
external to the project, the project’s internal organizational structure, and defines roles and
responsibilities for the project.
Section 4, Project Management Process. This section describes the management, technical, and
supporting processes.
Section 5, Supporting Processes. This section describes the processes used to support the
project including configuration management.
Appendices: Task Descriptions, Acronyms, and Project Plan
Pooled Fund Project - PMP
Pooled Fund Project - PMP UA_PFP_PMP
Page 9 of 28
2 REFERENCES
2.1 STANDARDS AND DOCUMENTS The standards and documents listed below are referenced in this document:
A Description of the SSC San Diego Standard Process Assets (SPA), PR-OPD-35, SSC San
Diego
Institute of Electrical and Electronics Engineers (IEEE) Standard for Software Project
Management Plans, IEEE Standard 1058-1998, IEEE, December 1998
Project Management Plan Template, TM-PP-01, SSC San Diego
2.2 DEVIATIONS AND WAIVERS Deviations and/or waivers from the project’s documented standard processes or procedures will be
defined in the individual build plans as necessary and approved by agreement between the Project
Manager and the Program Manager.
3 PROJECT ORGANIZATION The project organization is divided into two primary categories: External Interfaces and Internal Structure.
The following sections define these categories, define roles, and identify personnel assigned to the roles.
3.1 EXTERNAL INTERFACES External organizational interfaces and the chain-of-command for the MMITSS Project are defined by the relationships show in Figure 2. The responsibilities of the organizational entities and key positions shown in Figure 2 and are defined in Table 2.
Pooled Fund Project - PMP
Pooled Fund Project - PMP UA_PFP_PMP Page 10 of 28
Figure 2 – External Organization Interfaces
POSITION ROLES/RESPONSIBILITIES
CTS PFS PI
(Brian Smith) Principal Investigator for the Cooperative Transportation
System Fool Fund Study, which is the overall project
tasked to develop infrastructure based connected
vehicle applications
CTS PFS Project Manager
(Hyungjun Park) Responsible for Project Management and
Oversight
Pooled Fund Project - PMP
Pooled Fund Project - PMP UA_PFP_PMP Page 11 of 28
CTS PFS Project Panel
Greg Larson -CalTrans
Faisal Saleem - Maricopa County Arizona)
Ben McKeever (FHWA)
Danielle Deneau (Oakland County Michigan)
Melissa Lance (VDOT)
Hyungjun Park (UVA – Center for Transportation Studies)
Ray Derr (TRB/NCHRP)
Provides direction, review, and input to the Project
Manager and Project Team
Other PFS Members
(TBD)
Other PFS members may be asked to review
documentation and findings.
Project Team – PI
(Larry Head)
Responsible for the management and technical leadership
of the project.
Project Team
(See: Figure 3) Team members are responsible for contribution to
technical execution of the project plan. PI for each Team
organization is responsible for the team members at that
organization.
Table 2 – Programmatic Roles and Responsibilities
3.2 INTERNAL STRUCTURE The Project Team is led by the PI (Dr. Larry Head). Dr. Head will be responsible for leading and directing
all management and technical aspects of this project. He will be assisted in the management of the
budget, cost controls, and human resource management by Joanne Canalli (Senior Business Manager,
Systems and Industrial Engineering Department, College of Engineering, University of Arizona). He will
be assisted in technical management by Ann Wilkey. Ms. Wilkey will provide internal audits for scope,
quality, communications, and risk management.
Project Team members from PATH and the technology partners will be contributors to the task
developments as defined in the scope of work. The PATH Project Team members will be managed by Dr.
Steve Shladover. The functional management organization of the project is shown in Figure 3.
