INDIAN RAILWAYS INSTITUTE OF CIVIL ENGINEERING. Introduction of high speed corridors on IR– impact...

Preview:

Citation preview

INDIAN RAILWAYS INSTITUTE OF CIVIL ENGINEERING

Introduction of high speed corridors on IR– impact & challenges before us

What is High Speed Corridor?

Generally, a corridor is considered High Speed

– If trains run at speeds above 250 km/h for at least over a significant part of journey in case of new construction.

– If trains run at 200 km/h in case of upgraded routes.

steam

HS tests

VHS tests

Competitive Advantage of High Speed Rail

Type 1 is the most classic and the "purest" high speed system. This constitute a network of lines used exclusively by high speed trains which do not operate on any other lines. The JR Central and JR West Shinkansen are such systems.

High Speed Network Systems

Type 2 is a network of high speed lines, again used exclusively by high speed trains but the trains in question also run on conventional lines e.g. Korea Train Express (KTX)

High Speed Network Systems

Type 3 is a system of high speed lines which are used not only by high speed trains (> 250 km/h) but also by conventional trains at lower speeds e.g. The Spanish system (AVE).

High Speed Network Systems

Type 4 is a mixed system .There is separate rolling stock and infrastructure for high speed . All types of train run on the high speed lines and the high speed trains run on all types of lines e.g. German (ICE) and Italian (Eurostar Italia).

High Speed Network Systems

Approach to high speed

• Improvement of conventional rail system

• Dedicated high speed corridors

Improvement of conventional rail system

• Advantages– Lower cost– Lesser time in implementation

• Limitations– Sharp curves Tilting train – Scheduling of trains (line capacity)– Old formation (only track renewed )– Maintenance mixed traffic

Dedicated high speed corridors

• Necessary if speed > 250 km/h

• Least constraints

• Proven technology up to 350 km/h

• Cost intensive

Track Parameters for High Speed Corridors

CURVES

Parameters* 270 km/h 300 km/h 350 km/h

Radius of curvature (m)

- Recommended 3846 4545 7143

- Normal 3226 4000 6250

- Exceptional 3125 4000 5556

Maximum Cant (mm)

- Normal 180 180 180

- Exceptional 180 180 180

Cant Deficiency ( mm)

- Normal 100 85 65

- Exceptional 130 100 85

*French Railways

Track Parameters for High Speed

CURVES

Parameters* 270 km/h 300 km/h 350 km/h

Cant excess (mm)

- Normal 100 100 -

- Exceptional 110 110 -

Variation of cant deficiency (mm/s)

- Normal 30 30 30

- Exceptional 50 50 50

Length of parabolic connection (m)

R=3125m

L=270m

R=4000m

L=300m

R=5556m

L=350m

*French Railways

Ruling Gradient

Generally steeper gradients permitted.

• French Railways – Gradient allowed up to 350/00

– Circular transition curves of 12000m radius between two different gradients

• Japanese Railways– Maximum gradient may attain 150/00

– Circular transition curves always provided between two successive gradients

Spacing of Tracks

Country

Minimum distance between tracks (m)

250 km/h 300 km/h 350 km/h

France 4.2 4.2 4.5

Germany 4.5 4.5 4.5

Italy 4.5 5.0 5.0

Spain 4.3 4.7 4.7

For Standard Gauge

Track Bed

• Long term settlement– Treating of material wherever necessary

• Drainage

– Suitable graded granular material with minimum of fines

– A layer of Geo-grid/concrete/ tarmac– Sub-ballast & Ballast

• Ballast less track bed

Tunnels

Problem of airwaves– Increased cross-sectional area of

tunnel

– Avoiding double line tunnels

– Operating only air sealed coaches

– Provision of pressure release shaft

Bridges

• Sudden impact loading due to change in vertical stiffness between bridge deck and approach embankment

• Resonance with certain spans

Track Laying

For high Speed corridors – Track laying quality is most crucial

Stringent requirements for

– Dimensions

– Materials

– Tolerances

Very few contractors who can deliver.

Other Issues

• Level crossing– Normally not suitable for high speed operation grade seperation – Interlocking of train signal with that of road – Automatic road barriers

• Fencing– Generally fenced.

