Introduction to software engineering

Preview:

DESCRIPTION

Introduction to software engineering

Citation preview

1

SWE 205 - Introduction to Software Engineering

Lecture 7 - Software Project Management

2

Lecture Objectives To discuss project planning and

planning process. To show how graphical schedule

representations are used by project management

To discuss the notion of risks and the risk management process

3

Project Management process

Project Schedule

Start activities according to schedule

Review Project progress

Update the project schedule

Negotiatedeliverables

4

The Project Plan The project plan sets out:

The resources available to the project; The work breakdown; A schedule for the work.

5

The Project Plan

Quality Plan

Validation Plan

Configuration Plan

Maintenance Plan

Staff Development Plan

Quality Procedures and Standards

Approach, Resources, Schedule

Configuration Management Process

Maintenance Process, cost, required effort

How skills and experience of the Project team will be developed

6

Project Plan Structure Introduction. Project organisation. Risk analysis. Hardware and software resource

requirements. Work breakdown. Project schedule. Monitoring and reporting mechanisms.

7

Milestones & Deliverables Activities in a project should be

organised to produce tangible outputs for management to judge progress.

Milestones are the end-point of a process activity.

Deliverables are project results delivered to customers.

8

Project Scheduling Split project into tasks and estimate time and

resources required to complete each task. Organize tasks concurrently to make optimal

use of workforce. Minimize task dependencies to avoid delays

caused by one task waiting for another to complete.

Dependent on project managers intuition and experience.

9

Scheduling Challenges Estimating the difficulty of problems and

hence the cost of developing a solution is hard.

Productivity is not proportional to the number of people working on a task.

Adding people to a late project makes it later because of communication overheads.

The unexpected always happens. Always allow contingency in planning.

10

Bar charts & Activity Networks Graphical notations used to illustrate the

project schedule. Show project breakdown into tasks.

Tasks should not be too small. For example, they should take about a week or two.

Activity charts show task dependencies and the the critical path.

Bar charts show schedule against calendar time.

11

Task Durations & Dependencies

Task Duration (days) Dependencies

T1 8

T2 15

T3 10 T1

Component-A Design

Component-A Implementation

12

Progress from one Milestone to another.

Activity Network

start

T2

M3T6

Finish

T10

M7T5

T7

M2T4

M5

T8

4/7/03

8 days

14/7/03 15 days

4/8/03

15 days

25/8/03

7 days

5/9/03

10 days

19/9/03

15 days

11/8/03

25 days

10 days

20 days

5 days25/7/03

15 days

25/7/03

18/7/03

10 days

T1

M1 T3T9

M6

T11

M8

T12

M4

13

Activity Network

start

T2

M3T6

Finish

T10

M7T5

T7

M2T4

M5

T8

4/7/03

8 days

14/7/03 15 days

4/8/03

15 days

25/8/03

7 days

5/9/03

10 days

19/9/03

15 days

11/8/03

25 days

10 days

20 days

5 days25/7/03

15 days

25/7/03

18/7/03

10 days

T1

M1 T3T9

M6

T11

M8

T12

M4

Minimum time required to finishthe project. (critical path)

14

Activity Network

start

T2

M3T6

Finish

T10

M7T5

T7

M2T4

M5

T8

4/7/03

8 days

14/7/03 15 days

4/8/03

15 days

25/8/03

7 days

5/9/03

10 days

19/9/03

15 days

11/8/03

25 days

10 days

20 days

5 days25/7/03

15 days

25/7/03

18/7/03

10 days

T1

M1 T3T9

M6

T11

M8

T12

M4

Less chances of causing delayin project schedule.

15

Grantt Charts4/7 11/7 18/7 25/7 1/8 8/8 15/8 22/8 29/8 5/9 12/9 19/9

T4

T1T2

M1

T7T3

M5

T8

M3

M2

T6

T5

M4

T9

M7

T10

M6

T11M8

T12

Start

Finish

Flexibility in completionDate

16

Staff Allocation 4/7 11/7 18/7 25/7 1/8 8/8 15/8 22/8 29/8 5/9 12/9 19/9

T4

T8 T11

T12

T1

T3

T9

T2

T6 T10

T7

T5

Fred

Jane

Anne

Mary

Jim

Specialists e.g Security Analyst

17

Risk Management Risk management is concerned with

identifying risks and drawing up plans to minimise their effect on a project.

A risk is a probability that some adverse circumstance will occur Project risks affect schedule or resources; Product risks affect the quality or performance of

the software being developed; Business risks affect the organisation developing

or procuring the software.

18

Risk Management - Example An experience Programmer leaves a

project. Project risk - possible delay in system

delivery. Product risk - Replacement may be less

experienced and more chances of errors. Business risk - Programmer’s experience is

not available for future products.

19

Risk Management Process

Risk avoidanceand contingency

plans

Risk planning

Prioritised risklist

Risk analysis

List of potentialrisks

Riskidentification

Riskassessment

Riskmonitoring

20

Risk Indicators

Risk type Potential indicators

Technology Late delivery of hardware or support software, many reportedtechnology problems

People Poor staff morale, poor relationships amongst team member,job availability

Organisational Organisational gossip, lack of action by senior management

Tools Reluctance by team members to use tools, complaints aboutCASE tools, demands for higher-powered workstations

Requirements Many requirements change requests, customer complaints

Estimation Failure to meet agreed schedule, failure to clear reporteddefects

21

Key Points Planning and estimating are iterative

processes which continue through out the course of a project.

Project scheduling involves preparing various graphical representations showing project activities, their durations and staffing.

Risk management is concerned with identifying risks which may affect the project and planning to ensure that these risks do not develop into major threats.