View
229
Download
0
Category
Preview:
Citation preview
INDIANOIL PETRONAS PRIVATE LIMITED
Executive Summary for
The Proposed Expansion of Production Capacity from 5,76,000 TPA to 23,04,000 TPA of LPG
at Athipattu Village, Ponneri Taluk, Thiruvallur
District
Category B - Schedule 6(b)
Executive Summary for the Proposed Increase in LPG Throughput
EXECUTIVE SUMMARY
I. PROJECT DESCRIPTION
M/s IndianOil Petronas Pvt. Ltd. has commissioned a LPG Import/Export Terminal at Ennore
in the year 2012 to meet the LPG requirements of Tamil Nadu, Karnataka and Andhra
Pradesh. The Terminal was set up with the aim of increasing LPG availability and
eliminating transportation costs by bullet trucks. Blended LPG from the terminal caters to the
LPG demand in the southern region of India.
Propane/Butane is pumped from Ennore Jetty to the Terminal, blended to produce LPG, The
LPG is transferred to bullet tankers & Indane Bottling Plant, Athipattu for distribution. The
Terminal is operated on a single shift production basis to produce 5,76,000 TPA of LPG. The
present project proposal is to expand the production capacity to 23,04,000 TPA by increasing
the shifts of operation from one to three and by installing four additional Truck Loading
Filling (TLF) bays.
Need For the Project and Its Importance
India is the fourth largest consumer of LPG (15 million tonnes per year) in the world
following USA, China and Japan. With home deliveries of 3 million LPG cylinders per day
(900 Million/year), India is also the third largest domestic consumer of LPG.
With a combined bottling capacity of 0.4 million TPA, Tamil Nadu was facing a LPG deficit
of 0.8 million TPA and this shortfall was met by transporting LPG from Mangalore by road.
IPPL has commenced operations at Ennore to meet the LPG requirements of Tamil Nadu,
Karnataka and Andhra Pradesh. The IPPL facility at Ennore was set up with the aim of
increasing LPG availability.
Project Location
The extent of the site falls between 13º15’17.45”N and 13º15’33.52”N latitude and
80º17’49.75”E and 80º18’25.63”E longitude (Topo sheet Nos. 66 C/3, 66 C/4, 66 C/7, 66
C/8). There are several industries located in the vicinity of the Terminal such as IOCL
Bottling Plant (east), North Chennai Thermal Power Plant (east) & Zuari Cement grinding
unit (north). Nearest settlement is Athipattu Pudhunagar (south). The project site is
accessible by road (Chennai – Pulicat road SH 104) and rail (Athipattu Railway station,
Chennai Suburban Railway). The Environmental Setting of the project is given in Table 1.
1
Executive Summary for the Proposed Increase in LPG Throughput
The location map of Project site is given in Figure -1.
Table 1- Environmental Settings of the Project Site
S. No. Particulars Details
1 Latitude 13°15'18"N
2 Longitude 80°18'8"E
3 Site Elevation above MSL 3 m
4 Topography Plain
5 Present land use at the site Special & Hazardous Industrial Area
6 Nearest highway National Highway 5 – 15.4 km (W)
7 Nearest railway station Athipattu Railway Station – 250m (S)
8 Nearest airport Chennai International Airport – 31 km (SSW)
9 Nearest town / city Chennai – 19km (S)
10 Water body Koratalaiyar river – 1.10km (E)
11 Nearest Port Ennore–4.2km (NE)
Chennai – 18km (S)
12 Hills / valleys Nil in 15 Km radius
13 Archaeologically important places Nil in 15 Km radius
14
National parks / Wildlife Sanctuaries/
Eco sensitive zones as per Wild Life
Protection Act, 1972
Nil in 15 Km radius
15 Reserved / Protected Forests Nil in 15 Km radius
16 Seismicity Zone III according to the Indian Standard
Seismic Zoning Map as of January 2012.
17 Defense Installations Nil in 15 Km radius
2
Executive Summary for the Proposed Increase in LPG Throughput
Figure 1 - Location Map of Project Site
3
Executive Summary for the Proposed Increase in LPG Throughput
Land Requirement
The total land available under the ownership of the IPPL is 110 acres (445350 m2). The land use
break-up showing the existing and proposed activities is given in Table 2.
The proposed expansion will be carried out within the existing land that belongs to IndianOil
Petronas Private Limited. The land use classification of the site as per CMDA land use map is
“Special & Hazardous Industrial Zone”.
