FDOT District 6 ITS Project Update Manuel Fontan, E.I. ITS Project Manager

Preview:

Citation preview

FDOT District 6FDOT District 6ITS Project UpdateITS Project Update

Manuel Fontan, E.I.

ITS Project Manager

OutlineOutline

ITS Program Updates

Other Deployment Updates

ITS Operations Contract Updates

Operational Updates

ITS Program UpdatesITS Program Updates

US 1/SR 5 Estimated Completion Date: April 25, 2008 4 DMS 17 CCTV 6 Detectors

ITS Program UpdatesITS Program Updates

I-395/SR A1A & Port of Miami Letting Date: October 9, 2007 1 DMS (Port of Miami) 8 CCTV (Mainline); 2 CCTV (Port of Miami) 10 Detectors (Mainline)

ITS Program UpdatesITS Program Updates

SR 826 Letting Date: October 9, 2007 3 DMS 6 New CCTV (4 on Interchanges and 2 for

DMS Verification); 4 Existing 37 Detectors

ITS Program UpdatesITS Program Updates

ITS Technical Consultant Services

Letting Date: Approximately May 2008

Executed: Approximately July 2008

Budget Amount: $ 1.5 Million/5 Years

ITS Program UpdatesITS Program Updates

95 Express (Miami-Dade County) – Phase 1A (SR 112 to GGI) Design Build Initiated Equipment/Devices:

Tow CCTV Toll Rate Signs Lane Status Signs (1 Line DMS)

Estimated Completion Date: Summer 2008 Estimated Completion Date - All phases: Summer 2010

Ramp Metering Initial metering will be for the 8 NB ramps on the 95

Express Lanes limits Turned on simultaneously with 95 Express Lanes

Other Deployment UpdatesOther Deployment Updates

June 2008 FDOT District 6 SunGuide™ TMC Intranet

Release 2.0 RRDIS Release 2.0

ITS Operations Contract UpdateITS Operations Contract Update Notice to Proceed: December 17, 2007

Staff Transitioned: January 14, 2008 24 positions

TMC Operations: 16 Positions 1 TMC Manager 1 Assistant TMC Manager 1 Road Ranger Contract

Manager 2 Shift Supervisor 2 TMC Lead Operators 9 TMC Operators

Contract Support: 3 Positions 1 Contract Project Manager 1 Office Manager 1 Receptionist (Front Desk)

IT: 5 Positions 1 IT/ITS Maintenance Manager 1 Network Administrator 2 IT Administrators 1 Software Systems

Operational UpdatesOperational Updates February 2008

Operational UpdatesOperational Updates February 2008

Operational UpdatesOperational Updates February 2008

Questions?Questions?

Manuel Fontan, E.I.FDOT District 6(305) 499 - 2493

Manuel.Fontan@dot.state.fl.us