View
215
Download
0
Category
Preview:
DESCRIPTION
doc.: IEEE /0054r0 Submission Agenda and Results The TG focused on comment resolutions with 59 technical and 9 general comments open The TG heard several contributions related to the comments and many of them were accepted as comment resolutions –All the comments were addressed This gives the TG an opportunity to ask the WG chair to submit an updated draft into WG re-circulation LB Draft meeting minutes available in 19-13/0037r3 Approved comment resolutions available in /0204r9 March 2013 Mika Kasslin, NokiaSlide 3
Citation preview
doc.: IEEE 802.19-13/0054r0
Submission Mika Kasslin, Nokia
March 2013
Slide 1
TG1 Closing Report for March 2013
Notice: This document has been prepared to assist IEEE 802.19. It is offered as a basis for discussion and is not binding on the contributing individual(s) or organization(s). The material in this document is subject to change in form and content after further study. The contributor(s) reserve(s) the right to add, amend or withdraw material contained herein.
Date: 2013-03-21
Authors:Name Company Address Phone email Mika Kasslin Nokia Otaniementie 19,
02150 Espoo, Finland +358-50-4836294 mika.kasslin@nokia.com
doc.: IEEE 802.19-13/0054r0
Submission Mika Kasslin, Nokia
March 2013
Slide 2
Abstract
This is TG1 closing report from March 2013 plenary meeting in Orlando, FL, USA
doc.: IEEE 802.19-13/0054r0
Submission Mika Kasslin, Nokia
Agenda and Results• The TG focused on comment resolutions with 59
technical and 9 general comments open• The TG heard several contributions related to the
comments and many of them were accepted as comment resolutions– All the comments were addressed
• This gives the TG an opportunity to ask the WG chair to submit an updated draft into WG re-circulation LB
• Draft meeting minutes available in 19-13/0037r3• Approved comment resolutions available in 19-
12/0204r9
March 2013
Slide 3
doc.: IEEE 802.19-13/0054r0
Submission Mika Kasslin, Nokia
What’s Next?
1. The TG requested the TG editor to prepare by April 4th, 2013, a new 802.19.1 draft for WG re-circulation LB
2. The TG kindly asks the 802.19 WG chair to start a 25-day WG Re-circulation Letter Ballot on a new 802.19.1 draft no later than April 8th, 2013
March 2013
Slide 4
doc.: IEEE 802.19-13/0054r0
Submission Mika Kasslin, Nokia
Tentative Schedule
• wk-Mar25• wk-Apr01: New draft released by the TG editor• wk-Apr08: WG re-circulation ballot opens• wk-Apr15• wk-Apr22• wk-Apr29: WG re-circulation ballot closes• wk-May06• wk-May13: May 2013 interim meeting
March 2013
Slide 5
doc.: IEEE 802.19-13/0054r0
Submission Mika Kasslin, Nokia
Teleconferences
• The TG will have no teleconferences before the May 2013 interim
March 2013
Slide 6
doc.: IEEE 802.19-13/0054r0
Submission Mika Kasslin, Nokia
May 2013 Interim Objectives
• Continue comment resolutions and resolve all the remaining comments– After this meeting we have still 63 technical and general
comments open• Have the draft prepared for a recirculation WG LB
after the March 2013 meeting so that the ballot closes before the May 2013 interim
• Decide on whether the 802.19.1 draft is ready to be made available for IETF PAWS
March 2013
Slide 7
doc.: IEEE 802.19-13/0054r0
Submission Mika Kasslin, Nokia
Targeted TG1 Timeline
• Second Working Group Letter Ballot: October 2012• Recirculation Letter Ballot: March 2013• Recirculation Letter Ballot: July 2013• Form Sponsor Ballot Pool: July 2013• Initial Sponsor Ballot: November 2013• Recirculation Sponsor Ballot: March 2014• Final WG/EC Approval: July 2014• RevCom/Standards Board Approval: September 2014
March 2013
Slide 8
Recommended