HERRIMAN CITYPAVEMENT MAINTENANCE PROGRAM Herriman City
Engineering Department
Introduction
Herriman City has experienced tremendous growth over the last several years
Many new subdivisions and associated roads have been constructed in the City
Deterioration
The rapid growth and construction activity has exposed our roads to traffic and heavy loads, which in some cases accelerated the deterioration of our roads
InventoryCurrently Herriman City has as
an inventory of 17,821,898 SF of asphalt road.
A well implemented preventive Road Maintenance plan is needed to take care of our roads and keep them operative and functional.
Preventive Maintenance
Preventive Maintenance not reactive maintenance
Deterioration = Life
Very Cost Effective Applicable for all pavements Right treatment, right pavement, right time Importance of life-cycle cost analysis
Preventive Maintenance
Pavement Life Curve
Starting Early Saves Money
“Every $1 spent in keeping a good road good precludes spending $6-$14 to rebuild one that has deteriorated.”
NowLater
Asphalt Preservation Treatments
Crack seal Patching Fog seal Chip seal Slurry surfacing Overlay Full Depth reclamation
HERRIMAN CITY
Primary Road Maintenance Treatments: Crack seal/ Patching/Slurry seal Mill and Overlay Full depth reclamation (FDR)
Dirt Road pavement
HERRIMAN CITYRoad Maintenance Plan
Recommended 6 Year Slurry Seal
Maintenance Plan
Click icon to add picture
Road Maintenance Plan SummarySlurry Seal Projects
Recommended 6 Year Overlay Maintenance
PlanClick icon to add picture
Road Maintenance Plan SummaryOverlay Projects
Recommended 6 Year Full
Depth Reclamation
Click icon to add picture
Road Maintenance Plan SummaryFull Depth Reclamation
Recommended 6 Year Dirt
Road Paving Plan
Click icon to add picture
Road Maintenance Plan SummaryDirt Road Paving Plan
Road Maintenance
PlanClick icon to add picture
Road Maintenance - Copper Creek
Areas in red are to be sawcut and repaired
Emma Mine Road in Copper Creek
Note size of cracks
Cracks sealed 2009 New cracks formed 2010
Emma Mine and Powder Cove
Cracks sealed 2009 New cracks formed 2010
Emma Mine Road in Copper Creek
Cracks sealed 2009 New cracks formed 2010
Copper Creek Road Repair
Cost of repairs this year in Copper Creek
Cost of repairs in 2007: $25,000 Cost of repairs in same area 2010: $230,000 New roads need a timely schedule of regular
maintenance 5-7 years after Initial Construction
Midas Gold and Claim Staker roads most critical areas
Midas Gold and Claim Staker Way
Cracks sealed 2009 New cracks formed 2010
Midas Gold and Claim Staker Way
Cracks sealed last year
New cracks formed this year
Claim Staker Way and Midas Gold Road
Cost of repairs in 2007: $15,000 Cost of repairs in same area 2010: $175,300 New roads need a timely schedule of regular maintenance
5-7 years after initial Construction
Copper Creek Road Repair
2011 2013 2015 2017 2027 2029 20312019 2021 2023 2025
Fog Seal$37,000
Slurry Seal$100,500 Slurry Seal
$135,000
Slurry Seal$84,000
Pavement Management Option
Slurry Seal$120,000
Future Value: $ 458,000Present Value: $ 255,000
Every Dollar Spent on
Pavement Management
Saves Ten Dollars for Future Repairs!
Budget: ~$23,000 Annually
Budget: ~$235,000 Annually
2011 Pavement Scenario
(Herriman Towne Center & 5600 W)
20312019 2021 2023 2025 2027 20292011 2013 2015 2017
Full DepthReclaimation$3.3. Million
Overlay$1.4 Million
No Pavement Management Option
Future Value: $ 4.7 MillionPresent Value: $ 2.9 Million
5 yrs
5 yr
s
10
yrs
15 yrs
20
yrs
15 yrs
20
yrs
10 yrs
Budget Requirements
Annual Budget Requirements for Current Roadways (18.3 Million Square feet):
Pavement Management Option▪ $853,000
No Pavement Management Option
▪$9.4 Million
Recommended