EUT443 – Engineering Management Chapter 1 The World of Project Management

Preview:

Citation preview

EUT443 – Engineering Management

Chapter 1

The World of Project Management

EUT443 – Engineering Management

WHAT IS A PROJECT?

EUT443 – Engineering Management

Why the emphasis on project management?• Many tasks do not fit neatly into business-

as-usual.

• Need to assign responsibility and authority for achievement of organizational goals.

EUT443 – Engineering Management

Characteristics of Projects

• Unique

• Specific Deliverable

• Specific Due Date

EUT443 – Engineering Management

Other Common Characteristics of Projects• Multidisciplinary

• Complex

• Conflict

• Part of Programs

EUT443 – Engineering Management

PMI Definition

“A temporary endeavor undertaken to create a unique product or service”

Project Management Institute, 2000

EUT443 – Engineering Management

PROJECT MANAGEMENT VS. GENERAL MANAGEMENT

EUT443 – Engineering Management

Skill Requirements for Effective Project Management• Conflict Resolution

• Creativity and Flexibility

• Ability to Adjust to Change

• Good Planning

• Negotiation– win-win versus win-lose

EUT443 – Engineering Management

WHAT IS MANAGED? THE THREE GOALS OF A

PROJECT

EUT443 – Engineering Management

Figure 1-1: Performance, Cost, and Time Project Targets

EUT443 – Engineering Management

THE LIFE CYCLES OF PROJECTS

EUT443 – Engineering Management

Figure 1-2 The Project Life Cycle

EUT443 – Engineering Management

Figure 1-3 An Alternate Project Life Cycle

EUT443 – Engineering Management

SELECTING PROJECTS

EUT443 – Engineering Management

Nonnumeric Selection Methods• The Sacred Cow

• The Operating/Competitive Necessity

• Comparative Benefits

EUT443 – Engineering Management

Figure 1-4 The Q-Sort Method

EUT443 – Engineering Management

Numeric Selection Methods

• Financial Assessment Methods– payback period– discounted cash flow

• Scoring Methods– unweighted 0-1 factor method– weighted factor scoring method

EUT443 – Engineering Management

Payback Period

InflowsCash Net Annual

Investment Fixed Initial

EUT443 – Engineering Management

Discounted Cash Flow

n

tt

t

k

F

10 )1(

I- (project) NPV

where

I0 = the initial investment

Ft = the net cash flow in period t

k = the required rate of return or hurdle rate

EUT443 – Engineering Management

The Weighted Scoring Model

n

jjiji wsS

1

where

Si = the total score of the ith project

sij = the score of the ith project on the jth criterion

wj = the weight or importance of the jth criterion

EUT443 – Engineering Management

Confronting Uncertainty – The Management of Risk

EUT443 – Engineering Management

What uncertainties are encountered in project management?• Time required to complete a project

• Availability of key resources

• Cost of resources

• Timing of solutions to technological problems

• Actions taken by competitors

EUT443 – Engineering Management

Can uncertainty surrounding projects ever be eliminated?• No, but it can be managed

EUT443 – Engineering Management

Risk Analysis

• Estimate probabilities or distributions associated with key parameters

• Develop analytic or simulation model

• Analyze distribution of outcomes generated by model

EUT443 – Engineering Management

Risk Analysis with Crystal Ball• Assumption Cells

• Distribution Gallery

• Forecast Cells

EUT443 – Engineering Management

THE PROJECT PORTFOLIO PROCESS

EUT443 – Engineering Management

The Project Portfolio Process

• Step 1: Establish a Project Council• Step 2: Identify Project Categories and Criteria• Step 3: Collect Project Data• Step 4: Assess Resource Availability• Step 5: Reduce the Project and Criteria Set• Step 6: Prioritize the Projects within Categories• Step 7: Select the Projects to be Funded and

Held in Reserve• Step 8: Implement the Process

EUT443 – Engineering Management

The Aggregate Project Plan

EUT443 – Engineering Management

Figure 1-12 An Example Aggregate Project Plan

EUT443 – Engineering Management

Copyright

Copyright John Wiley & Sons, Inc.

All rights reserved. Reproduction or translation of this work beyond that permitted in Section 117 of the 1976 United States Copyright Act without express permission of the copyright owner is unlawful. Request for further information should be addressed to the Permissions Department, John Wiley & Sons, Inc. The purchaser may make back-up copies for his/her own use only and not for distribution or resale. The Publisher assumes no responsibility for errors, omissions, or damages, caused by the use of these programs or from the use of the information herein.

Recommended