Improving quality of plan submissions
Scope
- Introduction
- Information to be shown on plans
- Extent of responsibilities of QP in A&A works
- Changes to audit disciplinary procedure
- Conclusion
7/27/2019 Improving Quality of Plan Submission
3/29
Introduction
- Some Qualified Persons did not show adequate details ontheir fire safety plans submitted to SCDF for approval
- As a result, Audit Processing Officer needs clarification withQP, resulting in delay to obtain TFP/FSC
-Checklists for the necessary and useful details to beshown on the fire safety plans for submission to SCDF(Checklists For Submissions Of New AndAddition/Alteration Fire Safety Works (FSSD Circular Dated 5May 09))
- Highlight some of the details
- New Erection & Addition/Alteration works
7/27/2019 Improving Quality of Plan Submission
4/29
- Space of 150 mm x 100mm on top left
hand corner shall be kept blank for FSSD endorsement
- To provide
- Location plan
A/A & newerection
- Whole floor layout plans
- Detail unit layout plans
- Sectional /elevation view- Site plan new erection
7/27/2019 Improving Quality of Plan Submission
5/29
FSSDEndorsement
QPEndorsement
Miscellaneous
Project Title
Means of access to site
Distances between buildings
Location of existing and proposed internal fire hydrant
100mm
150mm
7/27/2019 Improving Quality of Plan Submission
6/29
7/27/2019 Improving Quality of Plan Submission
7/29
To state the fire resistance ratings of all compartment walls,fire doors, shutters and other fire safety measures- shutter to indicate with insulation rating, if required
7/27/2019 Improving Quality of Plan Submission
8/29
To indicate positions of WR/DR landing valve and HR
HRHR
HR Hosereel
7/27/2019 Improving Quality of Plan Submission
9/29
- To endorse on plans the type of fire protection system provided for thebuilding
- To endorse on plans that Emergency Voice Comms system, smoke controlsystem are provided for the building, if required
This floor is protected by sprinkler system
7/27/2019 Improving Quality of Plan Submission
10/29
MV
To indicate the type of ventilation system provided for smoke stoplobby/fire fighting lobby and exit staircases
7/27/2019 Improving Quality of Plan Submission
11/29
Min
10m
Min
10m
x
7/27/2019 Improving Quality of Plan Submission
12/29
93 sqm
7/27/2019 Improving Quality of Plan Submission
13/29
The raised floor is protected by automatic
alarm system
Raised floor
- To indicate the material and the type of fire protectionsystem in concealed space
200mm
7/27/2019 Improving Quality of Plan Submission
14/29
- Fire engine accessway
- To provide calculation to show the perimeter required forfire engine accessway; and to indicate roads that have beendesignated as fire engine accessway
Area = 15000 sqm
Required perimeter= 1/2 x perimeter of building
= x 50 m = 25m
7/27/2019 Improving Quality of Plan Submission
15/29
Hydrant
- Location of existing and proposed internalfire hydrants
- To indicate location of public hydrant if it is
used to cover the proposed fire engineaccessway/access road
- Public hydrant on opposite site of road (morethan one lane) cannot be used
C t b d
7/27/2019 Improving Quality of Plan Submission
16/29
Fire EngineAccessway
Fire Engine
Access Road
H
Cannot be used
to serve the
development
H
7/27/2019 Improving Quality of Plan Submission
17/29
Unprotected opening
- To submit form FSSD BP4
- To attach sketches to show the detail calculationof unprotected openings
A f l i t l 6 12 72
7/27/2019 Improving Quality of Plan Submission
18/29
Area of enclosing rectangle = 6m x 12m = 72 sqm
Unprotected areas = 2m x 2m x 8 = 32 sqm
Unprotected percentage: 32 sqm/72 sqm = 36 %
Setback distance based on Table 2 = 4.6m (interpolation)
7/27/2019 Improving Quality of Plan Submission
19/29
Occupant load (OL) & Exit capacity (EC) calculations
- To submit OL and EC calculations for all newprojects
- To submit for change of use for unit
- To highlight in the project title that there is
change of use- To recalculate the occupant load of the
floor involved in change of use- To ensure new occupant load does not
exceed exit capacity
7/27/2019 Improving Quality of Plan Submission
20/29
EXTENT OF RESPONSIBILITY OF QUALIFIED PERSONSIN A&A WORKS (FSSD Circular dated 5 Feb 10)
- Some Qualified Persons are not certain about theextent of their responsibilities in carrying outaddition/alteration works in existing buildings.
- FSSD produced tables detailing the extent of QPsresponsibilities when carrying out various typesof addition/alteration works in existing buildings.
7/27/2019 Improving Quality of Plan Submission
21/29
7/27/2019 Improving Quality of Plan Submission
22/29
7/27/2019 Improving Quality of Plan Submission
23/29
7/27/2019 Improving Quality of Plan Submission
24/29
START
7/27/2019 Improving Quality of Plan Submission
25/29
APO present the case to Audit
Check Committee (ACC)
NoACC
Explanation
accepted by
ACC?
Yes
Yes
APO inform QP of non-
compliant items
START
NoACC
Any major non
compliant item?
Current procedure
- Plans randomlyselected for audit
check
Yes
7/27/2019 Improving Quality of Plan Submission
26/29
No APO
Amendment
plans
required?
Yes
Yes
QP submits
amendment
plansEnd
APO present to Audit
Disciplinary Committee
(ADC)
APO follow up
with the decision
ADC decides on
the action on the
QP
- Audit Disciplinary Committee (ADC)
decides on action against errant QP
- Revised plan audit procedure
7/27/2019 Improving Quality of Plan Submission
27/29
*-Increase % of audit to100%
- inform QP that all hissubsequent submissionswill be checked prior to
approval. Project will bedisapproved if major non-compliant items are found.(QP has to pay 25% oforiginal plan fee for re-submission)
- inform PEB/BOA
- Court action
- MAA is excluded from
the computation of 100%audit check
3rd ADC
Increase % of audit to 50%
QP submits plans
Any ADC case?Reduce %
of audit
No
No
Yes
Actions against QP *
QP submits plans
Any ADC case?Reduce %
of audit
Yes
Start
Counting ofADC cases is onrolling 5 yearsbasis
Audit selectionbase on QPsubmission
7/27/2019 Improving Quality of Plan Submission
28/29
Conclusion
- Quality plans
- to show all relevant information
- to comply with technical requirement
- Reduce delay to obtain TFP/FSC