Table 2 - Land Use Break-Up
Sl.No. Description Breakup Area
(Existing) (sq.m)
Breakup Area (Proposed)
(sq.m)
Final Breakup in %
1 Production Building 4287 4654.5 1.05
2 Area for Future Facilities 130000 129632.5 29.11
3 Ancillary / Supporting Buildings 8158 No change 1.83
4 Storage Area 6212 No change 1.39
5 Road Area 37000 No change 8.31
6 Parking Area 61500 No change 13.81
7 Green Belt / Landscape Area 174993 No change 39.29
8 Rain Water Harvesting Pond Area 23200 No change 5.21
Total 445350 445350 100
Magnitude of Operation
M/s. IPPL currently operates the Import / Export Terminal having production capacity of
5,76,000 TPA at Athipattu in Thiruvallur District. The final throughput after expansion will
be 23,04,000 TPA. The increase in throughput of LPG will be achieved by increasing the
number of shifts from one to three and by installing four additional Truck Loading Filling
(TLF) bays.
Infrastructure already present at the Terminal include cooling tower system, RO plant, boiler,
fuel storage systems, sewage treatment plant, rainwater harvesting pond, etc. to support the
process operations. For the proposed expansion the existing infrastructures will be sufficient,
however 4 additional Truck Loading Filling (TLF) bays will be setup, in addition to the 12
4
Executive Summary for the Proposed Increase in LPG Throughput
existing bays to achieve the proposed throughput. The throughput before and
after expansion is given in Table-3.
Table 3 - Throughput (Before and After expansion)
S. No. Product Capacity of Operation (TPA)
Existing Proposed Additional After Expansion
1. LPG 5,76,000 17,28,000 23,04,000
LPG Import / Export Terminal Operating Procedure
LPG production at IPPL consists of the following stages,
The products (Butane & Propane) are received in refrigerated state by ship at Jetty of
Ennore Port.
2 nos. cross country pipelines each having total length of approx. 12.5 KM is used to
transfer Butane/Propane from Jetty to the Terminal.
Product shall be stored in refrigerated state.
Product shall be heated to 15oC prior to blending, mercaptan dosing is done and LPG is
transferred to loading stations/Indane Bottling Plant.
The Manufacturing Process flowchart is given in Figure 2, and material balance for complete
loading unloading/operation in Table 4.
Table 4 - Mass balance for complete loading / unloading operation
Number of bays (A)
Filling capacity
(B)
Number of hours of
operation per day (C)
Average production per day
(D) = (A) x (B) x (C)
Number of days
working per year
(E)
Average production /year
(F) = (D) x (E)
12 (existing) 20 T/hr 8 1920 TPD 300 5,76,000 MTPA
16= 12 + 4 Proposed
(Expansion)
20 T/hr 24 7680 TPD 300 23,04,000 MTPA
5
Executive Summary for the Proposed Increase in LPG Throughput
Figure 2 - Manufacturing Process Flow Chart
Project Cost - The estimated cost for installing the four additional Truck Loading Filling
(TLF) bays is Rs.2 Crores (Rupees Two Crores Only).
6
Executive Summary for the Proposed Increase in LPG Throughput
II. DESCRIPTION OF THE ENVIRONMENT
Primary baseline environmental monitoring studies were conducted during three months
from January 2015 to March 2015 and details are as follows:
Meteorology - The maximum and minimum temperature recorded during the study
period is 36°C and 17°C. The relative humidity found varying from 64 to 94%. The
predominant winds are mostly from Northeast, East southeast directions.