Pooled Fund Project - PMP
Pooled Fund Project - PMP UA_PFP_PMP Page 12 of 28
Research Team PI(Larry Head)
Scope Management
(L. Head)
Cost Management(L. Head)
Quality Management
(L. Head)
Human Resource Management
(L. Head)
Communications Management
(L. Head)
Risk Management(L. Head)
Internal Communications
Audit(Wilkey)
Internal Risk Mgmt. Audit
(Wilkey)
Internal HR Mgmt Audit
(Wilkey)
Internal Quality Audit
(Wilkey)
Internal Cost Audit(Wilkey)
Internal Scope Mgmt. Audit
(Wilkey)
ExternalScope Mgmt. Audit
(Park)
ExternalCost Audit
(Park)
ExternalQuality Audit
(Park)
ExternalHR Mgmt. Audit
(Park)
External Communications
Audit(Park)
ExternalRisk Mgmt. Audit
(Park)
Figure 3 – Functional Management Organization
4 MANAGEMENT PROCESS
4.1 START-UP This project does not require any special training, staffing, or resource allocation in order to begin the
project. The project will start with a Kick-Off meeting. The primary goals of the Kick-off meeting will
include: (1) introduction of the PFS Team, (2) introduction of PFP MMTISS Team, (3) Overview of the
Pooled Fund Study Objective, (4) Project Objectives, (5) Overview of Draft Project Management Plan,
and (6) Question and comment segment.
4.2 BUDGET AND COST CONTROL The Principal Investigator (PI) is responsible for ensuring the project costs meet the planned budget.
Cost management establishes mechanisms, processes, and or procedures to measure, monitor, and
control the cost of work completed, comparison of planned-to-budgeted cost, and corrective actions when
controls are out of bounds. The Pooled Fund Project (PFP) will use an updated version of the PFP
Project Plan (MPP) as the baseline of labor estimates at a tasking level. The cost estimates for travel and
material/supply costs are defined in the original proposal. On a monthly basis the PFP PI will compare
the MPP baseline with the actual task progress to determine if task costs are within bounds. Also on a
monthly basis, the costs associated with travel and materials/supplies will be compared with the budgeted
amounts in the proposal. Deviations greater than 10% will be considered “out of bounds” and detailed in
the quarterly report.
In all cases, the PI maintains total control over the resolution of any problems that are identified. If either
the problem or the corrective action taken constitutes a program risk, the risk is quantified, minimized as
much as possible, and added to the risk management database along with its contingency actions.
Pooled Fund Project - PMP
Pooled Fund Project - PMP UA_PFP_PMP Page 13 of 28
4.3 QUALITY CONTROL The PFP quality management approach is defined to ensure that the project objectives are attained in a
timely and useful manner: (1) Concept of Operations, CONOPS, (2) System Requirements, (3) System
Design, and (4) System Test Plan.
Six metrics have been defined to ensure these Project Objectives are achieved:
Tracking and Oversight – The tracking and oversight metrics are defined more specifically in the Scope
Management and Cost Management sections. The PFP quality management approach defines a
quarterly assessment, auditing, and reporting process to ensure that progress on the four project
objectives are occurring within scope and cost bounds.
Briefings, Meetings, and Communications – A structured and planned approach for collaborating and
sharing information is defined as follows:
Internal Team Meetings – Teleconferences are scheduled to occur weekly on Tuesdays from 4:30-
5:30PM PST. Until a WebEx connection is defined, a dial-in service has been defined: Call in Number
916-209-4534 Pin: 6389144. Materials reviewed in the weekly teleconferences will be made available
through the PFP CM system (SVN) repository prior to the meeting. In addition, draft meeting minutes will
be posted in the repository within three days and quality reviewed and approved meeting minutes will be
posted within seven days.
Briefings – Quarterly briefings will be offered to the PFP sponsor and/or PFS Panel. In addition to
technical and design information for the PFP project objectives, these briefings will include updates on the
quarterly audits defined throughout the PMP. Materials reviewed in the briefings will be made available
through the PFP SVN repository and email attachment for those participants without access to the PFP
SVN repository.
Communications – As appropriate and needed, the PFP PI will offer communications via telephone,
email, and physical mail. The PFP SVN repository will serve as the primary source of technical
information, since CM processes have been defined to ensure the timeliness and integrity of the content.
