| DER INTERCONNECTION GUIDE
Brooks, Alberta
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 2
| DER INTERCONNECTION GUIDE
Contents
DISCLAIMER ........................................................................................................................................... 2
OVERVIEW .............................................................................................................................................. 3
PHASE 1 PRE-APPLICATION CONSULTATION ................................................................................. 4
PHASE 2 HIGH LEVEL STUDY (HLS): APPLICATION AND STUDY ................................................... 5
PHASE 2.1 APPLICATION FOR HIGH LEVEL STUDY ........................................................................... 5
PHASE 2.2 HIGH LEVEL STUDY ............................................................................................................ 6
PHASE 3 DETAILED LEVEL STUDY (DLS): APPLICATIONS AND DESIGN ....................................... 8
PHASE 3.1 APPLICATION FOR DISTRIBUTION DETAILED LEVEL STUDY ......................................... 8
PHASE 3.2 DISTRIBUTION DETAILED LEVEL STUDY AND DESIGN ................................................... 9
PHASE 3.3 TRANSMISSION DETAILED STUDY AND DESIGN ........................................................... 10
PHASE 4 INTERCONNECTION PROPOSAL ..................................................................................... 12
PHASE 5 CONSTRUCTION ............................................................................................................... 13
PHASE 5.1 PRE-CONSTRUCTION ...................................................................................................... 13
PHASE 5.2 CONSTRUCTION ............................................................................................................... 14
PHASE 5.3 COMMISSION .................................................................................................................... 15
PHASE 6 OPERATE .......................................................................................................................... 16
ANNEX A MILESTONES FLOWCHART (INFORMATIVE) ............................................................... 17
ANNEX B DER INTERCONNECTION FLOWCHART (INFORMATIVE)............................................ 18
ANNEX C DOCUMENTS AND FORMS (INFORMATIVE)................................................................. 31
ANNEX D GLOSSARY OF ACRONYMS (INFORMATIVE) ............................................................... 32
Disclaimer
LIMITATION OF LIABILITY AND DISCLAIMER This document is not a replacement for electrical codes or
other applicable standards. This document is not intended or provided as a design specification or as an
instruction manual. The DER owner, employees or agents recognize that they are, at all times, solely
responsible for the generator plant design, construction and operation. FortisAlberta Inc. (FAI), and any person
employed on its behalf, makes no warranties or representations of any kind with respect to the DER
requirements contained in this document, including, without limitation, its quality, accuracy, completeness or
fitness for any particular purpose, and FAI will not be liable for any loss or damage arising from the use of this
document, any conclusions a user derives from the information in this document or any reliance by the user on
the information it contains. FAI reserves the right to amend any of the requirements at any time. Any person
wishing to make a decision based on the content of this document should consult with FAI prior to making any
such decision.
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 3
| DER INTERCONNECTION GUIDE
Overview
This guide outlines the Distributed Energy Resources (DER) interconnection with FortisAlberta and explains
the phases for DER projects, including Distributed Generation (DG). Each phase includes these components:
• Purpose
• Key Matters
▪ The information contained in these sections is intended to capture the important, fundamental considerations for the project development to be reviewed. The lists are intended as general conversation starters at the beginning stages of each phase that will lead into more comprehensive discussions as the project progresses.
▪ The Key Matters are not exclusive to the specific project phase in which they are listed. Each topic listed can be utilized in conversations for other phases. The Key Matters listed do not represent all the requirements for a project. Detailed Requirements are captured in subsequent sections.
• Milestones
• Customer Requirements
▪ The technical requirements to be met for each phase.
• FortisAlberta Roles and Responsibilities
• Queue
▪ This section of each phase outlines the practices FortisAlberta has implemented to administer the Substation Feeder Capacity Queue (the DER Queue). The objectives of the DER Queue Management Practices are as follows:
▪ Ensure fair and non-discriminatory treatment of DER projects
▪ Ensure efficient progression of DER projects through the interconnection process
▪ Clarify key queuing milestones in the interconnection process
▪ Align FortisAlberta’s queueing practices with Alberta Electric System Operator’s (AESO) Stage 2 On Hold for Behind the Fence (BTF) projects
▪ FortisAlberta’s DER Queue phases and timelines are applicable to every customer’s project, regardless of the number of projects waiting to connect at a substation feeder.
