II BILL OF QUANTITIES / SCHEDULE OF RATES Water and... · bill 2: construction of 4 doors vip...

Preview:

Citation preview

II BILL OF QUANTITIES / SCHEDULE OF RATES

RENJA PRIMARY SCHOOL

BILL 1: CONSTRUCTION OF 50 M3 FERRO-CEMENT TANK - 1 NO.

AS PER DRAWING NO. UN-HABITAT-RAIN-2014- FERRO -CEMENT TANK

Item Description Unit Quantity Unit price Ksh.

Total Amount Ksh.

1 Site preparation, trimming and Excavation of tank foundation to remove black cotton/ top soil upto 300 mm

m3 9.0

2 Hardcore filling - well rammed and compacted -300 mm thick m3 9.0

Slab reinforcement

3 Weld mesh- BRC 104 pcs 12

4 Y 10 bars - column pcs 1.0

5 Starter bars for the walls - Y 8 pcs 4

6 Chicken mesh- starter rolls 1.0

Floor concrete

7 Casing of floor slab 100 mm -1.2.4 ratio m3 3

Walls

Reinforcement

8 Y 8 bars pcs 25

9 Chicken mesh- walls rolls 5

Mortar

10 Cast layers of mortar in walls upto 75mm thickness, mix 1:3 with water proof cement

m2 195

Roof

Reinforcement

11 Y 8 bars pcs 38

12 Chicken mesh rolls 3

Mortar

13 Cast layers of mortar in walls upto 60 mm thickness, mix 1:3 with water proof cement

m2 54.0

Item

Description Unit Quantity Unit price Ksh.

Total Amount Ksh.

Formwork

14 Plywood pcs 19

15 Props pcs 40

16 Timber -3 x 2 ft 200

Nails

17 Assorted Kg 10

Fittings

18 GI pipe 11/2" ( 38 mm) pcs 2

19 Elbow 11/2" pcs 12

20 Elbow (¾") pcs 4

21 Socket 11/2" pcs 4

22 ¾" GI pipe (Class B) pcs 2

23 Mosquito screen pcs 2

24 Plug (11/2") pcs 2

25 ¾" nipple pcs 4

26 Thread tape pcs 8

27 ¾" tap (Pegler) pcs 2

Gutters

28 Fix at least 30 m of gutters, connected to the tank through a 3”

medium duty uPVC pipe sum 1

Total amount materials and labour

Add 5% contigiency

Total amount

BILL 2: CONSTRUCTION OF 4 DOORS VIP LATRINE- SANPLAT TYPE- 1 NO.

AS PER DRAWING NO. UN-HABITAT-RAIN-2014-VIP LATRINE BOYS WITH URINAL

Item Description Unit Quantity Unit price Kshs.

Total Amount Kshs.

Excavation

1 Site preparation, trimming and Excavation Soil trimming up to 600 mm depth

m3 16

2 Excavation of 4 pits each measuring 1m diameter and depth not less than 15m

m3 48

Lining of the walls

3 Casting of trapezoidal cement blocks measuring 355 mm x 200 mm x 75mm, with cement/sand 1:7,

m3 4000

4 Y 10 bars -foundation - strip foundation pcs 5

5 Foundation walls - stones/blocks 600 mm m2 16

6 Hardcore filling - 600 mm m3 8

Slab reinforcement

7 Y 10 bars- for squat blocks pcs 2

8 Weld mesh - slab pcs 3.6

Floor concrete

9 Casing of floor slab 100 mm -1.2.4 ratio ( squat blocks separate as per the drawing and removable)

m3 2

Walls

10 Brick walls as per the drawing m2 49

11 Wall pass kg 25

Lintel

13 Reinforcement - 4 Y8 +links pcs 3

14 Lintel concrete m3 0.2

Item Description Unit Quantity Unit price Kshs.

Total Amount Kshs.