Air Environment - To establish the baseline status of the ambient air quality in the study
area, the air quality was monitored at eight (8) locations. The maximum and minimum
values of Ambient Air Quality monitoring are given in the following table
7
Executive Summary for the Proposed Increase in LPG Throughput
Locations PM10, µg/m3
PM2.5, µg/m3
SO2, µg/m3
NOX, µg/m3
Ammonia µg/m3
Ozone, µg/m3
CO, mg/m3
Lead, µg/m3
Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max
Project Site
(AAQ1) 51.1 63.8 23.4 28.6 7.4 10.1 12.4 17.1 BDL(<5) 12.2 16.4 0.21 0.48 BDL(<0.1)
Athipattu
(AAQ2) 46.3 56.4 19.2 23.4 5.3 7.4 10.3 13.4 BDL(<5) 6.8 9.4 BDL(<0.1) BDL(<0.1)
Vallur
(AAQ3) 52.7 67.4 21.8 27.4 6.8 8.3 12.1 16.4 BDL(<5) 10.7 15.1 0.12 0.18 BDL(<0.1)
Vichoor
(AAQ4) 43.8 53.4 20.1 26.5 5.1 7.1 9.2 14.7 BDL(<5) 9.2 13.6 BDL(<0.1) BDL(<0.1)
Ennore
(AAQ5) 50.8 71.6 26.8 37.9 8.2 13.6 15.8 23.8 8.2 13.3 13.3 19.2 0.18 0.37 0.12 0.18
Minjur
(AAQ6) 45.1 52.8 18.2 23.5 5.2 6.7 12.5 16 BDL(<5) 8.8 12.7 BDL(<0.1) BDL(<0.1)
Kattulpalli
(AAQ7) 46.8 54.3 23.5 27.1 6.1 8.5 8.2 10.8 BDL(<5) 5.7 9.5 BDL(<0.1) BDL(<0.1)
Voyalur
(AAQ8) 38.4 46.5 16.8 20.4 5.0 5.4 7.3 9.4 BDL(<5) BDL(<5) BDL(<0.1) BDL(<0.1)
8
Executive Summary for the Proposed Increase in LPG Throughput
Location Benzene, µg/m3 Benzo[a]pyrene ng/m3
Arsenic ng/m3
Nickel ng/m3
Total VOC (µg/m3)
Min Max Project Site BDL (<0.1) BDL (<0.01) BDL (<1) BDL (<1) 19 51
Athipattu BDL (<0.1) BDL (<0.01) BDL (<1) BDL (<1) BDL (<1)
Vallur BDL (<0.1) BDL (<0.01) BDL (<1) BDL (<1) BDL (<1)
Vichoor BDL (<0.1) BDL (<0.01) BDL (<1) BDL (<1) BDL (<1)
Ennore BDL (<0.1) BDL (<0.01) BDL (<1) BDL (<1) BDL (<1)
Minjur BDL (<0.1) BDL (<0.01) BDL (<1) BDL (<1) BDL (<1)
Kattulpalli BDL (<0.1) BDL (<0.01) BDL (<1) BDL (<1) BDL (<1)
Voyalur BDL (<0.1) BDL (<0.01) BDL (<1) BDL (<1) BDL (<1)
9
Executive Summary for the Proposed Increase in LPG Throughput
The results of the monitored data indicate that the ambient air quality of the region in general
is in conformity with respect to the norms of National Ambient Air Quality standards
(NAAQS) of CPCB, with present level of activities.
Noise Environment - The noise monitoring has been conducted at six (6) locations in the
study area. The highest noise level was found to be 52.8 dB (A) during day time. The
lowest noise level was found to be 41.1 dB (A) during night time. However the noise
levels are found to be well within the CPCB standards.
Water Environment - Six (6) groundwater samples and one (1) surface water sample
within the study area were considered for assessment. The water samples were collected
and analyzed during 2015. The analysis of ground water results indicate that the average
pH ranges in between 7.28 -8.12, TDS ranges from 424 mg/l - 1225 mg/l, Total Hardness
ranges from 190 mg/l - 710 mg/l, iron content ranges from 0.07mg/l – 0.16mg/l, nitrate
content ranges from 5 mg /l – 42 mg/l was observed.
The analysis of Surface water results indicate that the pH of 8.06, TDS of 31304 mg/l,
Total Hardness 5400 mg/l, DO 6.1 mg/l was observed. Total Coliform of 542/100 ml and
Faecal Coliforms of 358/100 ml was observed.
Soil Environment - Six locations within the study area were selected for soil sampling. It
has been observed that the pH of the soil was ranging from 7.52 to 8.52, Conductivity of
the soil ranges from 0.066 to 0.824 mS/cm. Since the EC value is less than 2000 µS/cm,
the soil is said to be non-saline in nature. Soil organic content varied from 0.51 to 0.96 %
which indicates the very low level of organic matter.
Ecological Environment - There are no endemic and endangered species of flora and
fauna within the study region. There is no wild life sanctuary, national park or bird
sanctuary with in the 15 km radius of the project site.
