Douglas R. Failing, P.E. Executive Director, Highway Program

LA Metro’sHighway Program

LA Metro’sHighway Program

May 10, 2013

Construction Management Association of America (CMAA)

Highway ProjectsHighway Projects

2

3Possible problem Major issue!On targetOK

State Route 710 NorthState Route 710 North

Construction CompleteConstruction CompleteCurrent

2029Current

2029Forecast

2029Forecast

2029

SCHEDULESCHEDULE

Alternatives Analysis Fall 2012Draft EIR/EIS Spring 2014Public Hearing Spring 2014Final EIR/EIS Summer 2015Record of Decision Summer 2015

Total Cost ($ mil.)Total Cost ($ mil.)

Current$780

Current$780

Forecast$2.6 – 5.4B*

Forecast$2.6 – 5.4B*

BUDGETBUDGET

Secured Funds: Measure R - $780MUnsecured Funds: $1.82B – $4.62B*Potential P3 Opportunity

!

* Denotes a range of cost for several higher cost alternatives

OK

• Alternatives Analysis – completed in Dec. 2012• http://www.dot.ca.gov/dist07/resources/envdocs/docs/710s

tudy/

• Alternatives:– No Build– Transportation System Management/Transportation

Demand Management (TSM/TDM) – Bus Rapid Transit (BRT)– Light Rail Transit (LRT)– Freeway Tunnel

4

State Route 710 NorthState Route 710 North

State Route 710 North Build State Route 710 North Build AlternativesAlternatives BRT LRT Freeway Tunnel*

5

6Possible problem Major issue!On targetOK

Cost

Interstate 710 South EIR/EIS*Interstate 710 South EIR/EIS*

Construction CompleteConstruction CompleteCurrent

2028Current

2028Forecast

2028Forecast

2028

SCHEDULESCHEDULE

Draft REIR/REIS 2014 2014 Public Hearing 2014 2014 Final REIR/REIS 2015 2015 Record of Decision 2015 2015

Multiple Early Action Study Projects with various schedules

Total Cost ($ mil.)Total Cost ($ mil.)

Current$395

Current$395

Forecast$6.75B

Forecast$6.75B

BUDGETBUDGET

Secured Funds: Measure R - $395MUnsecured Funds: $6.36B – TBD*Potential P3 Opportunity

!

Begin Construction 2020 2021

*Some of these funds will be utilized for I-710 Early Action Projects

!

7Possible problem Major issue!On targetOK

I-710 Early Action ProjectsI-710 Early Action Projects

Total Cost ($ mil.)Total Cost ($ mil.)

Current$26.8

Current$26.8

Forecast$26.8

Forecast$26.8

BUDGETBUDGET

SCHEDULESCHEDULE

various (see below)

Completed 0 $ 000 N/AOngoing 1 $10,400 2013Future 4 $16,400 2018

TOTAL* 5 $26,800 2030

#APPR. PROJECTSBUDGET

(000’S) COMPLETION

*Multiple projects to be programmed with various schedules through 2030

8Possible problem Major issue!On targetOK

Cost

High Desert Corridor (Environmental)High Desert Corridor (Environmental)

Total Cost ($ mil.)Total Cost ($ mil.)

Current$65

Current$65

Forecast$65

Forecast$65

BUDGETBUDGET

Funds include: STIP (GF), Measure R, Measure I, and federal earmarks• Scope includes Project Approval and Environmental Document (PA/ED) only

Environmental Document CompleteEnvironmental Document Complete

Current2014

Current2014

Forecast2014

Forecast2014

SCHEDULESCHEDULE

Draft ED CirculationPublic Hearing Final EDRecord of Decision

2013201320142014

OK

9Possible problem Major issue!On targetOK

Total Cost ($ mil.)Total Cost ($ mil.)

Current$700

Current$700

Forecast$700

Forecast$700

BUDGETBUDGET

Funds include: Measure R, Prop C 25%, Toll Revenues and SHOPP

OK

PROJECTS UNDER CONSIDERATION:• I-5 North Capacity Enhancements (Phase 2A: Truck Lane + HOV from SR-14 to Parker Rd.)•I-5 Pavement Rehabilitation • SR-71 Expressway Gap Closure (from I-10 to Mission Blvd.)• SR-71 Expressway Gap Closure (from Mission Blvd. to Rio Rancho Rd.)• Soundwall Package 10: I-210 Pasadena and Arcadia• Soundwall Package 11: I-405 & SR 170 in Los Angeles

