View
0
Download
0
Category
Preview:
Citation preview
Finance & Administration Committee
Information Item IV-A
April 9, 2015
Financial Status Update and
FMO Progress Report
Page 37 of 58
Washington Metropolitan Area Transit Authority
Board Action/Information Summary
TITLE:
Financial Status Update and FMO Progress Report
PRESENTATION SUMMARY:
Staff will update the Committee on WMATA's overall financial status and on the status of WMATA's Corrective Action Plan (CAP) responses to the Federal Transit Administration's (FTA) Financial Management Oversight (FMO) report. In addition, staff will provide an overviewof the functions and activities of the Internal Compliance Office.
PURPOSE:
Provide an update the Committee on WMATA's overall financial status and on the status of WMATA's Corrective Action Plan (CAP) responses to the Federal Transit Administration's(FTA) Financial Management Oversight (FMO) report. In addition, staff will provide an overview of the functions and activities of the Internal Compliance Office.
DESCRIPTION:
Key Highlights:
Since last month's report:WMATA's FFY2014 PRIIA grant application for $148.5 million was certified by the Department of Labor on March 11. The final grant award is pending the FTA Administrator’s final approval of the program of projects. When awarded, this will bring the total value of grants awarded since January to $733 million.$7 million of federal grant reimbursement funds were successfully drawn.Moody's downgraded WMATA's debt rating one notch from Aa3 to A1.
WMATA committed to 65 CAP items in response to FTA’s FMO findings andadvisory comments. To date, documentation has been submitted for 62 of 65CAPs. Two Material Weakness CAP submissions, originally due September 8,2014, have been extended to June 30, 2015, and the final Advisory Comment CAPhas a committed due date of June 30, 2015.WMATA's Office of Internal Compliance was established and is responsible formonitoring compliance with CAPs.
Background and History:
The FMO report of June 10, 2014, identified nine separate findings, including threematerial weaknesses and six significant deficiencies. An additional five advisory
Action Information MEAD Number:201454
Resolution:Yes No
Page 38 of 58
comments were also identified. A total of 45 recommendations from FTA for addressingthe findings and comments were included in the FMO report.
Discussion:
Since last month's report, the following notable actions have occurred that impact WMATA's overall financial status:
WMATA's FFY2014 PRIIA grant application for $148.5 million was certified by theDepartment of Labor on March 11. The final grant award is pending the FTAAdministrator’s final approval of the program of projects. When awarded, this will bring the total value of grants awarded since January to $733 million.$7 million of federal grant reimbursement funds were successfully drawn.Moody's downgraded WMATA's debt rating one notch from Aa3 to A1.
The FMO Dashboard contains the status as of March 31, 2015 of the 65 CAP items byfinding level, the status of FMO-related training in key areas, a chart illustrating thequality and acceptance level of recent drawdown packages, and a summary of thenumber of FTA recommendations fulfilled based upon CAP submissions. WMATA continues to maintain a cumulative success rate of 98 percent for federal grant reimbursement requests.
Overview of the Internal Compliance ProcessWMATA’s Office of Internal Compliance is responsible for assessing, reviewing, and monitoring WMATA’s adherence to financial management controls and related policies and procedures.
The Office of Internal Compliance (OIC) conducts objective assessments and reviews to monitor WMATA’s adherence to financial management controls and related policies and procedures, with a primary focus on compliance with applicable federal regulations necessary to preserve WMATA’s federal grant eligibility. Reviews are designed to evaluate the design and operating effectiveness of financial management controls, whichincludes internal controls over compliance with applicable regulations and internal policies and procedures.
The OIC fosters a greater awareness of risk management and internal controls by providing related guidance and training.The OIC partners with departments with financial management control responsibility across WMATA to review and evaluate the efficiency and effectiveness of business processes and assists with the implementation of “bestpractices”.
The evaluation of the system of internal controls over financial management is completed using a top-down risk based approach. A top-down risk based approach begins with an understanding of the overall risk of compliance and risks to financial management operations. With clearly defined compliance and financial management objectives, the Office of Internal Compliance is able to identify and assess the risks to meeting these objectives and the level of risk presented by each area of financial management operations. A focus is then placed on entity-level controls and the controlswithin each department and business functions responsible for financial management processes and related controls.
Page 39 of 58
The objective of this approach is to direct higher level of focus to business units and functions that present a higher level of compliance risk to WMATA.
With reasonable understanding of the overall risk of compliance at the entity and the individual business process level, the OIC selects for testing those controls that sufficiently address the assessed risk of compliance. Controls are evaluated as part of individually scheduled reviews defined in an annual Compliance Review Workplan.
The nature, timing, and extent of reviews (test work) completed are in alignment with the related risk level. Reviews are designed to evaluate the design and operating effectiveness of WMATA’s internal controls over compliance with applicable regulations and internal policies and procedures, and to provide reasonable assurance that the risks have been reduced to an acceptable level.
The result of compliance reviews and testing completed are summarized and reported for appropriate resolution. Management will be required to provide a timely corrective action plan for all deficiencies noted. The Office of Internal Compliance will manage all deficiencies identified through resolution with CAP follow up reviews as applicable.
With a primary focus on FMO CAP Follow up, the Office of Internal Compliance developed a work plan which includes a total of 18 scheduled reviews through June 30, 2015.The office of Internal Compliance has completed 3 of the scheduled reviews, 9 are now in progress, and 5 reviews have a future start date.