15 Timber formwork - 8x1 ft 36

16 Timber formwork - 3x2 ft 50

17 Round poles pcs 3

Roofing

18 Nails 4" kg 2

19 Nails 3" kg 2

20 Nails 2" kg 2

21 Roofing nails kg 1

22 Timber 8"x1" ft 50

23 Timber 3"x2" ft 50

24 Timber 2"x2" ft 80

25 Install Galvanized Iron sheet (30 gauge)- 2.5 m pcs 7

26 Fix roof as per dimension sum 1

Doors

27 Butt joint timber doors ( 1900 x 850) with hinges, locks both inside and outside

No 4

Paints and finishes

Plaster

28 2 layers of plaster ( 15mm )on all walls m2 90

29 Floor screed m2 16

30 Undercoat paint ltrs 4

31 Emulsion paint - 4l - external tin 2

32 Gloss paint - 4l - internal - wet areas tin 2

33 White tiles- urinal wall up to 1.2 m cuttons 3

Item Description Unit Quantity Unit price Kshs.

Total Amount Kshs.

Plumbing

34 Install 4" Vent pipe (10 ft) + vent cover+ screen pcs 4

35 Install uPVC 6" waste pipe - urinal No 1

36 2" - waste pipe uPVC - urinal drain to soak pit No 2

Total amount materials and labour

Add 5% contingency

Total amount

BILL 3: CONSTRUCTION OF 4 DOORS VIP LATRINE- SANPLAT TYPE- 2

AS PER DRAWING NO. UN-HABITAT-RAIN-2014-VIP LATRINE IRLS WITHOUT URINAL

Item Description Unit Quantity Unit price Kshs.

Total Amount Kshs.

Excavation

1 Site preparation, trimming and Excavation Soil trimming up to 600 mm depth

m3 16

2 Excavation of 4 pits each measuring 1m diameter and depth not less than 5m

m3 48

Lining of the walls

3 Casting of trapezoidal cement blocks measuring 355 mm x 200 mm x 75mm, with cement/sand 1:7,

m3 4000

4 Y 10 bars -foundation - strip foundation pcs 5

5 Foundation walls - stones/blocks 600 mm m2 16

6 Hardcore filling - 600 mm m3 8

Slab reinforcement

7 Y 10 bars- for squat blocks pcs 2

8 Weld mesh - slab pcs 4

Floor concrete

9 Casing of floor slab 100 mm -1.2.4 ratio ( squat blocks separate as per the drawing and removable)

m3 2

Walls

10 Brick walls as per the drawing m2 49

11 Wall pass kg 25

Lintel

13 Reinforcement - 4 Y8 +links pcs 3

14 Lintel concrete m3 0.2

15 Timber formwork - 8x1 ft 36

Item Description Unit Quantity Unit price Kshs.

Total Amount Kshs.

16 Timber formwork - 3x2 ft 50

17 Round poles pcs 3

Roofing

18 Nails 4" kg 2

19 Nails 3" kg 2

20 Nails 2" kg 2

21 Roofing nails kg 1

22 Timber 8"x1" ft 50

23 Timber 3"x2" ft 50

24 Timber 2"x2" ft 80

25 Install Galvanized Iron sheet (30 gauge)- 2.5 m pcs 7

26 Fix roof as per dimensions and details sum 1

Doors

27 Butt joint timber doors ( 1900 x 850) with hinges, locks both inside and outside

No 4

Paints and finishes

Plaster

28 2 layers of plaster on all walls m2 90

29 Floor screed m2 16

30 Undercoat paint ltrs 4

31 Emulsion paint - 4l - external tin 2

32 Gloss paint - 4l - internal - wet areas tin 2

Plumbing

33 Install 4" Vent pipe (10 ft) + vent cover+ screen pcs 4

Total amount materials and labour

Add 5% contingency

Total amount

BILL 4: SUPPLY OF HAND WASHING FACILITIES

Item Description Unit Quantity Unit price Kshs.

Total Amount Kshs.

