Expanding Tacoma LinkThe 1.6 mile Tacoma Link light rail line currently serves six stations from the Theater District to the Tacoma Dome Station. Trains run every 12 minutes during the day and served nearly a million riders in 2011. Voters in 2008 approved an expansion of Tacoma Link as part of the Sound Transit 2 ballot measure. Sound Transit’s Tacoma Link Expansion Alternatives Analysis project will identify and study alternative travel corridors for expansion of the Tacoma Link light rail system.
Over the next 12 months, Sound Transit in cooperation with the City of Tacoma and Pierce Transit will engage the wider community to help identify a range of alternatives, study these alternatives, and determine a preferred corridor alternative for the expansion. The study will also produce a project financing plan that will identify committed and potential funding sources.
Tacoma Link Expansion Stakeholder Group Final Report 2011From July 2010 through January 2011 Sound Transit, the City of Tacoma and Pierce Transit convened a group of community stakeholders, including neighborhood and business leaders, to begin looking at possible routes and station locations to expand Tacoma Link. This document details the work of the Tacoma Link Expansion stakeholder group and its recommendations on potential corridor alternatives for expanding Tacoma Link. The group’s mission was to provide commentary and feedback on potential corridor alternatives using their expertise as representatives of diverse constituencies. This qualitative, community-focused report should help guide decision-makers during further technical planning.
Para información acerca del proyecto llame al: 1-‐800-‐823-‐9230
1-‐800-‐823-‐9230 1-‐800-‐823-‐9230, чтобы получить
информацию о проекте. 프로젝트에 관한 정보는 다음으로 연락하십시오: 1-‐800-‐823-‐9230
Involving the Tacoma community•Sound Transit is committed to
communicating with Tacoma residents and businesses about the Tacoma Link Expansion and providing you with meaningful opportunities to get involved. Over the next year, you will have opportunities to:
•Receive advance notice about public meetings and opportunities to provide input on the Tacoma Link Expansion project through local newspapers, blogs, project mailings and the project website.
•Attend public meetings to hear project updates, learn how decisions will be made and provide input on the Tacoma Link Expansion.
•Meet Sound Transit staff in your community and talk to us about your questions, comments or concerns.
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
PP
P
P
P
P
P
P
P
P
P
P
P
P
130th120th
Lakewood
Puyallup
Sumner
Federal Way Auburn
Kent
Tukwila
Renton
Issaquah
Tacoma
RedmondKirkland
Bothell
Everett
Seattle Bellevue
Woodinville
Edmonds
Mukilteo
Lynnwood
Tacoma Dome
IssaquahHighlands
Overlake Transit Center
MercerIsland
Rainier
University ofWashington
Canyon Park
Ash Way
South Everett
Eastgate
SeaTac /Airport
DuPont
SODO
Stadium
Pioneer Square
Westlake
University Street
International District/Chinatown & King Street
S 200th
Kent/Des Moines
Totem Lake
SouthSammamish
South Tacoma
Union Station/ S 19thConvention Center/ S 15thCommerce Street/ S 11thTheater District/ S 9th
S 25th
West Seattle
Northgate
TBD
TacomaCommunityCollege
S 272nd/Federal Way
Mountlake Terrace
U District
Roosevelt
Bellevue Transit Center
SouthBellevue
Hospital
First Hill
Capitol Hill
Overlake Village
Shoreline
Burien
To Gig Harbor and Purdy
East Main
Beacon Hill
Mount Baker
Columbia City
Othello
Rainier Beach
Tukwila/International Blvd
Bonney Lake
SE Redmond
Link Light RailCentral Link (SeaTac/Airport–Westlake/Seattle)Tacoma Link (Tacoma Dome–Theater District)Under Construction (Opens 2016)In DesignIn Planning/ Planned
Sounder Commuter RailEverett–Seattle SounderLakewood–Tacoma–Seattle Sounder
ST Express Regional BusExpress Bus ServiceFuture Bus Rapid Transit (BRT)
Supporting InvestmentsPark & Ride – Rail Station or Bus FacilityRail Station, Transit Center or Bus StopImprovementsFirst Hill Streetcar (Opens 2014)HOV/Transit ImprovementsHOV Direct Access Ramp, Freeway Station or Overpass
Ferry Terminal AmtrakSea-Tac Airport
MAP KEY
P
For information in alternative formats, call 1-800-201-4900/ TTY Relay: 711 or email accessibility@soundtransit.org.