The initial risk assessment scheduled for completion as of June 30, 2015, will be used to develop a full annual compliance review work plan starting with fiscal year 2016 (July 1, 2015 - June 30, 2016).
FUNDING IMPACT:
TIMELINE:
RECOMMENDATION:
No action required - information item only.
Information item only, no impact on funding.Project Manager: J. Blair Fishburn
ProjectDepartment/Office: CFO
Previous Actions July 2014 through March 2015 - Monthly presentations to FA Committee on FMO status of FTA submissions and CAP items.
Anticipated actions afterpresentation
May 2015 and forward - completion of remaining three CAP items and long-term compliance monitoring.
Page 40 of 58
Financial Status Update andFMO Progress Report
Finance & Administration CommitteeApril 9, 2015
Washington Metropolitan Area Transit Authority
Page 41 of 58
Purpose
• Provide update on WMATA financial status• Provide monthly progress report on FMO
Corrective Action Plans (CAPs), FTA feedback and follow-ups
Page 42 of 58
Financial Update Since Last Month
• FFY2014 PRIIA grant application for $148.5 million certified by Department of Labor:– Grant award is pending FTA Administrator’s
final approval of program of projects– Will bring total value of grants awarded since
January to $733 million
• Grant reimbursement draws of $7 million• Moody’s debt rating downgrade of one
notch (from Aa3 to A1)
Page 43 of 58
FMO Dashboard as of 03/31/2015
Page 44 of 58
FMO Dashboard –CAPs Status by Finding
Page 45 of 58
FMO Dashboard – Reimbursement Request Success Rates
Page 46 of 58
FMO Dashboard –Compliance Training
475
300
200
448
267
171
0 100 200 300 400 500
Procurement
Grants Management
Asset Management
No. Trained Staff Training Estimate
Page 47 of 58
FMO Dashboard – Completionof FMO Recommendations
Page 48 of 58
FMO Summary Timeline
Final FMO Report
received from FTA
June 10, 2014
June 30 –Sept. 30
62 CAP items
submitted to FTA
30-, 60- & 90-day CAP follow-ups received from FTA
Oct. 1 –Oct. 22
Extension dates
submitted to FTA for
two 90-Day CAP Items
Oct. 31
Nov. 5
90-day CAP follow-ups submitted
to FTA
30-, 60- & 90-day CAP follow-ups received from FTA
Dec. 10 -Dec. 22
Dec. 23 –Jan. 30
30-day & 90-day
CAP follow-ups submitted
to FTA
Oct. 15
30- & 60-day CAP
follow-ups submitted
to FTA
90-day CAP follow-ups received from FTA
Feb. 25
March 20
90-day CAP follow-ups submitted
to FTA
Page 49 of 58
• WMATA submitted follow-up responses to FTA on March 20 relating to FMS Access Controls
• WMATA’s Office of Internal Compliance has initiated FMO CAP Self-Assessment Reviews:– Budget Controls– Cash & Grants Management– Federal Financial Reporting– Procurement & Job Order Contracts
Update
Page 50 of 58
Internal Compliance Process Overview
• Established Fall 2014• Director joined WMATA on January 26, 2015
• Monitors adherence to financial management controls• Fosters awareness of risk management and internal
controls by providing related guidance and training• Partners with WMATA’s departments to improve
business process efficiency and effectiveness
WMATA’s Office of Internal Compliance
Responsibilities
Page 51 of 58
Internal Compliance Process Overview (cont.)
Approach and Methodology
Page 52 of 58
Risk-Based Review Process
• Risks assessed on impact and probability of occurrence • Overall risk rating assigned to each area• Initial risk assessment to be completed by June 30, 2015
Internal Compliance Process Overview (cont.)
Insignificant Minor Moderate Significant Major
Low Moderate Elevated High High
Low Low Moderate Elevated High
Low Low Moderate Elevated Elevated
Insignificant Low Low Moderate Moderate
Insignificant Insignificant Low Moderate Moderate
Prob
ability
What is the
likelih
ood of risk
occurren
ce?
ImpactWhat is the potential impact or consequence?
Rare
Almost Certain
Likely
Possible
Unlikely
Page 53 of 58
• Policy Reviews• Risk and Control Reviews • Control Validations • Control Certifications
Results and Corrective Action Plans (CAPs)• Results are analyzed, summarized, and reported • Management required to provide timely corrective
action plans • Deficiencies managed through resolution
Nature of Reviews
Internal Compliance Process Overview (cont.)
Page 54 of 58
Summary of Review Activity
Financial Management Areas
FY Q2 Reviews (Oct‐Dec 2014)
FY Q3 Reviews(Jan‐Mar 2015)
FY Q4 Reviews (Apr‐Jun 2015)
FY 2015
Planned In Progress Completed Planned In Progress Planned Planned Total
Procurement Controls 2 1 1 5 4 1 8
Grant Management Controls 2 0 2 3 3 0 4
Financial Management Controls 0 0 0 2 2 3 6
Totals 4 1 3 10 9 4 18
Plans – Next 6 Months • Complete risk assessment and FY2016 work plan• Compliance and internal control awareness and
accountability • Follow-up activities from completed reviews
Internal Compliance Process Overview (cont.)
Page 55 of 58
• Achieve progress milestones and participate in monthly FTA Region III reviews
• WMATA’s Office of Internal Compliance will continue follow-up reviews of FMO CAPs
Next Steps
Page 56 of 58
Recommended