Socio-Economic Environment - According to 2011 census, Tiruvallur district had a
population of 37,28,104. With a sex-ratio of 987 females for every 1,000 males, much
above the national average of 929. A total of 4,05,669 were under the age of six,
constituting 2,08,449 males and 1,97,220 females. Scheduled Castes and Scheduled
Tribes accounted for 8, 21,646 and 47,243 of the population respectively. Average
literacy rate of Tiruvallur district in 2011 were 84.03 compared to 76.94 of 2001. The
10
Executive Summary for the Proposed Increase in LPG Throughput
district had a total of 9,46,949 households. There were a total of 12,47,918 main workers,
comprising 60,436 main cultivators, 1,73,150 main agricultural laborer’s, 9,72,590 other
workers, 2,90,136 marginal workers, 13,008 marginal cultivators, 97,436 marginal
agricultural laborers.
III. ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION MEASURES
Ambient Air Environment - No emissions will be generated during the operations as the
entire process will be carried out through close circuit piping from storage area to filling
shed. The only point sources of emissions will Boiler, D.G sets & Fire Engines, they have
been fitted with stacks of adequate height to disperse the pollutants.
Impact on Water Environment - Total water requirement for M/s IPPL during proposed
expansion is 187 KLD, which will be sourced through CMWSSB, for the existing operation
water is sourced through CMWSSB. There is no requirement for drawl of surface /
groundwater or diversion from other sources.
During the proposed expansion, 51.2 KLD sewage will be generated, which will be treated in
the existing Sewage Treatment Plant (treatment capacity 60 KLD). DM Plant and Cooling
Tower blowdown (13.422 KLD) will be treated using RO plant & permeate (10.47 KLD) will
be recycled to DM plant (8.182 KLD) and the Cooling Tower (2.288 KLD). RO reject (2.95
KLD) & Boiler Blow Down (1 KLD) will be diverted to solar evaporation ponds.
Impact on Ambient Noise Environment - Activities within the Terminal (loading /
unloading operations) will not cause any disturbances to people living in the proximate areas
outside the plant boundary. The only source of noise within the Terminal is DG operation.
DG sets are placed within acoustic enclosures. Necessary greenbelt with total area of 39.29%
has been provided to contain the noise emissions.
Solid and Hazardous Waste Generation – STP sludge generated will be used as manure for
green belt development. Used oil generated from DG set operation will be disposed to
TNPCB Authorized Used Oil Recyclers.
11
Executive Summary for the Proposed Increase in LPG Throughput
Details on Fire Protection System and Safety Measures – The Propane/Butane/LPG
import-export terminal of IPPL has an extensive network of pressurized fire hydrant system.
This system enables to fight fire anywhere within Terminal and to cool vessels and structures
to ensure their safety during an incident involving incidents of dangerous heat flux from a
burning fire. Fire Fighting Facility Alarms have been provided to display in Fire Pump House
and Main Control Room for operation of firefighting pumps, deluge valves, MV sprayers, fire
hydrants and monitors. A dedicated Fire Alarm network with manual call point type fire
alarm in the hazardous as well as in non-hazardous area has been provided. Adequate number
of Dry Chemical powder, CO2 Extinguishers and Fire Buckets are installed within the
terminal. State of the art Quartzite Bulb, Gas, Flame, Laser, Heat and Smoke detectors are
also installed throughout the terminal. Combination of Fire Detectors, Fire Alarm, Fire
Extinguishers and Fire hydrant system will ensure that conditions for major accident hazards
are never allowed to occur.
Impact on Socio-economic Environment - The present proposal is aimed at meeting the
LPG demand of the South India by increasing the throughput of LPG. Once the increased
throughput is achieved, the daily fuel requirements of people residing in Tamil Nadu,
Karnataka & Andhra Pradesh will be met and penetration of LPG supply in rural areas to the
tune of 75% can be achieved. It has positive impact on the social-economic conditions of the
area.
IV. ENVIRONMENTAL MONITORING PROGRAMME
Environmental monitoring plan for operation phases of the proposed increase of LPG
throughput has been prepared to ensure efficiency of implemented mitigation measures. In
order to implement the proposed environmental management program efficiently within the
organization, periodical monitoring as per statutory guidelines and mid course
corrections/actions, environmental cell will be established for successful implementation of
monitoring plan.
12
Executive Summary for the Proposed Increase in LPG Throughput
V. BENEFITS OF PROPOSED PROJECT
The proposed project shall yield following benefits:
• Increase in production of LPG will aid in meeting the demands of various LPG
bottling plants spread across the states of Tamil Nadu, Andhra Pradesh and
Karnataka .
• Improved penetration of LPG in rural areas will help in replacing the use of
biomass fuels like fire wood, cow dung, etc., with LPG which will in turn improve
the air quality, the health and quality of life of people.
