EVM and Main Linac Prototype Modules - CLIC B. Daudin – GS-AIS-PM

Preview:

Citation preview

EVM and Main Linac Prototype Modules - CLIC

B. Daudin – GS-AIS-PM

2

EVM and Main Linac Prototype Modules - CLIC

Quick overview of Earned Value Management (EVM)

APT / EVM and Main Linac Prototype Modules

In practise

08-Mar-2010

3

Earned Value Management (EVM)

•Help Project Managers to measure project progress in a objective manner

Why•Work

estimates

•Resource definition

•Progress reporting

How

•Early warnings on performance problems

Results08-Mar-2010

4

EVM basics

EVM metrics (schedule and cost variances)

Planned Value (PV) : work

planned

Earned Value (EV) : work

doneActual Cost

(AC) : resources

spent

All metrics are expressed in the same unit (CHF) along the time

08-Mar-2010

5

Accomplishment of work analysis

Schedule Variance

Cost Variance

08-Mar-2010

6

EVM in APT

•wider scope : CERN resource planning tool

APT: Activity Planning Tool

•WBS : hierarchical structure representing CERN activities

•Workunits

EVM : specific component of

APT

08-Mar-2010

7

EVM workunits for“Main Linac Prototype Modules”

•FRC-CMS-RF-TEST•RF TEST

CLIC•RF TEST

CLEX

WBS node or activity

•holder•Material

Resources - Budgets

•Deliverables – dates and quantities

Workunits:

08-Mar-2010

8

How to work with an EVM project

• Already done by Tiia• Write access on your workunits

Project definition

• Progress report screen• Every first Monday of the month, an email requiring progress reporting• If delay in progress reporting (no report in the last 4 weeks), a reminder is sent on

Monday of each week• If no progress, report it

Progress reporting by workunit holders

• Chart at the workunit level• Chart for the whole project• Crosstab on the whole project

Project monitoring

08-Mar-2010

10

Progress report screen

08-Mar-2010

back

11

Reminders

08-Mar-2010

back

12

Workunit EVM chart

08-Mar-2010

back

13

WBS EVM chart

08-Mar-2010

back

Recommended