Meeting minutes for PFP project teleconferences and meetings will be available through the PFP SVN
repository and useful for assessing recent and historical progress on tasking and technical pursuits.
Documentation Quality – As part of the Communications Management approach, feedback on
documentation contents is solicited and incorporated using the CM processes defined for this project.
The CM processes and use of the PFP SVN repository ensure that all internal and external PFP
participants have access to the most current version of a document as well as useful historical
information. In addition to accessibility and integrated feedback, the originating author of a document has
change control authority to ensure that suggested changes are incorporated properly. In most instances,
this change control is achieved through Microsoft Word “Track Changes” functionality.
4.4 RISK MANAGEMENT The strategy to manage project risk is to continually monitor and track potential project risk. The general
approach to risk management is shown in . Table 3 is the risk tracking matrix that will be used to identify,
quantify, manage, and monitor project and task risks. After identification of a risk, the risk is managed by
a defined process detailed in the following steps. The risk is assigned an identifier (ID) and a Risk
Owner. The task is entered into the Risk Tracking Matrix and summarized using the Risk Statement. The
potential impact to the project (Impact Statement) will be provided to allow reviewers to understand the
risk. If the risk is associated directly with a project task, a reference to the WBS shall be included. The
Pooled Fund Project - PMP
Pooled Fund Project - PMP UA_PFP_PMP Page 14 of 28
Likelihood and Severity will be estimated (High (1.0-0.7; Red), Medium (0.69-0.20; Yellow), or Low (0.19-
0.01; Green)) and a Risk Score = Likelihood * Severity will be used to quantify the risk assessment.
Risks can be identified by any member of the project team, the UVA project management team, and the
PFP panel members. Risks shall be reviewed in the weekly project teleconferences and included in the
monthly progress reports. Any risk that as a high Risk Score (greater than 0.7) shall be reported to the
CTS PFP PM immediately. Risks shall be tracked and managed until the management team is satisfied
that risk has been mitigated adequately. Once a risk has been addressed, it shall remain in the risk
tracking matrix throughout the duration of the project, but it will be labeled “Closed” in the Risk Score
column (Blue).
Figure 4 – Risk Management Process
1. PlanningEstablishment of the risk
management program plan and
assignment of responsibilities
2. Risk IdentificationAnticipation, recognition &
prioritization of potential
adverse outcomes and the
associated root causes
3. Risk AssessmentCharacterization of the
Magnitude and likelihood of
risks, to the depth warranted
4. Risk AnalysisEvaluation of costs and benefits
associated with available risk
mitigation options, if needed
5. Risk HandlingProgram intervention to reduce
or eliminate risks, if justified,
and tracking to assure success
Program
Management &
Systems
Engineering
Requirements, Functions& System Elements
Modifications to
program plan
Table 3 – Risk Tracking Matrix
4.5 HUMAN RESOURCE MANAGEMENT The roles and responsibilities of the project management team, project panel, and project technical team
are defined in Table 4 below.
