7/31/2019 Mechanical Work
1/4
NO Activity Location Level Supervisor Contractor Completed% Remaining % Completion Remarks
1 PPRC + UPVC Piping B- Mazznine B-M M.Bilal Grace Engineers 100 0 Not Provided Completed
2 Acessories Installation B- Mazznine B-M M.Bilal Grace Engineers 60 40 Not ProvidedIndian WC Flush Tank, Floor Drains, Padestle type
wash basin still not received
3 PPRC + UPVC Piping B-1 B-1 M.Bilal Grace Engineers 80 20 Not Provided Pipe & wash room Accessories awaited
4 Installation of pumps Plant Room B-1 B-1 Yousuf Ali Mecatech 0 100 June 15 2012 Subjected of completion of foundations
5 Installation of chillers Plant Room B-1 B-1 Yousuf Ali Mecatech 0 100 June 23 2012 Subjected to arrival of chillers
6 Installation of piping Plant Room B-1 B-1 Yousuf Ali Mecatech 0 100 June 30 2012 Subjected to route cleaning
7Installation of
Electrical panelPlant Room B-1 B-1 By Electrical Dept. Mecatech 0 100 June 23 2012
8Electrical & control
workPlant Room B-1 B-1 By Electrical Dept. Mecatech 0 100 June 30 2012
9Testing &
commissioningPlant Room B-1 B-1 Awais & Yousuf Mecatech 0 100 July 15 2012 Subjected to availability of gas and power
10 PPRC + UPVC Piping B-2 B-2 M.Bilal Grace Engineers 80 20 Not Provided Main line installation required
11 Installation Of Pumps B-3 B-3 M.Bilal &Yousuf Ali Technofire/ GraceEngineers
0 100 Not Provided Material procurment required
12Installation Of main
lineB-3 B-3 Arshad Ahsan Grace Engineers 0 100 Not Provided Material procurment required
13 Cleaning of B-3 Lines B-3 B-3 M.Ayaz 0 100 Not Provided Contractor required for work
14 Pipe riser connection G.F Yousuf AliMecatech
40 60 May 31 2012 Work in progress
15 Testing of FCUs G.F Yousuf AliMecatech
0 100 June 15 2012 Subjected to Provision of service doors in ceiling
16Electrical & ControlConnection of FCUS
G.F Yousuf AliMecatech
0 100 June 15 2012 Subjected to Provision of service doors in ceiling
17Installation of
multisplit units( LiftLobby)
G.F Yousuf AliMecatech
0 100 June 30 2012 Not yet started
18Testing &
CommissioningG.F Yousuf Ali
Mecatech0 100 June 30 2012
Subjected to arrival of chillers & installation of Cooling Towers
19 Duct Risers G.F Yousuf Ali ATS 20 80 Not Provided ATS has not provided any data yet20 Grills & Diffusers G.F Yousuf Ali ATS 0 100 Not Provided ATS has not provided any data yet
21FCU Connections of
ducts G.F Yousuf Ali ATS 100 0 Not Provided Completed
22Duct in common
areasG.F
Yousuf Ali ATS100 0 Not Provided Completed
23 Installation of pipe G.F Arshad Ahsan Mecatech 100 0 Not Provided Completed
Status Of Mechanical WorkThe CENTAURUS Shopping Mall
7/31/2019 Mechanical Work
2/4
NO Activity Location Level Supervisor Contractor Completed% Remaining % Completion Remarks
24Installation of
SprinklersG.F
Arshad Ahsan Technofire60 40 Not Provided Work in process
25 Installation of HRC G.F Arshad Ahsan Technofire 0 100 Not Provided Material Awaited26
Installation of Breeching inlet
G.FArshad Ahsan Technofire
0 100 Not Provided Material Awaited
27 Installation of Valves G.FArshad Ahsan Technofire
0 100 Not Provided Material Awaited
28 PPRC + UPVC Piping G.FM.Bilal Grace Engineers
100 0 Not Provided Completed
29 Acessories Installation G.FM.Bilal Grace Engineers
85 15 Not ProvidedIndian WC Flush Tank, Floor Drains, Padestle type
wash basin still not received
30Installation of cooling
TowersG.F
Yousuf Ali & M.Bilal Mecatech20 80 June 15 2012 Subjected to dismentling of scaff-folding
31
32 Pipe riser connection M-1Yousuf Ali Mechatech
40 60 May 31 2012 Work in progress
33 Testing of FCUs M-1Yousuf Ali Mechatech