▪ To remain in the DER Queue, customers must complete all the requirements in each interconnection phase within the time frames outlined. Any significant change to the approved scope of a project will result in the need for the project to be re-started and the risk of losing the project’s position in the DER Queue.
▪ If the DER Queue Management Practice requirements are not met, the project will be removed from the DER Queue. When projects are removed from the DER Queue, contingent projects will be considered next-in-line and those customers will be notified of the change with the corresponding updated High Level Study (HLS) or Detailed Level (DLS) Study (cost and available capacity).
NOTE: Milestones along with Roles and Responsibilities have visual flowcharts in Annex A and B respectively.
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 4
| DER INTERCONNECTION GUIDE
Phase 1 Pre-Application Consultation
Purpose
To assist customers who are new to DER to understand the overall connection process and investigate
hosting capacity at their sites of interest prior to entering the DER Queue. This is an information gathering and
project scoping phase to help customers select a feasible location. A Hosting Capacity map is also available
along with a project list by feeder, Hosting Capacity (fortisalberta.com).
Key Matters
(conversation starters)
1. Overall process – DER Interconnection Guide overview
2. Distributed Generation | FortisAlberta and Distributed Generation Library | FortisAlberta
3. Hosting Capacity Map & Distribution Generation Project List Hosting Capacity (fortisalberta.com)
3.1 Capacities of feeders and substations / Existing Connected Generators/Impact of “zero” load
3.2 Location of substation and project location
4. DER Application for HLS required to initiate a project
5. Customer proposed generator capacity
6. Application Fees for studies for application and different phases
7. An authenticated DER owner Single Line Diagram (SLD) will be required for the Detailed Level Study
(DLS)
8. Option M is an option now and will not be ongoing
Milestones
1. This is an optional step, however, it is recommended to help new customers understand the DER
Interconnection process, who is involved, and most importantly, where to find a location to successfully
connect the project.
2. Our consultation fees start at $500 to review up to five project locations. A fee of $250 will be added for
each additional location. Customers may submit a Pre-Application Request to
generation@fortisalberta.com.
Customer Requirements
1. Review the Hosting Capacity Map.
2. Review the DER-02 FortisAlberta Interconnection Requirements and other technical documents in the
Distributed Generation Library | FortisAlberta
FortisAlberta Roles and Responsibilities
1. All communication, deliverables, and invoicing are completed within the Customer Connections group.
2. Stakeholder Relations Manager (SRM) to discuss and provide high level assessment of potential customer
sites.
Queue
A project does not enter the DER Queue during this phase.
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 5
| DER INTERCONNECTION GUIDE
Phase 2 High Level Study (HLS): Application and Study
Purpose
For the customer to formally initiate the connection process, secure a spot in the distribution capacity queue,
and receive a high level assessment of generation interconnection requirements and a ballpark cost estimate
for interconnection. See phases 2.1 and 2.2 for Key Matters, Milestones, Requirements, Roles and
Responsibilities, and Queue.
Phase 2.1 Application for High Level Study
Purpose
To submit a HLS application and fees to formally initiate a high level study and secure a spot in the distribution
capacity queue.
Key Matters
(conversation starters)
1. Submission Package
1.1 DER HLS application
1.2 Site Location
1.3 Application Fee
2. Technical Requirements to initiate study
3. Queue entry and basic queue process
4. If a DER customer has a preference of any feeder, it should be mentioned in the DER HLS application
5. Distribution only (Transmission is optional)
Milestones
DER queue is entered once the HLS fee is paid. The high level study fee is $4,000 (+ GST) per site to
complete the distribution high level study. The optional transmission high level study fee is $3,000 (+ GST) per
site.
Customer Requirements
1. Review hosting capacity limits provided within the hosting capacity map and project list.
FortisAlberta Hosting Capacity
2. Submit the High Level Study Application to generation@fortisalberta.com.
3. Ensure the application has all the customer information required, including technical, to ensure the study
can proceed.
FortisAlberta Roles and Responsibilities
SRM presents the customer an option for a kickoff meeting and schedules it with Customer Planning if
requested.