Construction CompleteConstruction CompleteCurrent

2030Current

2030Forecast

2019Forecast

2019

SCHEDULESCHEDULE

RFQRFP Financial CloseConstruction Complete

OK

2013 2013/14 2014/15 2019

2013 2013/14 2014/15 2019

Accelerated Regional Transportation Improvements Accelerated Regional Transportation Improvements (ARTI) Project(ARTI) Project

10Possible problem Major issue!On targetOK

Construction CompleteConstruction CompleteCurrent

2026Current

2026Forecast

2026Forecast

2026

SCHEDULESCHEDULEOK

• Multiple projects to be programmed with various schedules through 2030

• Feasibility Study 2012

• Project Study Report 2013

• Preliminary Engineering 2014-2015

Total Cost ($ mil.)Total Cost ($ mil.)

Current$590M*Current$590M*

Forecast$590M*

Forecast$590M*

BUDGETBUDGET

Secured Funds: Measure R - $590MUnsecured Funds: TBD

*Denotes current secure funding and not expected to cover Feasibility Study improvement needs. Project costs to be determined post Feasibility Study

I-605 Corridor “Hot Spot” InterchangesI-605 Corridor “Hot Spot” Interchanges

1111Possible problem Major issue!On targetOK

Completed 1 $ 575 N/AOngoing 7 $ 15,573 2018Future 32 $ 40,852 2020

TOTAL 40 $57,000 2020

Measure R provides $170.0 Million over 30 years of which $57 Million has been programmed in the Subregion for FYs 2010-2016. Ongoing is defined as projects with executed Funding Agreements. Future is defined as projects with future phases of existing Projects or first years funding of a Project is beyond FY 2013.

Total Cost ($ mil.)Total Cost ($ mil.)

Current$32.4

Current$32.4

Forecast$170

Forecast$170

BUDGETBUDGET SCHEDULESCHEDULE

various (see below)

#APPROVED PROJECTS

BUDGET (000’S)

COMPLETION

Arroyo Verdugo COG Measure R Operational Arroyo Verdugo COG Measure R Operational Improvements ProgramImprovements Program

1212Possible problem Major issue!On targetOK

Completed 0 $ 0 N/AOngoing 9 $ 25,661 2018Future 7 $ 66,139 2020

TOTAL 16 $91,800 2020

Measure R provides $175.0 M over 30 years, $93.8 Million has been programmed for the Subregion by the Metro Board for FY’s 2010-16. Ongoing is defined as projects with executed Funding Agreements. Future is defined as projects with future phases of existing Projects or first years funding of a Project is beyond FY 2013.

Total Cost ($ mil.)Total Cost ($ mil.)

Current$91.8

Current$91.8

Forecast$175

Forecast$175

BUDGETBUDGET SCHEDULESCHEDULEvarious (see below)

COMPLETIONBUDGET

(000’S)#APPROVED PROJECTS

Las Virgenes/Malibu COG Measure R Operational Las Virgenes/Malibu COG Measure R Operational Improvements ProgramImprovements Program

1313Possible problem Major issue!On targetOK

COG Admin/Development N/A $ 6,754 2022Contingency/Reserves N/A $ 25,077 2019Completed 3 $ 2,152 2012Ongoing 18 $ 63,351 2022Future 36 $ 94,806 2022

TOTAL 57 $192,140 2022

Measure R provides $906.0 Million over 30 years of which $192.1 Million has been programmed in the Subregion for FYs 2012-2019. Ongoing is defined as projects with executed Funding Agreements. Future is defined as projects with future phases of existing Projects or first years funding of a Project is beyond FY 2013.

Total Cost ($ mil.)Total Cost ($ mil.)

Current$176.5

Current$176.5

Forecast$906

Forecast$906

BUDGETBUDGET SCHEDULESCHEDULEvarious (see below)

#APPROVED PROJECTS

BUDGET (000’S)

COMPLETION

South Bay (I-405, I-110, I-105 and SR-91) Ramp and South Bay (I-405, I-110, I-105 and SR-91) Ramp and Interchange Operational Improvements ProgramInterchange Operational Improvements Program

Upcoming Procurements Upcoming Procurements A&E Professional Services, Motorist Services & P3 ServicesA&E Professional Services, Motorist Services & P3 Services

14

http://www.metro.net/projects/pm-dept/(Highway Program Look Ahead Reports)

Highway Projects in ConstructionHighway Projects in Construction

15

http://www.metro.net/projects/pm-dept/(Highway Program Look Ahead Reports)

Questions?Questions?

Douglas R. Failing, P.E.

Executive Director – Highway Program

Los Angeles County Metropolitan Transportation Authority – Metro