Task Assignment\ Team Member
Task 1: Project and Systems Engineering Management
Task 2: Develop Concept of Operations (CONOPS)
Task 3: Develop System Requirements (SyRS)
Task 4: Conduct System Design
Task 5: Prepare a Deployment and Field Test Plan
Project Management Team
Brian Smith, UVA Review, Approve
Review, Approve
Review, Approve
Review, Approve
Review, Approve
Hyungjun Park, UVA Review, Approve
Review, Approve
Review, Approve
Review, Approve
Review, Approve
Melissa Vance, VDOT Review, Approve
Review, Approve
Review, Approve
Review, Approve
Review, Approve
Project Panel
Greg Larson (CalTrans) Review Review Review Review Review
Faisal Saleem (Maricopa County in Arizona)
Review Review Review Review Review
Ben McKeever (FHWA) Review Review Review Review Review
Danielle Deneau (Oakland County in Michigan)
Review Review Review Review Review
Ray Derr (TRB/NCHRP) Review Review Review Review Review
Project Team
Larry Head, UA Lead Input
Lead Input
Lead Input
Lead Input
Lead Input
Ann Wilkey, UA Support Input
Support Input
Support Input
Support Input
Support Input
GRA, UA Support Support Support Support
Steve Shladover, PATH Input Input Input Input Input
Wei Bin Zhang, PATH Input Input Input Input
Liping Zhang, PATH Input Input Input Input
Kun Zhou, PATH Input Input Input Input
Gary Duncan, Econolite Input Input Input
Eric Raamot, Econolite Input Input Input
Ramesh Siripurapu, Savari
Input Input Input
David Kelley, SCSC Input Input Input
Justin McNew, Kapsch Input Input Input
Mike Siebert, Volvo Technologies
Input Input Input
Table 4 – Project Roles and Responsibilities
Pooled Fund Project - PMP
Pooled Fund Project - PMP UA_PFP_PMP Page 17 of 28
4.6 SCOPE MANAGEMENT The project tasks are summarized in Appendix A. The scope will be managed according to the defined
project tasks to ensure successful delivery of the Concept of Operations, Requirements, System Design,
and Field Implementation and Test Plans.
5 SUPPORTING PROCESSES
5.1 COMMUNICATIONS MANAGEMENT This section reviews the integrated processes, provisions, and plans, detailed in other sections, that
ensure timely generation, collection, distribution, storage, retrieval, and ultimate disposition of key project
information. The Principal Investigator (PI) and Systems Engineer responsible for the activities and
products provided under Communications Management.
The PI is the primary point of contact (POC) for all communications between the Project Manager, CTS
PFS Project Panel, and Project Team. In the event of a planned or unplanned absence, the PI will define
an authorized delegate to serve as a POC. Such delegation will be authorized through a memorandum of
record detailing the delegate, delegated scope of authority, and specific period of delegation.
Working in collaboration with the Project Team, the PI shall be responsible for organizing team meetings
and critical communications in support of the ConOps Development members and stakeholders. The PI
will utilize the most appropriate communication forum, such as email, teleconferences, and written
documentation, to communicate with internal and external project members (See: Figure 2 and Figure 3)
on the organization and scheduling of project activities such as Stakeholder Meetings, Walkthrough
Reviews, Requirements Development, and Test, Integration, and Evaluation Plans.
Regular and effective communications with the Project Team are critical to the success of the project. As
such, weekly teleconferences are scheduled for Tuesday afternoons from 4:30-5:30PM PST. Until a
WebEx connection is defined, a dial-in service has been defined: Call in Number 916-209-4534 Pin:
6389144. Materials reviewed in the weekly teleconferences will be made available through the PFP CM
system (SVN) repository prior to the meeting. In addition, the SE will compile and post draft meeting
minutes in the repository within three days. The Quality Management and Configuration Management
plans provide provisions for reviewing the minutes, removing the “draft” marking, naming the documents
and electronic files, and posting the resulting materials in the project SVN repository.
The communication activities are summarized in Table 5. Configuration Management and Quality
Management sections provide information on details supporting written communications, document
identification, revision control, and storage. Refer to these sections for more specific information.
Communication Item/ Activity
Purpose Frequency Intended Audience
Monthly Progress Reports
Provide monthly status on project tasks, budgets, action items, and risk assessments.
Monthly Program Manager, Sponsoring Organization, Project Team
Update Conference Calls
Provide synopsis of project task progress, budgetary status, action item status, and risk assessments and solicit constructive feedback on project activities.
Quarterly Program Manager, Sponsoring Organization
Pooled Fund Project - PMP
Pooled Fund Project - PMP UA_PFP_PMP Page 18 of 28
Communication Item/ Activity
Purpose Frequency Intended Audience
Project Team Meetings Exchange and monitor task progress, identify and quantify project risks, and modify tasking responsibilities and details as appropriate.