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 6
| DER INTERCONNECTION GUIDE
Queue
FortisAlberta will issue an invoice for the HLS fee after your application is received. Once the HLS fee is paid
and the required technical information is provided to complete the study, the project enters the DER Queue. If
the invoice is not paid by the due date of 30 calendar days or if the appropriate technical information is not
provided, the project will be cancelled.
NOTE: Change of Scope: If a scope change is made by the customer (e.g., change of feeder, change of
location, increase of capacity, changes to the generator type), the project will be removed from the DER
Queue and a new HLS will be required along with applicable fees. If the change of scope does not negatively
impact the completed study results, a new HLS may not be required, and the project may retain the DER
Queue position at FortisAlberta’s sole discretion.
Phase 2.2 High Level Study
Purpose
To provide the customer a high-level assessment of the interconnection requirements at a specific site and a
ballpark cost for interconnection, including high level upgrade options.
Key Matters
(Conversation starters)
1. High Level Study Report results:
1.1 Impact of “zero” load and how it affects export while operating
1.2 Export capacity, feeder minimum load, and power factor – explanation of variations
1.3 Distribution system voltage regulation impacts on a project
1.4 CSA standard voltage limits
1.5 Outages – DERs export on primary feeder studied, not for alternate feeders for load restoration
1.6 Ballpark quote is done without a site check, any underground construction required at the detailed level study phase will require additional upgrades
1.7 Other considerations – fault contribution limits, equipment loading limits, Supply Transmission Service (STS)
2. Detailed Level Study Information package – contents, need for application, etc.
3. Deadline for queue
Milestones
High Level Study phase is complete when the customer signs and returns the high level study letter.
Customer Requirements
1. Review DER-02 FortisAlberta Interconnection Requirements 2. Customer returns HLS letter, signed with accepted HLS alternative indicated
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 7
| DER INTERCONNECTION GUIDE
FortisAlberta Roles and Responsibilities
1. Customer Planning completes HLS based on complete HLS application form and optional customer
meeting.
2. SRM reviews HLS study results and asks if the customer would like a review meeting for the results and
schedules one with Customer Planning if required.
3. Optional transmission HLS: SRM asks if one is desired, and if so, coordinates a scope document to be
created and sent to the transmission facility owner (TFO). SRM sends request and customer collected
payment to the TFO.
Queue
1. After the HLS is completed, FortisAlberta will send the HLS proposal for a review period of 30 calendar
days. FortisAlberta must receive the signed HLS acceptance letter for the location and/or option specified
in the HLS within 30 calendar days or the project will be removed from the DER Queue. Once
FortisAlberta receives the signed HLS acceptance letter, an invoice will be sent for the Detailed
Distribution Study and Transmission System Interconnection Study fees.
2. Any project removed from the DER Queue will have to begin the interconnection process again by
applying for a new HLS with all applicable fees.
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 8
| DER INTERCONNECTION GUIDE
Phase 3 Detailed Level Study (DLS): Applications and Design
Purpose
To initiate and complete detailed studies and design related to the distribution and transmission systems. To
initiate the Alberta Electric System Operator (AESO) Behind the Fence connection process, if required. The
distribution and transmission studies happen in parallel. See phases 3.1, 3.2, 3.3 for Key Matters, Milestones,
Requirements, Roles and Responsibilities.
Queue
Once the High Level Study is received, the customer has reached the first go/no-go point where they may
choose to tweak their project, submit a new HLS application with a revised scope for a new project , or
continue forward with a Detailed Distribution Study application. The Transmission System Interconnection
Study is kicked off concurrent with the Detailed Distribution Study.
Phase 3.1 Application for Distribution Detailed Level Study
Purpose
Submit the Detailed Level Study application and fees to initiate the detailed study activities and hold position in
the distribution queue.
Key Matters
(conversation starters)
1. DLS Application including all required information
2. Application Fees – FortisAlberta, TFO (protection study and power flow study security)
3. Technical Requirements to initiate study
4. See DER-02 FortisAlberta Interconnection Requirements
Milestones
Once a Detailed Level Study application and payment are received, the detailed level study will commence.