1 Supply 4 No. plastic hand washing basins - 60 litres fixed with GI taps -1/4" type Pegler and a fabricated steel stand

pcs 4

Total amount

SUMMARY- RENJA PRIMARY SCHOOL AMOUNT KSH

1 Bill 1: Construction of 50 m3 Ferro Cement Tank - 1 No.

2 Bill 2: Construction of 4 doors VIP latrine- SANPLAT TYPE- 1 No.

3 Bill 3: Construction of 4 doors VIP latrine- SANPLAT TYPE- 2

4 Bill 4: Supply of hand washing facilities

Project total

MATETE PRIMARY SCHOOL

BILL 1: CONSTRUCTION OF 50 M3 FERRO CEMENT TANK - 1 NO.

As per Drawing No. UN-HABITAT-RAIN-2014- FERRO -CEMENT TANK

Item Description Unit Quantity Unit price Kshs.

Total Amount Kshs.

1 Site preparation, trimming and Excavation of tank foundation to remove black cotton/ top soil up to 300 mm

m3 9

2 Hardcore filling - well rammed and compacted -300 mm thick

m3 9

Slab reinforcement

3 Weld mesh- BRC 104 pcs 12

4 Y 10 bars - column pcs 1

5 Starter bars for the walls - Y 8 pcs 4

6 Chicken mesh- starter rolls 1

Floor concrete

7 Casing of floor slab 100 mm -1.2.4 ratio m3 3

Walls

Reinforcement

8 Y 8 bars pcs 25

9 Chicken mesh- walls rolls 5

Mortar

10 Cast layers of mortar in walls up to 75mm thickness, mix 1:3 with water proof cement

m2 195

Roof

Reinforcement

11 Y 8 bars pcs 37

12 Chicken mesh rolls 3

Mortar

13 Cast layers of mortar in walls up to 60 mm thickness, mix 1:3 with water proof cement

m2 54

Formwork

14 Plywood pcs 19

15 Props pcs 40

16 Timber -3 x 2 ft 200

Item Description Unit Quantity Unit price Kshs.

Total Amount Kshs.

Nails

17 Assorted Kg 10

Fittings

18 GI pipe 11/2" ( 38 mm) pcs 2

19 Elbow 11/2" pcs 12

20 Elbow (¾") pcs 4

21 Socket 11/2" pcs 4

22 ¾" GI pipe (Class B) pcs 2

23 Mosquito screen pcs 2

24 Plug (11/2") pcs 2

25 ¾" nipple pcs 4

26 Thread tape pcs 8

27 ¾" tap (Pegler) pcs 2

Gutters

28 Fix at least 30 m of gutters, connected to the tank through a 3” medium duty uPVC pipe

sum

1

Total amount materials and labour

Add 5% contingency

Total amount

BILL 2: CONSTRUCTION OF 4 DOORS VIP LATRINE

AS PER DRAWING NO. UN-HABITAT-RAIN-2014-VIP LATRINE BOYS WITH URINAL

Item Description Unit Quantity Unit price Kshs.

Total Amount Kshs.

Excavation

1 Site preparation, trimming and Excavation Soil trimming up to 600 mm depth

m3 16

2 Excavation of pit as per dimension up to 5m min

m3 80

Foundation walls

3 Y 10 bars -foundation - strip foundation pcs 5

4 Foundation walls - stones/blocks 600 mm depth

m2 16

5 Hardcore filling - 600 mm m3 8

Slab reinforcement

6 Y 10 bars pcs 5

7 Weld mesh - slab pcs 5

Floor concrete

8 Casing of floor slab 100 mm -1.2.4 ratio( squat blocks separate as per the drawing and removable)

m3 2

Walls

10 Brick walls as per the drawing m2 50

11 Wall pass kg 25

Lintel

13 Reinforcement - 4 Y8 +links pcs 3

14 Lintel concrete m3 0.2

15 Timber formwork - 8x1 ft 36

16 Timber formwork - 3x2 ft 50

17 Round poles pcs 3

Roofing

18 Nails 4" kg 2

19 Nails 3" kg 2

20 Nails 2" kg 2

21 Roofing nails kg 1

22 Timber 8"x1" ft 50

Item Description Unit Quantity Unit price Total

Kshs. Amount Kshs.