Weekly Internal Project Team Members
Project Management Plan
Provide guidance on the management of the Pooled Fund: Multi-Modal Intelligent Traffic Signal System (MMITSS) project
Draft and Final PMP
Program Manager, Project Panel, Project Team
Stakeholder Meetings Solicit, gather, synthesize, and document input from identified stakeholders regarding goals, needs, and system performance measures.
Two Per Project Schedule
Program Manager, Project Panel, Stakeholder
Concept of Operations The ConOps provides a stakeholder-influenced vision and roadmap for the development, deployment, operation and maintenance of future Multi-Modal Intelligent Traffic Signal Systems.
Per Project Schedule
Program Manager, Project Panel, Stakeholder, Project Team
SyRS The System Requirements form the basis for the design, implementation, testing, and acceptance of any system.
Per Project Schedule
Program Manager, Project Panel, Project Team
Table 5 – Communication Activities
5.2 CONFIGURATION MANAGEMENT The evaluated metrics under CM include the proper work product identification, change control, records
management, and change reports. Identification of work products is achieved through the establishment,
adoption, and use of naming conventions. Change control of work products will be achieved through the
process of initiating track changes described previously under Documentation Quality.
Work Product Identification: Unless stated otherwise, all electronic work products will be available through
the PFP SVN repository.
CM-Controlled Item Filename
Project Plan Source: PFP_ProjectPlan.mpp Distribution: PFP_ProjectPlan.pdf
Project Management Plan (PMP) Source: PFP_PMP.docx Distribution: PFP_PMP.pdf
Monthly Progress Reports Source: PFP_MonthlyReport_mmyy.docx Distribution: PFP_MonthlyReport_mmyy.pdf
Quarterly Briefings Source: PFP_QtrBriefing_ddmmyy.pptx Distribution: PFP_QtrBriefing_ddmmyy.pdf
Quarterly Briefings Meeting Minutes Source: PFP_QtrBriefingMinutes_ddmmyy.docx Distribution: PFP_QtrBriefingMinutes_ddmmyy.pdf
Concept of Operations Draft Source: PFP_CONOPSDraft.docx Draft Distribution: PFP_CONOPSDraft.pdf Final Source: PFP_CONOPSFinal.docx Final Distribution: PFP_CONOPSFinal.pdf
Systems Requirements Document Source: DOORS Secondary Source: PFP_SRD.docx (DOORS export) Distribution: PFP_SRD.pdf
System Design Description Source: PFP_SDD.docx
Pooled Fund Project - PMP
Pooled Fund Project - PMP UA_PFP_PMP Page 19 of 28
CM-Controlled Item Filename
Distribution: PFP_SDD.pdf
System Test Plan Source: PFP_STP.docx (PFP_STPMatrix.xlsx) Distribution: PFP_STP.pdf, PFP_STPMatrix.pdf
Teleconference Meeting Minutes Source: PFP_Telecon_ddmmyy.docx Distribution: PFP_Telecon_ddmmyy.pdf
Table 6 – CM File Naming Conventions
Pooled Fund Project - PMP
Pooled Fund Project - PMP UA_PFP_PMP Page 20 of 28
6 APPENDICES
APPENDIX A: TASK DESCRIPTIONS Deliverables:
• Task 1: Project Plan, 3/29/2012
• Task 2: Concept of Operations, 8/16/2012
• Task 3: System Requirements Document, 12/6/2012
• Task 4: System Design Document, 1/17/2013
• Task 5: Deployment and Fiend Test Plan, 2/28/2013
Task 1 – Project and Systems Engineering Management
The purpose of this task is to provide project management support for all tasks described in this scope of
services. The Monthly Progress Reports shall contain the following sections: 1) Executive Summary
highlighting the overall project status and comments summarizing how and issues are being addressed,
2) Controls section highlighting any significant issues and the associated risk analysis, 3) Budget
Summary, 4) Status of Scheduled Milestones/Deliverables, and 5) Accomplishments and Plans.