The detailed level study fee is $10,000 (+ GST) for projects that do not require an AESO Behind the Fence
(BTF) project, and an additional $10,000 (+ GST) when there is an AESO Behind the Fence (BTF) project
involved.
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 9
| DER INTERCONNECTION GUIDE
Customer Requirements
1. Customer to provide a completed DLS Application including site plan, estimated generator and
transformer impedance details, and details for all supplemental grounding devices required. The
application will be delayed if the form is not filled out completely.
Note: Where FortisAlberta system data is required for engineering studies, sections may be excluded for
the initial submission.
2. Preliminary results for the following studies are required to start the protection assessment phase of the detailed level study.
▪ Effective Grounding (if applicable, see DER-02B)
▪ Short Circuit
3. Customer to provide a detailed SLD, authenticated by a professional engineer accredited with APEGA.
FortisAlberta Roles and Responsibilities
Contracts Analyst sends the DLS invoice.
Queue
FortisAlberta will advance the project to the Detail Distribution Study and Transmission System
Interconnection Study phase upon full payment of the applicable fees and submission of the Detailed Level
Study application within 30 calendar days or the project will be removed from the DER Queue.
Phase 3.2 Distribution Detailed Level Study and Design
Purpose
To complete detailed studies and design related to the distribution system.
Key Matters
(conversation starters)
1. Technical Requirements to complete Proposal
1.1 Short Circuit Study
1.2 Effective Grounding Study
1.3 Self-Excitation Study (If Applicable)
Milestones
FortisAlberta will provide a distribution interconnection cost to review.
Customer Requirements
Customer to provide updated SLD and required distribution protection/grounding studies.
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 10
| DER INTERCONNECTION GUIDE
FortisAlberta Roles and Responsibilities
1. SRM schedules and chairs a meeting with the customer, Customer Planning, Protection & Control, and
Operations Planning to verify technical requirements of the project and hand off the project to Operations
Planning for the AESO BTF process.
2. Customer Planning and Protection & Control complete all detailed distribution studies.
3. SRM engages the construction Project Manager.
4. Customer Connections provides the distribution detailed study results and cost as an information package.
Queue
The customer can decide to withdraw the project based on the distribution cost; in which case the project is
removed from FortisAlberta’s DER Queue.
Phase 3.3 Transmission Detailed Study and Design
Purpose
To complete detailed studies and design related to the transmission system. On behalf of the customer,
FortisAlberta to submit application to the AESO to initiate a Behind the Fence (BTF) Connection project and
technical scope with fees to the TFO.
Key Matters
(conversation starters)
1. Ensure clearly defined requirements for a System Access Service Request (SASR), Supply Transmission
Service (STS), In-service Date (ISD) and annual MW/h generation
2. TFO scope document requirements
• Clearly defined requirements for transfer trip, protection (reclose block, anti-islanding), load shed
2. TFO – transmission Anti-Islanding Screen or Study
Note: FortisAlberta studies shall be provided in the 110-day package
3. TFO Protection & Control Study is done by the customer or consultant hired by the customer
3. Generator Unit Owner’s Contributions (GUOC) payment
4. System Access Service Agreement (SASA) for STS
5. AESO Behind the Fence (BTF) Process
BTF Process Quick Reference Guide 2021.pdf (aeso.ca)
Milestones
Pay the transmission study fee. The cost varies based on project location and scope and starts at $30,000 (+
GST) for a typical project.
Customer Requirements
Complete AESO / Transmission related studies requirements (if required) for Anti-Islanding.
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 11
| DER INTERCONNECTION GUIDE
FortisAlberta Roles and Responsibilities
1. Customer Planning finalizes the AltaLink scope document
2. Operations Planning submits a System Access Service Request (SASR) to the AESO to initiate BTF
project.
3. Operations Planning coordinates with the customer, TFO, and the AESO to complete all deliverables of the
AESO BTF Process.
4. Customer Connections coordinates invoicing of the customer and payment to the TFO.
5. Transmission scope of work and estimate are generated at the end of the AESO BTF Stage 3/4.
Queue
1. If the project requires any transmission system upgrades, it is entered into the AESO Behind the Fence
(BTF) gating process. Typically, this Phase for the Transmission System Interconnection Study takes 32 to
36 weeks and FortisAlberta will maintain the project queue position during this time.
a. During this stage, the AESO applies its own queue management practices and requirements for
projects. Failure to meet these required timelines can result in removal from the AESO queue.