23 Timber 3"x2" ft 50

24 Timber 2"x2" ft 80

25 Install Galvanized Iron sheet (30 gauge)- 2.5 m

pcs 7

26 Fix roof as per dimension sum 1

Doors

27 Butt joint timber doors ( 1900 x 850) with hinges, locks both inside and outside

No 4

Paints and finishes

Plaster

28 2 layers of plaster on all walls m2 90

29 Floor screed m2 16

30 Undercoat paint ltrs 4

31 Emulsion paint - 4l - external tin 2

32 Gloss paint - 4l - internal - wet areas tin 2

33 White tiles- urinal wall up to 1.2 m cuttons 3

Plumbing

34 Install 4" Vent pipe (10 ft) + vent cover+ screen

pcs 4

35 Install uPVC 6" waste pipe - urinal No 1

36 2" - waste pipe uPVC - urinal drain to soak pit No 2

Total amount materials and labour

Add 5% contingency

Total amount

BILL 3: CONSTRUCTION OF 4 DOORS VIP LATRINE

AS PER DRAWING NO. UN-HABITAT-RAIN-2014-VIP LATRINE GIRLS WITHOUT URINAL

Item Description Unit Quantity Unit price Kshs.

Total Amount Kshs.

Excavation

1 Site preparation, trimming and Excavation Soil trimming up to 600 mm depth

m3 16

2 Excavation of pit as per dimension up to 5m min

m3 80

Foundation walls - stones

3 Y 10 bars -foundation - strip foundation pcs 5

4 Foundation walls - stones/blocks 600 mm m2 16

5 Hardcore filling - 600 mm m3 8

Slab reinforcement

6 Y 10 bars pcs 5

7 Weld mesh - slab pcs 5

Floor concrete

8 Casing of floor slab 100 mm -1.2.4 ratio ( squat blocks separate as per the drawing and removable)

m3 2

Walls

10 Brick walls as per the drawing m2 50

11 Wall pass kg 25

Lintel

13 Reinforcement - 4 Y8 +links pcs 3

14 Lintel concrete m3 0.2

15 Timber formwork - 8x1 ft 36

16 Timber formwork - 3x2 ft 50

17 Round poles pcs 3

Roofing

18 Nails 4" kg 2

19 Nails 3" kg 2

20 Nails 2" kg 2

21 Roofing nails kg 1

22 Timber 8"x1" ft 50

Item Description Unit Quantity Unit price Kshs.

Total Amount Kshs.

23 Timber 3"x2" ft 50

24 Timber 2"x2" ft 80

25 Install Galvanized Iron sheet (30 gauge)- 2.5 m

pcs 7

26 Fix roof as per dimension sum 1

Doors

27 Butt joint timber doors ( 1900 x 850) with hinges, locks both inside and outside

No 4

Paints and finishes

Plaster

28 2 layers of plaster on all walls m2 90

29 Floor screed m2 16

30 Undercoat paint ltrs 4

31 Emulsion paint - 4l - external tin 2

32 Gloss paint - 4l - internal - wet areas tin 2

Plumbing

33 Install 4" Vent pipe (10 ft) + vent cover+ screen

pcs 4

Total amount materials and labour

Add 5% contingency

Total amount

BILL 4: SUPPLY OF HAND WASHING FACILITIES

Item Description Unit Quantity Unit price Kshs.

Total Amount Kshs.

1 Supply 4 No. plastic hand washing basins - 60 litres fixed with GI taps -1/4" type Pegler and a fabricated steel stand

pcs 4

Total amount

SUMMARY AMOUNT KSH

Bill 1: Construction of 50 m3 Ferro Cement Tank - 1 No.

Bill 2: Construction of 4 doors VIP latrine- SANPLAT TYPE- 1 No.

Bill 3: Construction of 4 doors VIP latrine- SANPLAT TYPE- 1 No.

Bill 4: Supply of hand washing facilities

Project total

Recommended