Street Resurfacing Selected Contractor: Shelly Construction Curb to Curb Resurfacing Resurfacing will take place in phases, three phases in total. Construction will begin: March 23 rd (weather permitting) Madison Avenue Reconstruction
Citation preview
Madison
AvenueReconstructi
onDepartment of Planning and Development
Project Overview
Madison Avenue will be completely resurfaced from
Riverside to West 117th.
The project is being funded through Federal, State and
County funds.
$2.8 million
Cuyahoga County Department of Public Works is overseeing
project
Madison Avenue Reconstruction
Street ResurfacingSelected Contractor:
Shelly Construction
Curb to Curb Resurfacing
Resurfacing will take place in phases, three phases in total.
Construction will begin:March 23rd
(weather permitting)
Madison Avenue Reconstruction
Madison Avenue Reconstruction
Curb to Curb Construction
Madison Avenue Reconstruction
Phase AreaApprox.
Start DateApprox.
Finish Date
Phase 1 Riverside to Mars March 23rd May 6th
Phase 2 Mars to Wyandotte May 6th June 22nd
Phase 3 Wyandotte to W. 117th June 22nd September 4th
Traffic will be maintained in each direction, at all times.
Madison Avenue Reconstruction
Madison Avenue Reconstruction
Traffic LightsThe current traffic lights along Madison will be replaced with new signals and poles.
Concrete work will continue until June as the complete curb and ramp repairs.
Traffic poles are scheduled to be delivered in April
The new light system should be operational in July.
Madison Avenue Reconstruction
2015
J F M A M J J A S O N D
Traffic Signal Installation
Street Resurfacing
Madison
AvenueReconstructi
onDepartment of Planning and Development
Updated Information available at:www.onelakewood.com/Madison