Projects that are removed from the AESO Connection Queue will subsequently be removed from
the FortisAlberta DER Queue. Proponents can find detailed information on the AESO connection
process here, Connecting to the grid » AESO.
2. With the introduction of the AESO’s Stage 2 On Hold option, the project can be paused to allow the
customer to re-assess current conditions and the project’s continued viability. During the time the project is
using the AESO ‘On Hold’ option, the project is essentially parked, and other projects can now use the
Transmission capacity previously considered for your project. Selecting to place the project to the AESO’s
On Hold option will also park the project in FortisAlberta’s DER Queue.
3. The DER Queue position is not held while the project is On Hold. Projects that are placed On Hold during
Stage 2 in the AESO Connection Queue will be allowed to be put On Hold in FortisAlberta’s DER Queue
but subject to the same consequences of other projects advancing while the project is On Hold.
4. When the customer decides to restart their project, FortisAlberta will review any change(s) to the
FortisAlberta DER Queue and provide an update to the customer of the impact of restarting the project and
any new study requirements that may be required and/or the impact of DER Queue change(s). The
customer will then need to meet these new requirements and accepts the risk that the project parameters
may no longer be viable when the project is restarted.
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 12
| DER INTERCONNECTION GUIDE
Phase 4 Interconnection Proposal
Purpose
To provide the customer with a complete interconnection proposal, including all distribution and transmission
costs and construction requirements for their consideration.
Key Matters
(conversation starters)
1. Explanation of Proposal contents:
1.1 Detailed Level Study Report
1.2 Construction scope
1.3 Fees to move to Construction
1.4 TFO proposal
2. Changes from DER Owner would mean a new detailed study
Milestones
1. Distribution Detailed Level Study and Transmission System Interconnection Study are complete.
2. FortisAlberta will provide the customer with a Final Interconnection Proposal that outlines the final cost
for distribution and transmission infrastructure upgrades that are required to interconnect the project
(detail distribution interconnection cost, pre-paid Operating and Maintenance (O&M) cost and
Transmission Facility Owner (TFO) Proposal to Provide Service (PPS) costs). The proposal will also
specify the final technical requirements.
3. Construction is initiated upon customer acceptance and payment of all costs.
Customer Requirements
Review Interconnection Proposal and accept proposal.
FortisAlberta Roles and Responsibilities
Customer Connections compiles distribution scope & estimate, transmission scope & estimate, and virtual load
service estimate into a complete interconnection proposal.
Queue
1. FortisAlberta must receive the signed Quote Letter within 30 calendar days or the project is cancelled and
removed from the DER Queue.
2. Once the signed Quote Letter is received, FortisAlberta will send the construction invoices for the full
construction cost, Transmission, Distribution, O&M, and the administration fee.
3. FortisAlberta must receive the payment within 30 calendar days to advance the project to the construction
stage. If the full payment is not received by the invoice due date, the project will be removed from the DER
Queue.
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 13
| DER INTERCONNECTION GUIDE
Phase 5 Construction
Purpose
To initiate and complete all construction and commissioning required for the interconnection. See phases 5.1,
5.2, 5.3 for Milestones, Requirements, Roles and Responsibilities.
Key Matters
(conversation starters)
110-day, 30-day, commission checklists
Queue
Queue position maintained once the construction invoices are paid.
Phase 5.1 Pre-Construction
Purpose
To schedule and initiate construction and commissioning activities and draft formal agreements.