Deliverable: Project Management Plan
Deliverable: Monthly Progress Reports and Quarterly Update Conference Calls
Task 2 – Develop Concept of Operations (ConOps)
A Concept of Operations (ConOps) captures the stakeholders views of the system being developed and
is written so that it can be easily reviewed by the various stakeholder communities. The Concept of
Operations will provide a vision and a roadmap for the development, deployment, operation and
maintenance of future Multi-Modal Intelligent Traffic Signal Systems. It will identify clear goals for a Multi-
Modal Intelligent Traffic Signal System to achieve to support a transformation of traffic signal control from
today’s technology into a safer and more efficient system for the future. It will identify opportunities for
early deployment and adoption as an enabling technology that will support wide scale technology
adoption.
Deliverable: Report on Assessment of Relevant Prior and Ongoing Research
Deliverable: Stakeholder Workshop Report
Deliverable: Concept of Operations Document
Task 2.1 – Assessment of Relevant Prior and Ongoing Research
The Research Team will prepare a Report on Assessment of Relevant Prior and Ongoing Research that
will identify the literature and project sources. This report will be structured to include traffic control
algorithms and strategies, standards and technology developments, past and on-going projects, US DOT
and AASHTO strategic plans, and other sources of Connected Vehicle activities that could influence the
development of a Multi-Modal Intelligent Traffic Management System.
Task 2.2 – Solicit Stakeholder Input on Transformative Goals, Performance Measures and User
Needs
Pooled Fund Project - PMP
Pooled Fund Project - PMP UA_PFP_PMP Page 21 of 28
The Research Team will conduct two (2) stakeholder meetings, plus informal solicitations from relevant
stakeholders, to identify transformative benefits for the application, corresponding performance
measures, and user needs for the application. The first stakeholder meeting will include key stakeholders
representing different classes of users, owners, and operators. The second stakeholder meeting will be
conducted as a webinar where a larger and broader group of participants can be included. The Research
Team will develop a report summarizing the findings of the workshop.
Subtask 2.3 – Develop Concept of Operations (ConOps)
The Assessment of Relevant Prior Research, Stakeholder Inputs and Research Team vision will be used
to develop the Concept of Operations. The Concept of Operations document is intended to capture the
stakeholders’ views and is to be easily readable by the stakeholder community. The Research Team will
follow the IEEE Standard 1362-1998 format. A Concept of Operations Walkthrough will be conducted to
review the document with critical stakeholders.
Task 3 – Develop System Requirements (SyRS)
The System Requirements Specification forms the basis for the design, implementation, testing, and
acceptance of any system. Each requirement places a cost on the system, hence it is important that a
minimum set of requirements be defined and that each requirement be verifiable and traceable to its
origin, such as to a need identified in the Concept of Operations. Requirements can be related to system
functionality, the technology available to build the system, functional performance, acquisition and
operating cost, the system-ilities that include reliability, maintainability, availability, and trade-offs between
performance and cost/utilization. Requirements must also be testable so that the developed system can
be verified to satisfy the requirements. Requirements are based on sound understanding and analysis of
the problem.
The will develop a set of system requirements based on the Concept of Operations. The requirements will
be developed following the guidance in IEEE Standard 1233-1998, IEEE Guide for Developing System
Requirements Specifications and using the DOORS requirements management tool that supports
requirements tracking and management. The Research Team will prepare Walkthrough Workbooks and
will conduct a Requirements Review Meeting. Based on the comments received in the Requirements
Review the System Requirements will be revised and Comment Resolution Report will be developed and
delivered.
Deliverable: System Requirements Document
Task 4 – Conduct System Design
Based on the Concept of Operations and the System Requirements Specification, high-level system
designs will be developed based on deployment on the existing Arizona and California test beds. The
high level designs will be represented considering several stakeholder views. These views include the
users (multi modal travelers), operators, maintainers, and managers (owners). Since each of the field
sites is currently based on different technology, the high level design will seek to identify common and
custom design features required for the respective implementation.
