I-295 Flyover ProjectWestern Henrico County
Why is this being built?
To improve the flow of traffic on I-64 between Route 288 and I-295
• I-64: more than 55,000 cars/day (2005)• Estimate more than 74,000 cars/day by
2026• Congestion at I-64/I-295 interchange,
especially during rush hour
What’s being done?
What about sound walls?
The project calls for two sound walls:
1. Along I-64 east, west of Pouncey Tract Road between I-64 and the Reflections at West Creek complex.
2. Between northbound I-295 towards I-64 and the Twin Hickory neighborhoods of Waters Edge, Cobblestone Landing and Parsons Walk.
Sound wall along I-64 eastbound
Project Milestones
• April 11, 2006 – contractor began work
• Spring 2008 – Pouncey Tract Rd. widening completed
• Spring 2009 – entire project completed
How will construction affect traffic?
Lane closures
I-64 & Pouncey Tract 10 p.m.-6 a.m.I-295 7 p.m.-6 a.m.
I-64 detours to Broad St.
• Between 10:30 p.m. and 5:30 a.m. periodically during the construction
• Sunday-Thursday nights • No detour during certain holidays & special events • Detour maps at www.i295flyover.com
VDOT will announce lane closures and detours several days prior to implementation.
How will information be communicated to the public?
Project web site:
www.i295flyover.comSign up for traffic alerts & other project information
VDOT Public Affairs:
(804) 524-6179
REMEMBER…SAFETY FIRST
Please drive safely through the work zone.
Project-related questions???
Recommended