"The County Executive shall submit to the Council, not later than January 15 of each even-numbered year, a comprehensive six-year program for capital improvements. The County Executive shall submit to the Council, not later than March 15 of each year, comprehensive six-year program for public services and fiscal policy. The six-year programs shall require a vote of at least five Councilmembers for approval or modification. Final Council approval of the six-year programs shall occur at or about the date of budget approval.”

GSSC CIP and Public Benefit Projects

CIP Project CIP Number Tied to Staging? Y/N Status Additional Information

Muddy Branch Trail Connector N Not funded Associated with JHU Belward development

PSTA Relocation 471102, 470907 Y Funded Target date to open relocated PSTA Spring 2015

Travilah Fire Station 450504 N Funded and under construction http://www6.montgomerycountymd.gov/mcgtmpl.asp?url=/content/DGS/DBDC/RegionalProjectPages/UpcountyProjects/travilah_fire_station_32.asp

LSC Recreation Loop Y Not funded

Corridor Cities Transitway - Funding Y Not funded Planning and Engineering Funding in current Maryland State CTP

Corridor Cities Transitway - Under Construction Y Not funded

Corridor Cities Transitway - Operating Y Not funded

Elementary School N Not funded MCPS Project - Associated with PSTA redevelopment

LSC West Park N Not funded Associated with PSTA redevelopment

LSC Belward Recreation Fields and Trails N Not funded Associated with JHU Belward development

Medical Center Drive Extended Y Not funded

Decoverly Drive Extended N Not funded

Sam Eig Hwy/ Gt. Seneca Hwy Intersection Interchange N Not funded

Key West Avenue Widening N Not funded

Shady Grove Rd/Key West Ave. Intersection Interchange N Not funded

Gt. Senca Hwy/Muddy Branch Rd. Intersection Interchange N Not funded

North Potomac Community Center 720102 N Funded http://www6.montgomerycountymd.gov/mcgtmpl.asp?url=/content/DGS/DBDC/RegionalProjectPages/UpCountyProjects/north_potomac_crc.asp

Travilah Local Park N Not funded

Non-CIP Project

Greater Shady Grove Transportation Management District Y Funded In approved FY 2013 Operating Budget

Other Public Benefit Projects

LSC West Civic Green N Not funded

LSC Central Civic Green N Not funded

GSSC Master Plan LSC West

Gaithersburg West Master Plan M-NCPPC

LSC West: A New Residential Community • PSTA Relocation • Elementary School • Civic Green •Medical Center Drive Extended

16 M-NCPPC

GSSC Master Plan LSC Belward

Gaithersburg West Master Plan M-NCPPC

LSC Belward: Science & Research • Recreation Fields and Trails • Muddy Branch Trail Connector •

17 M-NCPPC

Muddy Branch Trail Connector

GSSC Master Plan

M-NCPPC

Connectivity: The LSC Loop 3.5- mile path connecting: Districts Destinations Belward Farm Schools Traville USG Open Spaces Passive and Active

19

June 10, 2010 M-NCPPC

The LSC Loop

On-Road with CCT On-Road without CCT Off-Road

Distinct from sidewalk Include transitions in high activity areas Enhanced road crossings

Recommended