0 100 June 15 2012 Subjected to Provision of service doors in ceiling
34Electrical & ControlConnection of FCUS
M-1Yousuf Ali Mechatech
0 100 June 15 2012 Subjected to Provision of service doors in ceiling
35Testing &
CommissioningM-1
Yousuf Ali Mechatech0 100 June 30 2012
Subjected to arrival of chillers & installation of Cooling Towers
36 Duct Risers M-1 Yousuf Ali ATS 20 80 Not Provided ATS has not provided any date of completion37 Grills & Diffusers M-1 Yousuf Ali ATS 0 100 Not Provided ATS has not provided any date of completion
38FCU Connections of
ductsM-1
Yousuf Ali ATS90 100 Not Provided
FCU connection ic Atriums Still pending due toinsufficient duct material
39Duct in common
areasM-1
Yousuf Ali ATS100 0 Not Provided Completed
40 Installation of pipe M-1 Arshad Ahsan Mechatech 100 0 Not Provided Completed
41Installation of
SprinklersM-1
Arshad Ahsan Technofire 60 40Not Provided
Work in process42 Installation of HRC M-1 Arshad Ahsan Technofire 0 100 Not Provided Material Awaited
43Installation of
Breeching inletM-1
Arshad Ahsan Technofire 0 100Not Provided
Material Awaited
44Installation of Valves
M-1Arshad Ahsan Technofire 0 100
Not ProvidedMaterial Awaited
45PPRC + UPVC Piping
M-1M.Bilal Grace Engineers 100 0
Not Provided
46 Acessories Installation M-1M.Bilal Grace Engineers
80 20 Not ProvidedIndian WC Flush Tank, Floor Drains, Padestle type
wash basin still not received47
48 Pipe riser connection M-2 Yousuf Ali MECATECH 40 60 May 31 2012 Work in progress
49Testing of FCUs
M-2Yousuf Ali MECATECH 0 100 June 15 2012 Subjected to Provision of service doors in ceiling
50Electrical & ControlConnection of FCUS M-2
Yousuf Ali MECATECH0 100 June 15 2012 Subjected to Provision of service doors in ceiling
7/31/2019 Mechanical Work
3/4
NO Activity Location Level Supervisor Contractor Completed% Remaining % Completion Remarks
51Testing &
CommissioningM-2
Yousuf Ali MECATECH0 100 June 30 2012
Subjected to arrival of chillers & installation of Cooling Towers
52 Duct Risers M-2 Yousuf Ali ATS 20 80 Not Provided ATS has not provided any date of completion53 Grills & Diffusers M-2 Yousuf Ali ATS 0 100 Not Provided ATS has not provided any date of completion54 FCU Connections M-2 Yousuf Ali ATS 100 0 Not Provided Completed
55Duct in common
areasM-2
Yousuf Ali ATS100 0 Not Provided Completed
56 Installation of pipe M-2 Arshad Ahsan MECATECH 100 0 Not Provided Completed
57Installation of
SprinklersM-2
Arshad Ahsan Technofire0 100 Not Provided Work in process
58 Installation of HRC M-2 Arshad Ahsan Technofire 0 100 Not Provided Material Awaited
59Installation of
Breeching inletM-2
Arshad Ahsan Technofire0 100 Not Provided Material Awaited
60Installation of Valves
M-2Arshad Ahsan Technofire
0 100 Not Provided Material Awaited
61PPRC + UPVC Piping
M-2M.Bilal Grace Engineers 100 0
Not Provided
62 Acessories Installation M-2M.Bilal Grace Engineers
80 20 Not ProvidedIndian WC Flush Tank, Floor Drains, Padestle type
wash basin still not received63
64Pipe riser connection
M-3Yousuf Ali MECATECH 40 60 May 31 2012 Work in progress
65 Testing of FCUs M-3 Yousuf Ali MECATECH 0 100 June 15 2012 Subjected to Provision of service doors in ceiling
66 Electrical & ControlConnection of FCUS
M-3Yousuf Ali MECATECH 0 100 June 15 2012 Subjected to Provision of service doors in ceiling
67Testing &
CommissioningM-3
Yousuf Ali MECATECH 0 100 June 30 2012Subjected to arrival of chillers & installation of
