Agile Project Inception

He Mian2010-11-09

Who am I

He Mian(何勉 ), A agile SW development Practitioner

Beneficiary 

Embracer 

Evangelist

Explorer

works in Alcatel-Lucent Shanghai Bell

mian.he@alcatel-sbell.com.cn

mian.a.he@gmial.com

Agenda

Challenge of Status Quo

Project Inception Inception targetProject goalProject planningArchitecture and Non-functional requirement Concerns

Try it all together

Challenge of Status Quo

Status-Quo

On timeOn budget

Within Scope

Struggling with Quality and always almost get it done

But ...

Unhappy CustomerUnhappy Developer

Unhappy Boss

Suffered Project Manager

Understand Reason of the Dilemma

1. Waterfall model and phase-based earned value management2. Contract Game3. Metrics organization, Functional teams 4. Go to the solution domain too soon5. Defined process over Motivated People6. Separate these who doing the work and who improving the work7. No Gold plating

Plan this Speech in Agile tour Qingdao. 7 sins of traditional Project Management & SW Engineering and Agile Way Out

Lean ThinkingSystem Thinking

Theory of constraint

ScrumXP 

KanbanLSD

MaryBas

DanielLv Yi

TWers

Light in the Dark

Let's start

Compose Cross Functional team

Feed them with Two Pizzas

Bring the Business people in

But, what's next …How to start

Target of Project Inception

Inception - Input

Tech. EvolutionDifferentiation

Product VisionBusiness Case (Return of Investments)Customer Needs

Ideas

Tech. Goals

Constraints

Critical dateBudget ConstraintsTech. constraints

Expectation from Inception

Project Goal

Project Plan

Feasibility , Critical Decision , Risk, Dependencies

Project Goal

Project Goal

For (target customer)

Who (statement of the need or opportunity)

The (product name) is a (product category)

That (statement of key benefit, that is, compelling reason to buy)

Unlike (primary competitive alternative)

Our product (statement of primary differentiation)

For (target customer)

Who (statement of the need or opportunity)

The (product name) is a (product category)

That (statement of key benefit, that is, compelling reason to buy)

Unlike (primary competitive alternative)

Our product (statement of primary differentiation)

Originated from the book “Cross the chasm”

Project Planning

Project Planning

Cost

Scope

TimeScope

Time Cost

fixed

variable

 

Scope

Time Cost

Start from Product Backlog Creation

Time and cost as constraint

Split in Problem DomainSolution DomainProblem Domain

Traditional Way

Agile Way

Splitting at Solution Domain

Splitting at Problem Domain

Why Split in Problem Domain

Quick Feedback

Enable Iteration Development Model

Customer Centric Consideration

Global Thinking for development team

Team collaboration, meaningful discussion

Mandatory for Scrum/XP Adoption

If I had 20 days to solve a problem, I would take 19 days to define it

Data Boundaries

Techniques for Splitting

Operation Boundaries

Scenario based

Non-Functional

Nonfunctional Based

Performance, Scalability … Make it work, make it better

Scenario Based

Meaningful Subset of steps Sunny day path, rainy day path

Operation Boundaries Based

C/R/U/D Connecting, Send the traffic, …

Data Boundaries Based

Subset of data Subset of supported protocol

Techniques for Splitting

What Makes good Product Backlog

Detailed appropriately

Emergent

Estimated

Prioritized

Detailed Appropriately

Fine grained

Coarse grained

Place holder

Priority

Done

Emergent

Originate from the project inception

Adapt with marketing changing

Emerge with the on-going of the product development

Estimated

5

3

13 8

In Relative Size

With Planning Poke

Prioritized

Financial Value

Cost of Development

Knowledge GainedRisk Removal

adjust

adjust

adjust

Now We haveOr

And …What else yet to be planned?

Planning Onion and Rolling wave Plan

Product Vision

Product Roadmap

Release Planning

Sprint Planning

Daily Planning

@ start of each release by PO and Team

@ First day of each sprint by team

@ Daily scrum meeting by team members

Release Planning

• Can be Epic based• Delivery planning or

sprint planning• Business priority as the

primary consideration• With consideration of

dependency and integrity• Compose meaningful

goal for each delivery/sprint

Risk PlanningPossibility

Impact

Risk ItemxxxxxxxxxxxxxxMitigation Action : xxx

Owner: xxxLow Mid High

Low

High

Mid

Tips on Architecture and Non-Functional requirement Concerns

What’s architecture

Architecture is the fundamental organization of a system embodied in its components, their relationships to each other and to the environment and the principles guiding its design and evolution.

-- IEEE-Std-1471-2000

What’s architecture

• What’s the primary determination factors of architecture? -- Non functional requirement

• What’s decision can be deferred and what can not be? -- Driven by risk and cost of change

A Conceptual Flow of the ATAM

From: http://www.sei.cmu.edu/architecture/tools/atam/

Thinnest Slice and Steel Thread

• Tech Risk focused• Just enough work to

prove the concept• Mock is allowed or even

encouraged• Code generated is not

supposed to directly reused

Spikes

• On Architecture decision validation

• On Development Tech.

• On Performance

• On Algorithm

• On User Experience

• On Business Process• On Domain Knowledge

Tips

Facts

Architecture is an ongoing job instead of an one time activity

What ever he does, in reality every SW developer is an Architect

Try

Run design workshop regularly with Engage stakeholders

Prove with real code (spike), don’t be “astronaut architect”

Build thinnest vertical slices to drive the Architecture Skelton out

Do customer-centric features with major architectural impact first

Defer the decision to the last responsive minutes

Performance Concerns -- discussion

What determines the Performance

What determines the theory limitation

What is the actual bottleneck

Why?How?

Try it all together

RiskSpike

Critical arch Decision

User stories

Biz needs, Vision, ROI

Collaboration

Inception (Sprint 0)

Velocity

Sprint Plan Burn Down

Daily Run

Burn UP Iteration Del.

Update

Sprint 1~n

Estimation

Priority

Release Plan

Release Planning

Now, We are on the way!

Inspect and Adapt

Thank You!