DECEMBER 2017

MID -2023

Q42018

Q42022

PROJECTAWARD

ADVANCEHEAVY

CONSTRUCTION

END HEAVY

CONSTRUCTIONSUBSTANTIALCOMPLETION

LEAD DESIGNERLEAD OUTREACH

DESIGN BUILD • Award Date: December 2017

• Project Budget Contained In:Approved 2015-2019 Capital Plan: $2,050M Future 2020-2024 Capital Plan: $ 538M

• Contract Type: Design-Build

1

LIRR Committee Report March 2018

FLORAL PARK

HICKSVILLE

EXPANSIONPROJECT

Widening of Floral Park Viaduct

2

Getting Ready for Bridge Reconstruction at Plainfield Ave

3

Getting Ready for Road Closure at Covert Ave Grade Crossing

4

Getting Ready for Platform Demolition at Merillon Ave Station

5

Installing SOE at Harrison Ave Garage in Mineola

6

Installing SOE at Cherry Lane Ave Bridge Abutments

7

Reconstruction of Carle Place Station

8

Constructing Urban Avenue Grade Crossing in Westbury

9

Keeping Communities Informed

10

Keeping Communities Up To date

11

https://lirrexpansion.com/http://www.amodernli.com/project/thirdtrack/

Keeping Communities Satisfied

12

Community Scorecard of Design-Builder Performance

Our Performance

• 98% of all submittals are returned within contract limits

• 9 day average submittal turnaround• Less than 2% outages cancelled by

LIRR• All invoices received since June 2018

are paid within 15 days

13

-

5

10

15

20

25

30

35

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

Days

Invoice Number

Invoice Payments

30.5%

62.6%

1.9%3.5%

0.0% 1.6%2.2%

Summary Use of Contractually Available Outages

Contractual Outages Used

Contractual Outages Not Used

Outages Cancelled by 3TC

Last Minute Cancellations byLIRROutages Cancelled by LIRRAdvance NoticeOutages Not Approved

Extra Outages Provided

Recommended