Thermal Generation

ALBIOMA

Le Galion - Thermal Power Plant 44 MW

This project concerned the implementation of a gas turbine of 44 MW on the Galion sugar refinery, in Martinique. On a turnkey basis, the works included: . the civil works engineering and works supervision, . the technical coordination with the turbine manufacturer, . the engineering, procurement, construction and commissioning of the electrical and mechanical balance of plant and of the control system. Management of all the interfaces of the project with the civil works company and the turbine manufacturer.

SOLUTION IMPLEMENTED

TURNKEY PROJECT Activity

Electricity, Mechanics, Automation & monitoring and control, Civil Works, Structures

Technologies Used GE LM6000 Aeroderivative Gas Turbine

Customer Benefits . Knowledge of the simple cycle process . Successfull integration of the turbine, its auxiliaries and the connection of the power plant

Business Units Involved Omexom Power Plants - Thermal

Philippe LENTZ - philippe.lentz@cegelec.comXavier DUCLOS - xavier.duclos@omexom.com

Country: France Site: Le Galion, Martinique Budget (k€): 10,000 Start Date: 01/2005 End Date: 12/2007

Contacts

SCAN WITH UBLEAM APPLICATION