AUG 2012
STAY INVOLVED!Find project information, updates and upcoming events on our website. Please visit www.soundtransit.org/TacomaLinkExpansion For additional information about Tacoma Link Expansion or to request a project briefing for your organization, Erin Hunter, South Corridor Outreach Lead, at 206-370-5511 or erin.hunter@soundtransit.org.
Sign up for email updates at www.soundtransit.org/subscribe.
CURRENT AND FUTURE SOUND TRANSIT SERVICE
Sound Transit plans, builds and operates regional transit systems and services to improve mobility for Central Puget Sound.Sound Transit l 401 S. Jackson St. l Seattle, WA 98104-2826 l 1-800-201-4900 / TTY Relay: 711 l main@soundtransit.org l www.soundtransit.org
Tacoma Link Expansion
Tacoma Link Expansion Alternatives Analysis Identify and study alternative travel corridors for expansion of the Tacoma Link light rail system.
Alternatives Analysis Alternatives Evaluation
Public Comment
Alternatives ReportSummer 2012 Winter 2013 Spring 2013Fall
NOV DEC MARCHPublic Comment Public CommentPublic Comment AUG
PreferredCorridor Identified Early Scoping
Early Scoping MeetingsSound Transit holds meetings for the public to comment on:
Routes and station locations Sound Transit should consider
Screening criteria Sound Transit should use to evaluate and compare different routes and station locations
Alternatives ScreeningSound Transit revises the list of alternatives and screening criteria based on public comments. Sound Transit screens route and stations and narrows it down to a few alternatives.
Alternatives Screening Public MeetingsSound Transit explains the criteria used to screen alternatives, presents which alternatives will be studied further, and collects public comment.
Sound Transit continues to study the alternatives. Consultants complete conceptual engineering to begin estimating the risks and costs of each alternative.
Alternatives EvaluationPublic MeetingsSound Transit presents a Draft Alternatives Analysis Report summarizing alternatives evaluation and collects public comment.
Report Revisions and Board PreparationSound Transit revises the Alternatives Analysis Report based on public comments and prepares to present to the Sound Transit Board.
Identification of Preferred Corridor by the Sound Transit BoardUsing the Alternatives Analysis Report, the Sound Transit Board identifies a preferred corridor.
Pre Alternatives Analysis ReportConcurrent with the work conducted by the Tacoma Link Expansion Stakeholder Group, Sound Transit prepared a technical report providing an initial analysis of the alternative corridors identified by the Stakeholder Group and two additional alternatives. The purpose of this analysis was to determine if the alternative corridors could meet community and Sound Transit objectives.
Alternatives AnalysisBuilding an expansion of Tacoma Link will require substantial federal funding. The Federal Transit Administration’s (FTA) discretionary New Starts program is the federal government’s primary financial resource for supporting locally-planned, implemented, and operated transit “guideway” capital investments, such as Tacoma Link. New Starts funding is awarded nationwide on a competitive basis following a rigorous, objective review of potential projects. Sound Transit plans to request New Starts funds for the Tacoma Link expansion project.
To be eligible and competitive for these federal funds we are completing an alternatives analysis (AA) for the project. An AA is the local forum for evaluating the costs, benefits, and impacts of a range of alternatives designed to address mobility problems and other locally-identified objectives in a defined transportation corridor, and for determining which particular investment strategy should be advanced for more focused study
and development. The goal of an AA is to provide the public, local officials, and potential funding partners with sufficient information for the decision-at-hand: that is, “What is the best solution for addressing our problems? What are its benefits? How much is it going to cost? And how are we going to pay for it?”