• To help in raising LPG coverage in rural areas to 75%.
• To meet the demands of industrial sector and also in complementing the various
measures taken by Government of India, like Make in India Campaign.
• LPG can be used as a substitute by industries instead of other fossil fuels like coal,
diesel, furnace oil etc, which emit more pollutants and greenhouse gases thereby
protecting the environment.
• Auto Gas is currently marketed as an economical & environment friendly fuel.
The current Auto Gas price in Chennai is 36.65 Rs/Ltr as opposed to Petrol (60.08
Rs/Ltr) & Diesel (47.28Rs/Ltr). Increasing its availability will remove bottle-
necks in its demand versus sales scenario & pave way for India to become one of
the leading Auto LPG markets of the world in the next few years.
• At present LPG is supplied to neighboring Indane Bottling Plant at 400MT/day.
Tripling the throughput at the Terminal will increase the quantity of LPG pumped
to the Indane Bottling Plant thereby increasing the availability of domestic LPG to
the populace residing in Chennai.
• No land acquisition is required for construction of proposed LPG filling facilities.
The socio-economic impacts linked to the acquisition of land and structures will
not appear in the project.
• During construction phase of the project no significant impact on environment are
anticipated.
• The proposed project will generate direct and indirect employment opportunities
mainly during the construction phase. Local semi-skilled and unskilled laborers
will get direct employment in the construction phase. This is a positive impact of
the proposed project.
13
Executive Summary for the Proposed Increase in LPG Throughput
• The proposed LPG increase in LPG throughput will provide cleaner fuel, which
will create healthy environmental conditions.
VI. ENVIRONMENT MANAGEMENT PLAN
AIR ENVIRONMENT MANAGEMENT
Adequate green belt has been developed on 174993 sq.m. within the terminal to mitigate the
pollution arising due to movement of vehicles. Regular monitoring of Boiler, DG Stack and
Ambient air quality monitoring will be carried out.
WATER ENVIRONMENT MANAGEMENT
Sewage generated will be treated in the existing STP prior to discharge to greenbelt. Trade
effluent in the form of blowdown & RO reject water is disposed to solar evaporation pans.
NOISE ENVIRONMENT MANAGEMENT
Acoustic enclosures are provided for D.G sets. Noise monitoring has been conducted
periodically at the Terminal and confirms the CPCB norms.
SOLID & HAZARDOUS WASTE MANAGEMENT
STP sludge generated will be used as manure for green belt development. Used/Spent oil
generated will be disposed through TNPCB Authorized recyclers.
RAINWATER & STORM WATER DRAINAGE NETWORK
The facility at M/s. IPPL has adequate rain water harvesting and storm water drainage
system, catchment area has been designed to capture rainwater along the driveways namely,
Paved Roads, Truck Parking, Fire water reservoirs and Elevated water tank. Collected storm
water is diverted to rainwater harvesting pond. Extensive storm water network has been
constructed within the terminal, the storm water run-off from roads/paved/landscaped areas is
being diverted to rain water harvesting pond.
GREENBELT DEVELOPMENT
The Terminal has a well developed greenbelt area along totaling to 174993 sq.m (39.29% of
total plot area).
14
Executive Summary for the Proposed Increase in LPG Throughput
ENVIRONMENTAL BUDGET – For implementation of environmental management plan and
monitoring plan capital cost and recurring cost per annum are as given below:
S.No. Description (Cost in lakhs rupee)
Capital cost Recurring cost per annum
1. Sewage treatment plant (O&M) 25 1.8 2. Environmental assessment & reporting -- 0.9 3. Greenbelt development 7 6.6 4. Occupational health check-up -- 4.6 5. Occupational safety 21 4.5
Total 53 18.4
VII. CONCLUSION
Based on the environmental assessment, all possible environment aspects have been
adequately assessed and necessary control measures have been formulated to meet with
statutory requirements, in the preparation of the EIA-EMP. This expansion in throughput of
LPG is very much required to meet the rise in demand and bridge the demand supply gap for
LPG, the proposed increase in throughput of LPG is aimed at meeting demand of LPG in
Tamil Nadu, Andhra Pradesh & Karnataka. The proposed increase in will also help in
achieving improved penetration of LPG in rural areas. Further the basic requirement of the
nearby villages will be strengthened by extending health care, educational facilities to
the community, providing drinking water to the villages etc. by M/s. IPPL.
15
Recommended