Key Matters
(conversation starters)
1. Customer should have Engineering studies by now ready to share (aligned with 110-day checklist)
2. Project Manager assigned and coordinating – to provide construction schedule
3. FortisAlberta Detailed study validation – communicate recalculation of power factor (p.f.) for full generator
size, then maximum generation export at unity (100% p.f.) for DER operations
4. Agreements/documents shared with the customer – (Interconnection Agreement, Operating Procedure,
Remote Trip Agreement (RTA), AESO energization Package deliverables Energization-Package-
Requirements-v6.pdf (aeso.ca), FortisAlberta DER Interconnection Checklist, DER-02 FortisAlberta
Interconnection Requirements, connection authorization form)
5. Identify risks that put a project that may delay project interconnection
6. Supervisory Control and Data Acquisition (SCADA) process – SCADA Junction Box (pick up from area
office, installation directions), DNP3 map points list location/approval, concentrator bench test report,
protection device/SCADA commissioning
Milestones
110-day checklist completion.
Customer Requirements
1. Complete the 110-day checklist with FortisAlberta and submit the 110-day package.
2. Point of Common Coupling (PCC) must be clearly defined at customer site.
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 14
| DER INTERCONNECTION GUIDE
FortisAlberta Roles and Responsibilities
1. Engineering, Project Manager, and Operations engage with the customer to define the final requirements
for interconnection, construction, and commissioning.
2. Customer Connections coordinates with the TFO to have the required funding in place.
3. Contracts Analyst will work with the customer to finalize the Interconnection Agreement and Operating
Agreements.
Queue
Queue position maintained once the construction invoices are paid.
Phase 5.2 Construction
Purpose
To complete all construction activities and energize customer site load.
Key Matters
(conversation starters)
1. 30-day checklist
2. Energization of site, providing power (not export generation, that is at the in-service date in a later phase)
3. Pre-commissioning
Milestones
30-day checklist completion.
Customer Requirements
Customer to complete the 30-day checklist with FortisAlberta and submit the 30-Day package.
FortisAlberta Roles and Responsibilities
1. FortisAlberta Project Manager completes distribution construction and connection of DER and engages
Operations and Field Technical Services for final interconnection and anticipate commissioning.
2. Operations Planning works with the AESO, TFO and the customer to complete required transmission
upgrades and meet all AESO BTF stage 5 requirements. Operational Planning, Protection & Control, and
SCADA coordinate with the customer to ensure all required studies are completed and accepted, and
commission DER with Field Technical Services.
3. Contracts Analyst coordinates ESA, Interconnection Agreement, and Operating Procedures sign-off with
customer.
Queue
Queue position maintained once the construction invoices are paid.
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 15
| DER INTERCONNECTION GUIDE
Phase 5.3 Commission
Purpose
To complete all commissioning activities required for power export. To complete the execution of formal
agreements. To establish relationship and expectations between the customer Operator-in-Charge (OIC),
Field Operations, and FortisAlberta Control Centre (FCC).
Key Matters
(conversation starters)
1. Commissioning checklist
1.1 Protection settings
1.2 SCADA points list and bench test report completed
2. Post-commissioning checklist
Milestones
Commission checklist completion.
Customer Requirements
1. Customer to complete the commissioning checklist with FortisAlberta
2. Submit Final Commissioning Report to FortisAlberta (IPSC Section 2)
FortisAlberta Roles and Responsibilities
1. Protection and Control to review all requirements.
2. Contracts Analyst to execute agreements.
3. FCC and Field Operations to communicate expectations.
Queue
No queue position, final stages of the project.
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 16
| DER INTERCONNECTION GUIDE
Phase 6 Operate
Purpose
To enable the export of power from the customer site. To maintain an effective (active and current) on-going
customer relationship.
Key Matters
(conversation starters)
1. Operating procedures and responsibilities confirmed
2. Annual requirements
2.1 Annual maintenance form from the customer
2.2 Operator-in-Charge information kept current
Milestones
1. Post-commission checklist complete.
2. As-built Drawings
3. Ongoing annual maintenance updates from the customer
4. Ongoing Operator-in-Charge (OIC) updates from the customer as required
Customer Requirements
1. Customer to complete the post commissioning checklist with FortisAlberta
2. Submit Power Quality Benchmark Report to FortisAlberta for review and approval.
3. Submit all as-builts
4. Comply with current industry standards.
FortisAlberta Roles and Responsibilities
Engineering revises standards with updates in the industry, codes, and external standards.
Queue
No queue position.
