E-LASS 2017 Pula

Faserverbund- und Stahl-Standard-Verbindung

11.10.2017

E-LASS 2017

The missing link 2

E-LASS 2017

The missing link – Aim of FAUSST 3

A standardised, class approved, joining method

between

metals (steel) and fibre reinforced materials (GFRP)

– Textile based transition joint as a half-finished

product

– No additional adhesive

– No special processes on the yard; just weld

E-LASS 2017

FAUSST 4

E-LASS 2017

Process chain 5

E-LASS 2017

Process chain 6

E-LASS 2017

Production 7

Source: Fa.Groz-Beckert

Pillar stitch

Alternatives: Tricot, Satin…

Stitch thread

E-LASS 2017

Weft Inlay 8

Weft Inlay

100%

Steel

100%

Glass

Hybrid

Two load transfer mechanism:

• Fibre friction

• Mechanical locking

E-LASS 2017

FAUSST Knitted fabric 9

• Steel – Glass fibre knitted hybrid transition fabric

• Design in close cooperation with Fritz Moll Textilwerke

GmbH &Co.KG. Second design loop in process.

Steel

Hybrid

Glass

E-LASS 2017

Process chain 10

E-LASS 2017

Geometries of the FAUSST connector 11

Different geometries possible….

Monolithic Laminate

Monolithic Laminate

Sandwich construction

E-LASS 2017

Process chain 12

E-LASS 2017

Resistance seam welding 13

E-LASS 2017

Test results: Half-finished product 14

Weld joint

Steel connector

FAUSST Fabric

E-LASS 2017

Process chain 15

E-LASS 2017

Standard Process 16

E-LASS 2017

FRP Structure with Steel frame 17

Manufacturing

supported by

E-LASS 2017

Process chain 18

E-LASS 2017

WIG Welding 19

E-LASS 2017

Prototype 20

Steel Structure

Weld joint

FAUSST connector

(steel)

FAUSST fabric

(several layers)

Weld joint

Composite Structure

E-LASS 2017

Test results 21

F_first

[kN]

F_max

[kN]

Linear

joint

strength

[kN/m]

Strength

[MPa]

6.3 (0.4) 10.8 (1.1) 217 (23) 11 (1)

Specimen details:

4 FAUSST layers

20mm overlap

E-LASS 2017

Outlook 22

• Mechanical characterisation in progress

• Prototype demonstration in progress

Contact Us if interested!

• Second design loop of FAUSST fabric initiated

• Planning transition joint with other materials

Aluminium Glass Carbon

E-LASS 2017

Conclusion 23

• Development of a novel, patent pending, textile based,

transition joint between steel structures and glass fibre

structures

• Joining of dissimilar materials via standard processes

• Mechanical characterization still in progress, but

competitive with adhesive joints.

• Discussion with class for way for approval

E-LASS 2017

24

A research project sponsored by the “industrielle

Gemeinschaftsforsuchung und - entwicklungschung (IGF

18785 BG) by the German Bundesministerium für

Wirtschaft und Energie (BMWi)

Schweißtechnische Lehr- und

Versuchsanstalt Mecklenburg-

Vorpommern GmbH

Center of Maritime Technologies e.V.

Alter Hafen Süd 4, 18069 Rostock Bramfelder Str. 164, 22305 Hamburg

Director:

Dr. Rigo Peters

Director:

Mr. Ketelhohn

Project leader: Dr. Rigo Peters Project leader: Dr. Lars Molter

Contact details:

Tel.: 0381/8115018

peters@slv-rostock.de

Contact details:

Tel.: 040/692087641

molter@cmt-net.org

E-LASS 2017

25Thank you!

Contacts and questions welcome at

luterbacher@cmt-net.org

Thank you for your attention!

www.fausst.com

E-LASS 2017 Pula 28.04.2017

Recommended