Cooling Towers68 Duct Risers M-3 Yousuf Ali ATS 20 80 Not Provided ATS has not provided any date of completion69 Grills & Diffusers M-3 Yousuf Ali ATS 0 100 Not Provided ATS has not provided any date of completion70 FCU Connections M-3 Yousuf Ali ATS 10 90 Not Provided Incompleted
71Duct in common
areas M-3 Yousuf Ali ATS 50 50 Not Provided Incompleted72 Installation of pipe M-3 Arshad Ahsan MECATECH 100 0 Not Provided Completed
73Installation of
SprinklersM-3
Arshad Ahsan Technofire 0 100Not Provided
Not yet started74 Installation of HRC M-3 Arshad Ahsan Technofire 0 100 Not Provided Material Awaited
75Installation of
Breeching inletM-3
Arshad Ahsan Technofire 0 100Not Provided
Material Awaited
76Installation of Valves
M-3Arshad Ahsan Technofire 0 100
Not ProvidedMaterial Awaited
77 PPRC + UPVC Piping M-3 M.Bilal Grace Engineers 100 0 Not Provided
78Acessories Installation
M-3M.Bilal Grace Engineers 80 20
Not ProvidedIndian WC Flush Tank, Floor Drains, Padestle type
wash basin still not received79
80 Pipe riser connection M-4Yousuf Ali MECATECH
40 60 May 31 2012 Work in progress
7/31/2019 Mechanical Work
4/4
NO Activity Location Level Supervisor Contractor Completed% Remaining % Completion Remarks
81 Testing of FCUs M-4Yousuf Ali MECATECH
0 100 June 15 2012 Subjected to Provision of service doors in ceiling
82 Electrical & ControlConnection of FCUS
M-4Yousuf Ali MECATECH
0 100 June 15 2012 Subjected to Provision of service doors in ceiling
83Testing &
CommissioningM-4
Yousuf Ali MECATECH0 100 June 30 2012
Subjected to arrival of chillers & installation of Cooling Towers
84 Duct Risers M-4 Yousuf Ali ATS 20 80 Not Provided ATS has not provided any date of completion85 Grills & Diffusers M-4 Yousuf Ali ATS 0 100 Not Provided ATS has not provided any date of completion86 FCU Connections M-4 Yousuf Ali ATS 60 40 Not Provided Testing of FCU connection still pending
87Duct in common
areasM-4
Yousuf Ali ATS60 40 Not Provided Testing and Installation still pending
88 Installation of pipe M-4 Arshad Ahsan MECATECH 100 0 Not Provided Completed
89Installation of
SprinklersM-4
Arshad Ahsan Technofire0 100 Not Provided Not yet started
90 Installation of HRC M-4 Arshad Ahsan Technofire 0 100 Not Provided Material Awaited
91Installation of
Breeching inletM-4
Arshad Ahsan Technofire0 100 Not Provided Material Awaited
92 Installation of Valves M-4Arshad Ahsan Technofire
0 100 Not Provided Material Awaited
93 PPRC + UPVC Piping M-4M.Bilal
Nadeem Akhter &Bro
100 0 Not Provided
94 Acessories Installation M-4 M.BilalNadeem Akhter &Bro 80 20 Not Provided
Indian WC Flush Tank, Floor Drains, Padestle typewash basin still not received
9596 AHU piping M-5 Yousuf Ali MECATECH 0 100 Not Provided Not yet started
97 Control Connections M-5Yousuf Ali MECATECH
0 100 Not Provided Not yet started
98Testing &
CommissioningM-5
Yousuf Ali MECATECH0 100 Not Provided Not yet started
99 Installation of FCUs M-5 Yousuf Ali MECATECH 0 100 Not Provided Not yet started
100Duct Connection of
AHUsM-5
Yousuf Ali ATS0 100 Not Provided Not yet started
101 Duct Risers M-5 Yousuf Ali ATS 0 100 Not Provided Not yet started102 Installation of pipe M-5 Arshad Ahsan MECATECH 100 0 Not Provided Completed
103Installation of
SprinklersM-5
Arshad Ahsan TECHNOFIRE0 100 Not Provided Not yet started
104 Installation of HRC M-5 Arshad Ahsan TECHNOFIRE 0 100 Not Provided Material Awaited
105Installation of
Breeching inletM-5
Arshad Ahsan TECHNOFIRE0 100 Not Provided Material Awaited
106 Installation of Valves M-5Arshad Ahsan TECHNOFIRE
0 100 Not Provided Material Awaited
107 Rain water piping M-5M.Bilal
Nadeem Akhter& Brother
60 40 June 30 2012 Materail arrived late