Phase I (June 2012-September 2012):Develop a list of possible corridor alternatives for expanding Tacoma Link. This list will be built upon the corridors identified by the Tacoma Link Expansion Stakeholder Group and Sound Transit’s Pre-AA study as well as additional input from the community.
•Hold open houses to seek input from the public and agencies on corridor alternatives. (August 2012). This public process will be accomplished as a part of “early scoping” under NEPA and SEPA, in order to obtain public input on the potential alternatives prior to any formal environmental documentation.
•Develop a written statement that explains the project’s purpose, need, goals and objectives.
•Define the alternatives and prepare for initial screening of alternatives.
•Submit “AA Initiation Package” to Federal Transit Administration (FTA).
•Phase II (October 2012-April 2013)
•Initial screening of alternatives including public and agency input. Screen the alternatives based on their ability to meet the project’s purpose and need.
•Define evaluation methods and evaluate the alternatives that come out of the screening, including public and agency input.
•Hold public meetings to discuss findings of the alternatives evaluation process.
•Prepare draft Alternatives Analysis report summarizing the alternatives evaluation and public/agency involvement process.
•Hold public meetings to discuss and take comments on the draft Alternatives Analysis Report.
•Finalize the Alternatives Analysis report and present to the Sound Transit Board.
•Sound Transit Board selects a preferred alternative to enter into the environmental review process and a project funding plan.
•Determine type of environmental review documentation needed and next steps for the project. An additional formal environmental scoping process under NEPA and SEPA may be required.
•Submit application for FTA New Starts/ Small Starts grant funding.
Thea Foss Waterw
ay
Puyallup River
Commencement Bay
N 15th St
Broadway
N M St
N I St
N Tacoma Ave
N 12th St
Pacific Ave Pacific Ave
Comm
erce St
Dock St
S 9th St
6th Ave
6th Ave
Martin Luther King Jr W
ayS J St
S Tacom
a Way
S 28th St
Puyallup Ave
S 30th St
E L St
E Portland Ave
S 34th St
S Wilkeson St
S 19th St
E 38th St
E 34th St
S 38th St
Pacific AvePacific Ave
N 1s
t St
Divisio
n Ave
S 15th St
S 11th St
Yakima Ave
Earnest S Brazill St
Market St
Holgate St
Jeffe
rson
Ave
S State St
S Ce
dar S
t
S 25th StS 25th St
Center St
S M St
E D St
S 43rd st
Mckinley AveS Thom
pson Av
Yakima Av
S Alaska St
S 48th St
Tacoma Ave S
E Portland Ave
E 21st St
Lincol
n Ave
E 11th
St
E L St
S 8th St
S 12th St
S 19th St
S M St
S G St
Tacoma Av S
E Portland Ave
Dock StA ST
S 12th St
S 10th StE 11th St
E 15th St
St Helens Ave
S 8th St
S 14th St
S J St
S J St
S 27th St
S 28th S
t
S G St
A St
S C St
St Paul Ave
S Taco
ma Wa
y
S 14th St
S 34th St
Theater District/ South 9th Street
Commerce Street/S 11th St
Convention Center/South 15th Street
Union Station/South 19th Street
Tacoma Dome
South 25th Street
McKinley Park
Rogers Park
McKinley Playfield
Foss Waterway Park
Lincoln/Eldridge
Sawyer Tot Lot
Sheridan Park
McCarver Playground
People's Community
Center
Stanley Playfield
Peck Field
Ferry Park
People's Park
Lincoln Heights
Irving Park
Thea's Park
Fireman's Park
Wright Park
Neighbors Park
Garfield Park
Ursich Gulch
Lot For Tots
5
5
5
705
705
16
509
UW Tacoma
Continued on back
Tacoma Link
Recommended