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 17
| DER INTERCONNECTION GUIDE
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 18
| DER INTERCONNECTION GUIDE
B1. Phase 1 Pre-Application Consultation
B2. Phase 2.1 Application for High Level Study
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 19
| DER INTERCONNECTION GUIDE
B3. Phase 2.2 High Level Study
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 20
| DER INTERCONNECTION GUIDE
B4. Phase 3.1 Application for Detailed Level Study
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 21
| DER INTERCONNECTION GUIDE
B5. Phase 3.2 Distribution Detailed Level Study and Design
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 22
| DER INTERCONNECTION GUIDE
B6. Phase 3.3 Transmission Detailed Study and Design
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 23
| DER INTERCONNECTION GUIDE
B7. Phase 3.3.0 AESO Behind the Fence Stage 0
B8. Phase 3.3.1 AESO Behind the Fence Stage 1
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 24
| DER INTERCONNECTION GUIDE
B9. Phase 3.3.2 AESO Behind the Fence Stage 2
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 25
| DER INTERCONNECTION GUIDE
B10. Phase 3.4.3/4 AESO Behind the Fence Stage 3 & 4
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 26
| DER INTERCONNECTION GUIDE
B11. Phase 4 Interconnection Proposal
B12. Phase 5.1 Pre-Construction
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 27
| DER INTERCONNECTION GUIDE
B13. Phase 5.2 Construction
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 28
| DER INTERCONNECTION GUIDE
B14. Phase 5.2.1 AESO Behind the Fence Stage 5
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 29
| DER INTERCONNECTION GUIDE
B15. Phase 5.3 Commission
B16. Phase 5.3.1 AESO Behind the Fence Stage 6
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 30
| DER INTERCONNECTION GUIDE
B17. Phase 6 Operate
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 31
| DER INTERCONNECTION GUIDE
Distributed Generation Library | FortisAlberta
FortisAlberta Customer Generator Options
DER Pre-application Form
Third-Party Authorization Distributed Generation
High Level Study Application in Distributed Generation Library | FortisAlberta
Detailed Level Study Application in Distributed Generation Library | FortisAlberta
DER-02 FortisAlberta Interconnection Requirements
FortisAlberta Interconnection Document Requirements
FortisAlberta DER Interconnection Checklist
Interconnection Protection Settings and Commissioning (IPSC)
Sample – Interconnection Protection Settings and Commissioning (IPSC)
Maintenance Verification Report
Sample – Maintenance Verification Report
Option M – Distributed Generation Charges and Credits
DER IFC Data Requirements
As-Built Generator Parameters
FortisAlberta Engineering Study Requirements
FortisAlberta Effective Grounding Study Requirements
Alberta Electric System Operator (AESO)
Connecting to the grid » AESO
https://www.aeso.ca/assets/DER-Ride-Through-Performance-Recommendations.pdf
Copyright © 2021 FortisAlberta. All rights reserved. No modifications or reproductions are allowed without written permission.
October 2021 Version 1 Printed on Nov. 16, 2021 Page 32
| DER INTERCONNECTION GUIDE
FortisAlberta DER: Distributed Energy Resources (DGs, MGs, etc. connecting to the distribution system) DG: Distributed Generation MG: Micro-Generation DLS: Detailed Level Study Energize: power to site ESA: Electrical Service Agreement
FCC: FortisAlberta Control Centre HLS: High Level Study IA: Interconnection Agreement with Operating Procedures agreement ISD: In-Service Date (DER exporting onto FortisAlberta system)
OIC: Operator-in-Charge OP: Operating Procedures PCC: Point of Common Coupling P&C: Protection and Control SCADA: Supervisory Control and Data Acquisition SSG: Small Scale Generation TFO: Transmission Facility Owner Alberta Electric System Operator (AESO)
AESO Acronym list: Behind the Fence (BTF) Process » AESO
BTF: Behind the Fence
EC: Energization Checklist ESR: Engineering Study Report FS: Functional Specification GUOC: Generator Unit Owner Contribution MARP: Maximum Authorized Real Power PDUP: Project Data Update Package SAS: System Access Service SASA: System Access Service Agreement SASR: System Access Service Request STS: Supply Transmission Service
Transmission Facility Owner (TFO) PPS: Proposal to Provide Service (costs for approval) SOW: Scope of Work