1. Introductions
2. Project Update
3. Design Review
Site Plan
Floor Plans
3D Views/ Perspectives
4. Environmental Sustainability
5. Schedule
6. Comments / Next Steps
EDGEWOOD RECREATION CENTER
PROJECT UPDATE
• Revised Building Design
• Additional Funding
• Agency Review
Commission of Fine Arts (CFA)
EDGEWOOD RECREATION CENTER
PROGRESS SITE PLAN
EDGEWOOD RECREATION CENTER
PLAN - FIRST FLOOR
PROGRESS FLOOR PLANS
EDGEWOOD RECREATION CENTER
PLAN - SECOND FLOOR
PROGRESS FLOOR PLANS
PROGRESS 3D VIEW
EDGEWOOD RECREATION CENTER
PROGRESS 3D VIEW
EDGEWOOD RECREATION CENTER
PROGRESS 3D VIEW
EDGEWOOD RECREATION CENTER
PROGRESS 3D VIEW
EDGEWOOD RECREATION CENTER
EDGEWOOD RECREATION CENTER
ENVIRONMENTAL SUSTAINABILITY
• LEED Silver Certification
• Urban Farm
• Photovoltaic Panels
• Rain Garden/Bio-Retention
• Rain Water Harvesting
• Storm Water Management
• Water Reuse Reduction
• Daylighting Interior Spaces
• Green Building Education
• Permeable Surfaces
• Recycled Content
EDGEWOOD RECREATION CENTER
SCHEDULE
Design………….Winter 2016
Bidding/Award…Spring 2017
Construction…...Summer 2017/
Summer 2018
EDGEWOOD RECREATION CENTER