Each design will include a detailed deployment specification that includes hardware components,
software components, software artifacts (e.g. J2735 MAPs, traffic signal controller databases) interfaces,
messages, backhaul communications, and power for the respective network topology. Each design will
Pooled Fund Project - PMP
Pooled Fund Project - PMP UA_PFP_PMP Page 22 of 28
include a requirements allocation view to ensure that each design meets the requirements. Each design
will be evaluated with respect to the requirements.
Deliverable: System Design Document
Task 5 – Prepare a Deployment and Field Test Plan
The Research Team will develop Field Deployment and Test Plans for both the California and Arizona
test networks. Each Field Deployment Plan will include a schedule and cost estimate and identification of
any specific issues that need to be addressed for the respective network. A common Test Plan will be
developed for both test beds. It is possible that one or more of the Dynamic Mobility Applications (e.g.
Intelligent Traffic Signal System, Transit Signal Priority, Mobile Accessible Pedestrian Signal System,
Emergency Vehicle Preemption, and Freight Signal Priority) might not be operational in one of the test
networks, but an important goal of this project is to demonstrate the ability to provide the same
functionality on different implementations and networks.
Deliverable: Deployment and Field Test Plan
Pooled Fund Project - PMP
Pooled Fund Project - PMP UA_PFP_PMP Page 23 of 28
APPENDIX B: ACRONYMS AASHTO American Association of State Highway and Transportation Officials CM Configuration Management CoE College of Engineering ConOps Concept of Operations CTS Center for Transportation Studies (University of Virginia) DMA Dynamic Mobility Applications CTS PFS Cooperative Transportation Systems – Pooled Fund Study DOORS Dynamic Object Oriented Requirement System DOT Department of Transportation DSRC Dedicated Short Range Communication FHWA Federal Highway Administration FSP Freight Signal Priority GHz Gigahertz (1 x 10
9 Hz)
GPS Global Positioning System HR Human Resources IEEE Institute of Electrical and Electronic Engineers GRA Graduate Research Assistant/Associate ID Identifier/Identification ISIG Intelligent Traffic Signal System ISO International Organization for Standardization ITS Intelligent Transportation Systems MMITSS Multi-Modal Intelligent Traffic Signal System MPP Microsoft Project Plan NCHRP National Cooperative Highway Research Program NTCIP National Transportation Communications for ITS PATH Partners for Advanced Transportation Technology (PATH) is administered by the Institute of
Transportation Studies (ITS) at the University of California, Berkeley
PDF Portable Document Format PFP Pooled Fund Project PFS Pooled Fund Study PI Principal Investigator PM Program Manager PMP Project Management Plan PPT PowerPoint PST Pacific Standard Time RFP Request for Proposal SAE Society of Automotive Engineers SCSC Subcarrier Systems Corporation SDD System Description Document SIE Systems and Industrial Engineering SPA Standard Process Assets SPaT Signal Phase and Timing SRD System Requirements Document SSC Space and Naval Warfare Systems Center STP System Test Plan SVN Subversion (Version Control System) TRB Transportation Research Board TSP Transit Signal Priority UA University of Arizona US United States V2I Vehicle to Infrastructure V2V Vehicle to Vehicle UVa University of Virginia VDOT Virginia Department of Transportation WBS Work Breakdown Structure
APPENDIX C: PROJECT PLAN
Pooled Fund Project - PMP
Pooled Fund Project - PMP UA_PFP_PMP Page 25 of 28
Pooled Fund Project - PMP
Pooled Fund Project - PMP UA_PFP_PMP Page 26 of 28
Pooled Fund Project - PMP
Pooled Fund Project - PMP UA_PFP_PMP Page 27 of 28
Pooled Fund Project - PMP
Pooled Fund Project - PMP UA_PFP_PMP Page 28 of 28