• Track Failures– Continuous track circuiting

• Environment-Noise problem

Track Geometry Monitoring

• Increased frequency of monitoring

• Track irregularity up to 80m wavelength important

• Present chords 7.2m & 9.6m grossly inadequate

• JR measures geometry based on 40m mid chord offset

• Tolerances either on 40m chord or absolute profiles

Track Maintenance Strategy

• Whether existing system of maintenance adequate

or

• Separate agency for monitoring and a separate agency for maintenance

Option

Monitoring by railway and Maintenance on contract

High Speed Line – Construction Costs per Km

Cost Aspects

Construction cost for a new high speed line - Euros 10 to 70 millions. (1 Euro = Rs.56)

Investment on a high speed project can be divided as

– 40% for civil works– 20% for track and rail works– 15% for earth works– 10% for electrification– 10% for signaling and communication– 5% for others

Cost Aspects

Average construction cost for

Tunnels - Euros 8 million / km

Bridges - Euros 16 million / km

Superstructures - Euros 1 million / km

Signaling system - Euros 1.5 million / km

Power supply - Euros 1.2 million / km

Some Asian Projects

Taiwan’s high speed rail line

• Project– Between Taipei – Kaohsiung– Total distance 345 km– Design speed 350 km/hr– Initial speed 300 km/hr– Journey time 1hr 20min– Project cost US $ 15 bn– Due inauguration in Dec. 2006– System Shinkansen 700 series trains

• Structures 39 km of bored tunnels 8 km of cut and cover tunnels 251 km of box girder viaducts

Some Asian Projects

Taiwan’s high speed rail line

• Build approach

Build – Operate – Transfer (BOT)

By Taiwan High Speed Rail Corporation ( THRC)

35 years concession period

Land provided by government

Some Asian Projects

South Korea High Speed Rail Route

• Project– Between Seoul and Busan

– Total distance 412 km

– Design speed 350 km/h

– Initial speed 300 km/h

– Project cost US $ 16.3 bn

– To be fully operational in 2010

– System French TGV (SYSTRA)

• Structures

Half of new track in tunnel About 25 % of track on 148 viaducts or bridges

Some Asian Projects

South Korea High Speed Rail Route

Funding

45% by government

29% by Korea High Speed Rail Const. Authority

24% foreign loan

2% private funding

Some Asian Projects

Chinese Railways

Maglev First commercial Maglev train

Pundong airport to the city center Shanghai

Total distance of 30 km covered in 8 min.

Maximum speed attained - 430 km/hr

Project cost $ 1.4 bn

High Speed Lines

China is building a 300 km/hr line from Beijing to Tianjin and has plans, including a 1300 km line between Beijing and Shanghai

China plans to build 12000 km of dedicated passenger railways costing US $ 95.4 bn by 2020

200 Engineers are being trained on high speed systems.

Recommendations of seminar held at IRICEN on Foundation Day,2005

• Imperative for IR to go for high speed routes because of rising competition from road and air sectors.

• With the boom in economy, more and more passengers will like to avail high speed transportation. Urgent steps required to introduce high speed trains as considerable time is required from inception to commissioning.

• IR will have to decide whether to construct dedicated corridors or

go for upgradation of existing routes. In view of near saturation of existing routes , dedicated route option is more reasonable.

Recommendations of seminar held at IRICEN on Foundation Day,2005

• Heavy investments required . Alternate methods of financing, setting of separate organisation and private participation may be considered.

• Execution of work for high speed lines will require quantum jump in technology.

• “ High Speed Centre” should be established at IRICEN. A task force should be set up to make use of expertise available with UIC and internationally.

0.0

0.5

1.0

1.5

2.0

2.5

0 10 20 30 40

Wavelength (m)

Tra

nsf

er F

un

ctio

n

TF( 7.2 m Chord )

TF( 9.6 m Chord )

Tilting Trains

• Carriages have tilting mechanism.

• 25 to 40% higher speed without upsetting the passengers.

• Speed up to 200 to 250kph

• Italy, Sweden, UK, Germany

Recommended