Elementary 33 Construction Update

Preview:

DESCRIPTION

Elementary 33 Construction Update. June 27, 2013. Michael E Finn. Overview. Preconstruction Phase General Specifications of Plans Milestones Site and Floor Plans. Preconstruction. Drawings Conceptual drawings completed Construction documents completed by July 1 - PowerPoint PPT Presentation

Citation preview

1

Elementary 33 Construction UpdateJune 27, 2013

Michael E Finn

2

• Preconstruction Phase• General Specifications of Plans• Milestones• Site and Floor Plans

Overview

3

• Drawings– Conceptual drawings completed– Construction documents completed by July 1– Plan submitted to city by July 8

• Subcontractors selected and Guaranteed Maximum Price by August 1

• Permits issued by September 13

Preconstruction

4

• Vehicle queuing and site layout– Significant adjustments made to accommodate city

requirements for queuing and traffic• Questions regarding zoning and the application of

zoning to School Districts– Open item and all parties continue to work with the city

• Total project expense– Many adjustments have been made to reduce expenses– Project still over $16M budget

• Adjacent ways funds to bridge the gap

Hurdles in Preconstruction

5

• Total space of 96,000 square feet in 2 main buildings

• Gymnasium remains separate from dining area– Gymnasium/Dining wing 23,200 square feet– Educational wing 72,800 square feet

• Classrooms– 4 classrooms per grade– 970 square feet K-3– 850 square feet 4-8

General Specifications of Site

6

• Permits issued by the city – September 13• Ground breaking ceremony – August 21• Leadership for site announced – January • Positions filled for 2014-2015 School Year - June• Certificate of occupancy issued – July• FF&E completed - July• Doors open for employees - August• Doors open for students - August

Milestone dates

7

Site Plan April 2013

8

New Site Plan 6-10-13

9

Page of Floor Plan 6-10-13

10

QUESTIONS

Recommended